CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bridgend County Borough Council
Development Control Committee, Thursday 11 June 2015

P/15/203/FUL - Glynogwr Lodge Glynogwr Bridgend - Erect 2 No. Log Cabin Holiday Units for motor bike walking and Countryside pursuits

Decided Planning 1 paper

Development Control Committee decided this item on Thursday 11 June 2015. Below is the council's own wording, with the papers it was decided on.

Item572

Resolved

That the following planning application be granted, subject to the conditions contained in the report of the Corporate Director – Communities. Code No. Proposal P/15/203/FUL Glynogwr Lodge Glynogwr Bridgend - Erect 2 No. Log Cabin Holiday Units for motor bike walking and Countryside pursuits
Word for word from the decision Bridgend published for this meeting. Source: democratic.bridgend.gov.uk

Follow this further

Built from Bridgend's papers

What the report saysPro

Report to Development Control Committee

RECOMMENDATION : GRANT WITH CONDITIONS

REFERENCE: P/15/203/FUL APPLICANT: MR DAVID WILLIAMS GLYNOGWR LODGE TY PENTWYN GLYNOGWR BRIDGEND

LOCATION: GLYNOGWR LODGE TY PENTWYN GLYNOGWR BRIDGEND

PROPOSAL: ERECT 2NO. LOG CABIN HOLIDAY UNITS FOR MOUNTAIN BIKE / WALKING AND GENERAL COUNTRYSIDE PURSUITS

RECEIVED: 25th March 2015

SITE INSPECTED: 15th April 2015

APPLICATION/SITE DESCRIPTION

The application proposes the erection of 2 detached three bedroom log cabins for mountain biking/walking and general countryside pursuit tourist accommodation. The proposed development is intended to be ancillary to the existing tourist accommodation at Glynogwr Lodge, which is a four bedroom (8 person) self catering establishment. In addition, the submitted plans show revised access arrangements into the site with the existing easterly access blocked up and a new wider centrally located access created to serve both the existing property, existing tourist lodge and the proposed development.

The cabins are to be sited just over 7m south of the northern site boundary to the rear of the properties known as Windmill House and Ty Maes Y Deri. One of the cabins will be positioned approximately 5.5m (at its nearest point) from the eastern site boundary with the Cemetery. Both of the structures will measure 13m long by 6.3m wide with a ridged roof reaching 3.2m in height. A roof canopy 1500mm will project from the southern elevation of the property over a timber decked area projecting a further 2.5m to the south of the cabin and 2m wider than the cabin. Internally the cabins will provide an open kitchen/dining/lounge area with three bedrooms, bathroom and utility. Photographs have been supplied showing the exterior of these buildings to be horizontally clad with timber logs with a felt type covering over the roof. The second cabin will be sited 10.5m to the west of the first cabin and be separated from it by a 4m wide vehicular driveway and turfed areas either side of the driveway. A courtyard area to be used for parking/turning purposes is shown to the west of the proposed cabins. This area measures 20m wide.

In the Design and Access Statement, which accompanies the submission, the applicant's agent considers that:-

14. The proposal is seeking to retain the character of the immediate area as a low density residential area with the development ensuring reasonable space remains in the development area following the erection of the log cabins and the upgrading of the associated building. In addition, the sloping nature of the site ensures that the log cabins are situated at a significantly lower level than the existing residential properties so that there will be no adverse effect on residential amenity.

15. The boundaries consist of stock proof fencing to the majority of the site and timber fencing between the development site and the residential properties to the northern boundary, which will remain in situ. RELEVANT HISTORY

P/14/677/FUL REFUSED 03-02-2015 ERECT 2NO. LOG CABIN HOLIDAY UNITS FOR EQUINE AND/OR MOUNTAIN BIKE HOLIDAY LETS & UPGRADE EXISTING STABLE For information, the reasons for refusal in respect of the earlier application were as follows:-

1. The proposed development will generate additional vehicular turning movements to or from the public highway at the substandard access, creating further traffic hazards to the detriment of highway safety. 2. Insufficient details of the associated building identified to be used for stables/storage of mountain bikes in connection with the tourist accommodation have been submitted to enable the implications of the proposal on the viability and amenity of neighbouring uses and their users/occupiers to be properly evaluated by the Local Planning Authority.

PUBLICITY

The application has been advertised on site. Neighbours have been notified of the receipt of the application. The period allowed for response to consultations/publicity expired on 8 May 2015.

NEGOTIATIONS

None

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P/15/203/FUL: Glynogwr Lodge Glynogwr Bridgend: Erect 2 No. Log Cabin Holiday Units for motor bike walking and Countryside pursuitsReport 917 KB DownloadRead as text

At this meeting

Whole meeting
564Site VisitsDecided 565Approval of MinutesApproved 568Amendment SheetOn the agenda 569P/15/183/FUL - The White House Briary Way Brackla - Change of use of dwelling to Res. Care Home & 2 Storey Ext.Decided 570P/14/800/FUL - Fmr Council Office Site Glanogwr Road Bridgend - Demolish Council offices and erect 3. No. 4 Detached houses with garagesDecided 571P/14/711/FUL - Former Bryncethin Nurseries & S Wales Wood Recycling Pant Hirwaun Heol-Y-Cyw - C/U Former Nursery and dwelling & Vehicle Storage new buildings Access Wood fuelled Boilers & Wood drying facilityDeferred
572P/15/203/FUL - Glynogwr Lodge Glynogwr Bridgend - Erect 2 No. Log Cabin Holiday Units for motor bike walking and Countryside pursuitsThis decision
573P/15/25/FUL - Playing Field at Heol Ysgol Bryn Castell Llangewydd Road Bryntirion - Erection of 67 dwellings new Access Car Parking Open Space Landscaping & Associated worksDeferred 574P/14/543/FUL - Land north Brynheulog Caerau Park Maesteg - 5.1M Solar array with Inverter stations Switchgear Cabins Fencing CCTV & AccessRefused 575P/14/742/OUT - Land north of Abergarw Farm Brynmenyn - Provision of 26 Building Plots and Access Road and Remove Modern type barnAgreed 576P/14/464/OUT - Land east of A4061 (BNDR) Coity - Outline application for 220 dwellingsAgreed 577P/14/824/RES - Island Farm Inst. of Sport Island Farm Bridgend - Res. Matters Highway Infrastructure Green Bridge and Drainage InfrastructureApproved 578P/15/125/FUL - 41 Merthymawr Road Bridgend - Retention of fence to Front/Side of PropertyApproved 579P/15/55/FUL - New Street Surgery Aberkenfig - Change of Use of No. 1 New Street to form Larger Surgery & 2 Storey Ext. with rear Parking SpaceDecided 580P/15/230/BCB - Caretakers School House Merlin Crescent Cefn Glas - Create New pedestrian & Vehicular access to Dwelling and New close Boarded timber Boundary FenceDecided 581AppealsNoted 582Review of Old Mineral Planning Consents (ROMP) Cornelly QuarriesNoted 583Training LogNoted 584Development Control Committee Site Visit PanelDecided 585Nomination and Appointment to the Rights of Way Sub-CommitteeDecided

Who was there

15 of 34 attended
NC
Councillor Norah ClarkeCommittee Member, present
SD
Sarah DanielCommittee Clerk, in attendance
PD
Councillor Pam DaviesCommittee Member, present
WD
Councillor Wyn Davies MBECommittee Member, present
GD
Gareth DenningOfficer, in attendance
JD
Jane DessentOfficer, in attendance
CF
Craig FlowerOfficer, in attendance
MG
Mark GalvinCommittee Clerk, in attendance
NG
Nicola GandyOfficer, in attendance
CG
Councillor Cheryl GreenCommittee Member, present
JJ
Julie JenkinsOfficer, in attendance
CJ
Councillor Cherie JonesCommittee Member, present

All 34 on the meeting page

More from Bridgend Development Control Committee

All decisions
MeetingDecisionOutcome
19 Oct 2023 Site VisitsThat a date for any site visits agreed by the Committee or identified in advance of the next meeting by the Chairpers... Agreed Open
19 Oct 2023 Approval of MinutesThat the Minutes of a meeting of the Development Control Committee dated 7 September 2023, be approved as a true and ... Approved Open
19 Oct 2023 Amendment SheetThe was accepted by the Chairperson as an urgent item under Part 4, paragraph 4 of the Council Procedure Rules. Decided Open
19 Oct 2023 Development Control Committee GuidanceThat the report of the Corporate Director – Communities, outlining the be noted. Noted Open
19 Oct 2023 P/23/147/FUL - Rear of 82 Merthyr Mawr Road, Bridgend, CF31 3NSThat the above application be granted, subject to the Conditions contained in the report of the Corporate Director – ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies