Policy, Projects and Resources Committee, Tuesday 20 June 2017 at 7.00pm

Leisure Strategy

Agreed Committee 1 paper

Policy, Projects and Resources Committee agreed this item on Tuesday 20 June 2017. Below is the council's own wording, with the papers it was decided on.

Item42

Resolved

RESOLVED 1. That Members agree to adopt the following phased approach to the delivery of the Leisure Strategy: · Phase 1 – King Georges Playing Fields and Warley Playing Fields · Phase 2 - Play areas, open spaces and options for ongoing maintenance and halls management · Phase 3 – Brentwood Centre and provision for sport across the borough 2. That the Corporate Projects Scrutiny Committee review the in accordance with the scope as set out in Item No.12 on this agenda and make recommendations to the Community, Health and Housing Committee. Reasons for Recommendation As part of the Council’s due diligence in delivering a successful Leisure Strategy, opportunities for income generation will be explored as part of the process. Comments received from Sport England as part of the Local Development Plan consultation, stated that a is required that assesses Council owned sports and leisure facilities in order that the Council can continue to work with partners to ensure that appropriate provision is made for the residents of Brentwood. The strategy should not only consider how the Council can provide services, but also how other partners can. The strategy should also use current sports facility evidence to identify strategic priorities to then inform what will be included in the Council’s Infrastructure Delivery Plan. Following this feasibility work, the Council will then be able to determine which projects will be funded by the Community Infrastructure Levy (CIL) and those funded by planning obligations. The Council’s Asset Management Strategy also sets out the need to maximise income where possible from its asset portfolio.
Word for word from the decision Brentwood published for this meeting. Source: brentwood.moderngov.co.uk

Follow this further

Built from Brentwood's papers

What the report saysPro

Report to Policy, Projects and Resources Committee

Executive summary

1.1It was agreed by Members at the 5 December 2016, Community, Health and Leisure Committee (min ref.207) that the Council commissioned a report to be undertaken by 4Global to review the Value for Money options and appraisal of the Council leisure facilities which. The leisure facilities include the Brentwood Centre, six community halls, Hartswood Golf Course and the Council’s play areas.

1.2It is proposed to adopt a three-phased approach to deliver the Leisure Strategy and that the Community, Health and Housing Committee will be tasked with the delivery of the strategy. It is also proposed that the Corporate Projects Scrutiny Committee will look at each of the phases at the appropriate time and that this will be added to the Committee’s work programme for 2017/18.

1.3There is a separate report at Item 12 of this agenda which will request the Corporate Projects Scrutiny Committee to review other corporate projects including the Leisure Strategy.

Recommendations

2.1That Members agree to adopt the following phased approach to the delivery of the Leisure Strategy:

Phase 1 – King Georges Playing Fields and Warley Playing Fields Phase 2 - Play areas, open spaces and options for ongoing maintenance and halls management Phase 3 – Brentwood Centre and provision for sport across the borough

2.2That the Corporate Projects Scrutiny Committee review the Leisure Strategy in accordance with the scope as set out in Item No.12 on this agenda and make recommendations to the Community, Health and Housing Committee. 3 Introduction and Background

3.1Working in conjunction with the Local Development Plan the Leisure Strategy will identify the future provision required in Brentwood to meet the needs of the residents.

3.2In order to ascertain the true running costs of the Council’s leisure facilities, it commissioned a value for money review and options appraisal of the its facilities which included the Brentwood Centre, six community halls (currently managed by Brentwood Leisure Trust), Hartswood Golf Course and the Council’s play areas.

3.34Global were appointed in 2016 to undertake this piece of work and this was completed in November 2016.

3.4A subsequent soft market testing exercise was also undertaken to further inform the discussion, particularly around any decisions to re-procure operational management, which could potentially realize some capital investment into the Council’s leisure facilities.

4 Issues, Options and Analysis of Options

4.1The Leisure Strategy is one of the key strategies as set out in the Vision for Brentwood 2016-19 document. In order to deliver a successful Leisure Strategy, Members and officers need to have a complete picture of the cost of the current provision, how it measures in value for money terms, the future options available to them, together with any risk profiles associated with its leisure facilities.

4.2The key decision for Brentwood Borough Council is how to best provide the level of leisure provision for both current and future Brentwood residents, bearing in mind that it has existing but ageing facilities and the future development pressures.

4.3The consultant’s report has set out a number of possible options in respect of the Brentwood Centre, the community halls, Hartswood Golf Course and the Council’s play areas. It also set out other possible operational management and procurement options that could be available to the Council. 4.4 The existing lease arrangements between Brentwood Leisure Trust and Brentwood Leisure Trading Limited will continue for six months (until December 2017) in relation to the Grant and Service Level agreement and the leases for the six community halls whilst officers explore other operational management options for the halls.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Leisure StrategyReport 98 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 24 attended
ML
Councillor Mrs Louise McKinlayChair, present
JK
Councillor John KerslakeVice-Chair, present
GB
Councillor Gareth BarrettCommittee Member, present
PF
Councillor Paul FaragherCommittee Member, present
CH
Councillor Chris HossackCommittee Member, present
RK
Councillor Roger KeebleCommittee Member, present
DK
Councillor David KendallCommittee Member, present
PM
Councillor Philip MynottCommittee Member, present
KP
Councillor Keith ParkerCommittee Member, present
PB
Councillor Paul BarrellCommittee Member, in attendance
RH
Councillor Roger HirstCommittee Member, in attendance
MJ
Councillor Mrs Jill HubbardCommittee Member, in attendance

All 24 on the meeting page

On this subject at Brentwood

Search all
  1. Leisure StrategyThis decision
  2. Leisure Procurement StrategyAgreed
  3. Leisure Strategy Action PlanAgreed
  4. Leisure Strategy RefreshAgreed
  5. Leisure Strategy Review and Action PlanNoted
  6. Leisure Strategy Action PlanAgreed

More from Brentwood Policy, Projects and Resources Committee

All decisions
MeetingDecisionOutcome
18 Sep 2018 2018/19 General Fund Revenue, Housing Revenue Account, Capital Budget Monitoring and Treasury Activity UpdateRESOLVED UNANIMOUSLY: 1. To agree the projected outturn position for 2018/19 of the Council’s General Fund Revenue bu... Agreed Open
18 Sep 2018 Department for Communities and Local Government (MHCLG) Pilot Programme for 75% Business Rates Retention - 2019/20RESOLVED UNANIMOUSLY: 1. Members note the content of the report and its potential implications for the forthcoming bu... Agreed Open
18 Sep 2018 Asset Development Programme UpdateTo approve the direction of the Asset Development Programme. Reason for the Recommendation To update the Committee on... Approved Open
18 Sep 2018 Feasibility Study for Parking on Housing GreensRESOLVED UNANIMOUSLY: 1. To instruct officers to identify possible sites for parking on Housing Greens and undertake ... Decided Open
18 Sep 2018 Leisure StrategyThat Members agree the and action plan at Appendix A. Reasons for Recommendation As part of the Council’s due diligen... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies