Resolved
That the report be noted.
Development Control Committee noted this item on Thursday 11 June 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
REVIEW OF OLD MINERAL PLANNING CONSENTS (ROMP) CORNELLY QUARRIES
Gaens Quarry, Grove Quarry and Cornelly Quarry have an historical consent to operate that pre- dates the modern planning system. They are also subject to an Interim Development Order (IDO) that dates back to the 1940s. Part of the IDO is that the consents are periodically reviewed.
Planning applications were submitted for Gaens Quarry (P/97/85/MIN), Grove Quarry (P/97/618/MIN) and Cornelly Quarry (P/97/623/MIN) for the periodic review of planning conditions. Prior to determination all the applications were called in by the (then) Welsh Office in 1998. The ‘call in’ procedure means that the Mineral Planning Authority (MPA) i.e. Bridgend CBC is no longer the determining body. Instead the application will be determined by the Welsh Ministers.
At the time there was some considerable discussion between the applicants, the MPA and the Welsh Office regarding the need for an environmental impact assessment (EIA). An EIA was eventually submitted in 2003.
A further planning application relating to Cornelly & Grove Quarries for the periodic review of the IDO was submitted in 2009 (P/09/738/MIN) this was also called in by the Welsh Government in 2010.
Further to this Welsh Government issued a scoping direction in 2013, which indicate that a further EIA was required and an environmental statement (ES) was submitted in 2014.
There is no proposal to extend the boundaries of the quarries under these applications.
It is now proposed to hold a Public Inquiry in order to discuss the issues on all the 'called in' applications. The Inquiry will be led by a Planning Inspector, who will prepare a report for consideration by the Welsh Ministers. BCBC will attend and participate in the Inquiry, however it is unlikely that BCBC will be represented by a legal advocate.
BCBC’s position is to examine, review and make comment on the proposed conditions as submitted although it is not in a position to amend or modify conditions regarding the operation of the quarries. Current national planning advice indicates that compensation will be payable if additional or modified conditions are imposed. It is possible that the Inspector could recommend changes to the conditions which could result in liability being put on BCBC.
The main issue in environmental terms is the impact on hydrogeology in relation the nearby Kenfig National Nature Reserve, Special Area of Conservation (SAC) and Site of Special Scientific Interest (SSSI) at Merthyr Mawr. Natural Resources Wales (NRW) will be providing the main input into this issue.
The Inquiry will discuss any issues of disagreement regarding the above and is due to take place in November 2015.
Recommendation That the contents of the report be noted.
MARK SHEPHARD CORPORATE DIRECTOR COMMUNITIES Background Papers See relevant application reference number.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Review of Old Mineral Planning Consents (ROMP) Cornelly QuarriesReport | 22 KB | DownloadRead as text |
Follow Development Control Committee at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Oct 2023 | Site VisitsThat a date for any site visits agreed by the Committee or identified in advance of the next meeting by the Chairpers... | Agreed | Open |
| 19 Oct 2023 | Approval of MinutesThat the Minutes of a meeting of the Development Control Committee dated 7 September 2023, be approved as a true and ... | Approved | Open |
| 19 Oct 2023 | Amendment SheetThe was accepted by the Chairperson as an urgent item under Part 4, paragraph 4 of the Council Procedure Rules. | Decided | Open |
| 19 Oct 2023 | Development Control Committee GuidanceThat the report of the Corporate Director – Communities, outlining the be noted. | Noted | Open |
| 19 Oct 2023 | P/23/147/FUL - Rear of 82 Merthyr Mawr Road, Bridgend, CF31 3NSThat the above application be granted, subject to the Conditions contained in the report of the Corporate Director – ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.