Policy, Projects and Resources Committee agreed this item on Tuesday 20 June 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED 1. That Members agree the list of Corporate Projects including scoping and timescales, as set out in Appendix A, are put forward for scrutiny. 2. That the Scrutiny Committee are requested to consider the as set in Appendix A and report back to the appropriate committee. Reason for Recommendation To ensure that the Corporate Plan 2016-2019 is supported by projects that deliver the necessary change.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
Report to Policy, Projects and Resources Committee
Executive summary
1.1Members will be aware of the key Corporate Projects that have been reported regularly to the appropriate committee of the council.
1.2At Annual Council it was agreed that the introduction of the Corporate Projects Scrutiny Committee would focus and scrutinise these key projects to ensure transparency, delivery and lessons learnt.
1.3Set out at Item No. 11 of this agenda is the proposed approach for the Leisure Strategy.
1.4This report includes the approach for the review of the Leisure Strategy and other Corporate Projects by the Corporate Projects Scrutiny Committee.
Recommendation
2.1That Members agree the list of Corporate Projects including scoping and timescales, as set out in Appendix A, are put forward for scrutiny. 2.2 That the Corporate Projects Scrutiny Committee are requested to consider the Corporate Projects as set in Appendix A and report back to the appropriate committee.
3. Introduction and Background
3.1The key corporate projects have previously been reported to the appropriate committee on their progress of the projects to date and upcoming actions. 3.2 The projects as set out in Appendix A are required to be scrutinised to ensure they meet the needs and objectives of the Corporate Plan.
3.3The projects will have interdependencies with other council projects and strategies that could have an effect on proposed timelines. In addition proposed timelines may alter as a results of options and decisions taken.
Reasons for recommendation
4.1To ensure that the Corporate Plan 2016-2019 is supported by projects that deliver the necessary change.
Consultation
5.1Not appropriate at this stage
6. References to Corporate Plan
6.1A Modern Council transforming its services to improve efficiencies and economies through new ways of working.
7. Implications
Financial Implications Name & Title: John Chance, Section 151 Officer Tel & Email [email protected] Tel 01277 312712
7.1These will be fully evaluated as part of the business case process
Legal Implications Name & Title: Daniel Toohey, Monitoring Officer Tel & Email [email protected] Tel 01277 312860
7.2The legal implications in respect of service level agreements etc. will need to be considered in detail should this option be progressed.
Other Implications (where significant) – i.e. Health and Safety, Asset Management, Equality and Diversity, Risk Management, Section 17 – Crime & Disorder, Sustainability, ICT.
7.3These will all be addressed should the option be progressed.
Background papers
8.1None at this stage 9. Appendices to this report Appendix A
Follow Policy, Projects and Resources Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Asset Development Programme UpdateTo approve the direction of the Asset Development Programme. Reason for the Recommendation To update the Committee on...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.