Bridgend County Borough Council
Development Control Committee, Thursday 11 June 2015

P/14/543/FUL - Land north Brynheulog Caerau Park Maesteg - 5.1M Solar array with Inverter stations Switchgear Cabins Fencing CCTV & Access

Refused Planning 1 paper

Development Control Committee refused this item on Thursday 11 June 2015. Below is the council's own wording, with the papers it was decided on.

Item574

Resolved

That the following application be refused for the reasons contained in the report of the Corporate Director – Communities. Code No . Proposal P/14/543/FUL Land north Brynheulog Caerau Park Maesteg - 5.1M Solar array with Inverter stations Switchgear Cabins Fencing CCTV & Access
Word for word from the decision Bridgend published for this meeting. Source: democratic.bridgend.gov.uk

Follow this further

Built from Bridgend's papers

What the report saysPro

Report to Development Control Committee

RECOMMENDATION : REFUSE

REFERENCE: P/14/543/FUL APPLICANT: MARCOL AFAN ENERGY C/O MR ROBERT CURRIE INDUSTRIAL SECURITIES 10 UPPER BERKELEY STREET LONDON

LOCATION: LAND NORTH BRYNHEULOG CAERAU PARK MAESTEG BRIDGEND

PROPOSAL: 5.1MW SOLAR ARRAY WITH INVERTER STATIONS,SWITCHGEAR CABINS,FENCING,CCTV & ACCESS

RECEIVED: 8th August 2014

SITE INSPECTED: 15th August 2014

APPLICATION/SITE DESCRIPTION

The application seeks consent for a solar array with inverter stations, switches gear, cabins, fencing, CCTV and associated access on land north of Brynheulog, Caerau Park, Maesteg.

The application site is located to the north of Bryn Heulog residential estate in Caerau and is bordered to the east by the A4063 (Cymmer Road) which connects the Llynfi and Afan valleys. The site lies on the upper parts of a south-facing hillside close to the head of the Llynfi valley between 250 AOD and 340 AOD. The landcover is primarily felled coniferous plantation, following clearance due to Phyopthera ramorum infection (larch die back). Overall, the site comprises of a highly undulating mixture of convex and concave slopes that are open and prominent at the head of the valley, exposed to the south and to a lesser extent to the east and west.

The revised application proposes the construction of a photovoltaic (PV) solar array covering area 10.31 hectares (opposed to the original 30.41 hectares) and includes approximately 26,000 solar panels, inverter stations, Distribution Network Operator (DNO) switchgear cabins, security fencing, CCTV and access. A description of each of these components is provided below.

SOLAR PANELS The proposed development comprises an array of freestanding solar PV panels with an overall generating capacity of 5.1 MW of renewable energy (reduced from 18.4 MW). The solar panels are designed to absorb sunlight and maximise electricity generation while minimising reflection and glare. The panels will be inclined to 25 degrees with the lowest part of the table approximately 0.6 metres above ground and the highest point 2 metres above ground. The surface of each solar panel will be constructed from toughened glass beneath which is a non- reflective layer, electrical connections, silicon and a backing layer. All of these are set in an aluminium frame.

The solar panels will be mounted on a framework, which will be arranged in rows facing south to maximise sunlight exposure. Each row will vary in length depending on the site topography. The AC current generated by the solar panels will be transferred through suspended cables, which will be located to the rear of the panels. The framework will be mounted on galvanised steel posts secured into the ground by steel piles.

INVERTER STATIONS In order to convert the direct current (DC) electricity generated by the solar panels to alternating current (AC) suitable for distribution into the local electrical distribution network, 5 inverter stations are positioned at strategic locations throughout the solar array. The inverter stations will be 8.6 metres long, 2.6 metres wide and 3.15 metres high. The cabins are typically clad in aluminium in a colour selected to suit the local surroundings.

DNO SWITCHGEAR Two DNO switchgear cabins containing electrical switchgear for the Local Electricity Distribution Network Operator (DNO) will be required. The cabins will be 6 metres long, 2.55 metres wide and 2.8 metres high. They will be set on a concrete base 6.3m long, 2.7m wide and 0.3m high.

SECURITY FENCE AND CCTV A perimeter fence will be erected around the outside of the site, set back from the solar panels by approximately 4 metres to avoid shading. The fencing will be 2.5 metres high and each panel section will be set between posts to achieve a width of 2.5 metres. A double leaf gate of the same height with a width of 4 metres will service the entrance to the solar park. The fencing will be a wire meld mesh, typically green in colour.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P/14/543/FUL: Land north Brynheulog Caerau Park Maesteg: 5.1M Solar array with Inverter stations Switchgear Cabins Fencing CCTV & AccessReport 6.4 MB DownloadRead as text

At this meeting

Whole meeting
564Site VisitsDecided 565Approval of MinutesApproved 568Amendment SheetOn the agenda 569P/15/183/FUL - The White House Briary Way Brackla - Change of use of dwelling to Res. Care Home & 2 Storey Ext.Decided 570P/14/800/FUL - Fmr Council Office Site Glanogwr Road Bridgend - Demolish Council offices and erect 3. No. 4 Detached houses with garagesDecided 571P/14/711/FUL - Former Bryncethin Nurseries & S Wales Wood Recycling Pant Hirwaun Heol-Y-Cyw - C/U Former Nursery and dwelling & Vehicle Storage new buildings Access Wood fuelled Boilers & Wood drying facilityDeferred 572P/15/203/FUL - Glynogwr Lodge Glynogwr Bridgend - Erect 2 No. Log Cabin Holiday Units for motor bike walking and Countryside pursuitsDecided 573P/15/25/FUL - Playing Field at Heol Ysgol Bryn Castell Llangewydd Road Bryntirion - Erection of 67 dwellings new Access Car Parking Open Space Landscaping & Associated worksDeferred
574P/14/543/FUL - Land north Brynheulog Caerau Park Maesteg - 5.1M Solar array with Inverter stations Switchgear Cabins Fencing CCTV & AccessThis decision
575P/14/742/OUT - Land north of Abergarw Farm Brynmenyn - Provision of 26 Building Plots and Access Road and Remove Modern type barnAgreed 576P/14/464/OUT - Land east of A4061 (BNDR) Coity - Outline application for 220 dwellingsAgreed 577P/14/824/RES - Island Farm Inst. of Sport Island Farm Bridgend - Res. Matters Highway Infrastructure Green Bridge and Drainage InfrastructureApproved 578P/15/125/FUL - 41 Merthymawr Road Bridgend - Retention of fence to Front/Side of PropertyApproved 579P/15/55/FUL - New Street Surgery Aberkenfig - Change of Use of No. 1 New Street to form Larger Surgery & 2 Storey Ext. with rear Parking SpaceDecided 580P/15/230/BCB - Caretakers School House Merlin Crescent Cefn Glas - Create New pedestrian & Vehicular access to Dwelling and New close Boarded timber Boundary FenceDecided 581AppealsNoted 582Review of Old Mineral Planning Consents (ROMP) Cornelly QuarriesNoted 583Training LogNoted 584Development Control Committee Site Visit PanelDecided 585Nomination and Appointment to the Rights of Way Sub-CommitteeDecided

Who was there

15 of 34 attended
NC
Councillor Norah ClarkeCommittee Member, present
SD
Sarah DanielCommittee Clerk, in attendance
PD
Councillor Pam DaviesCommittee Member, present
WD
Councillor Wyn Davies MBECommittee Member, present
GD
Gareth DenningOfficer, in attendance
JD
Jane DessentOfficer, in attendance
CF
Craig FlowerOfficer, in attendance
MG
Mark GalvinCommittee Clerk, in attendance
NG
Nicola GandyOfficer, in attendance
CG
Councillor Cheryl GreenCommittee Member, present
JJ
Julie JenkinsOfficer, in attendance
CJ
Councillor Cherie JonesCommittee Member, present

All 34 on the meeting page

On this subject at Bridgend

Search all
  1. P/14/543/FUL - Land north Brynheulog Caerau Park Maesteg - 5.1M Solar array with Inverter stations Switchgear Cabins Fencing CCTV & AccessThis decision
  2. P/22/716/FUL - Land to the South of Felindre Road, Pencoed, CF35 5HUApproved
  3. P/23/92/FUL - Land South of Former St. Johns School, (North of 22 Bryneglwys Gardens,) Newton, Porthcawl, CF36 5PRApproved
  4. P/23/218/FUL - Land at Brynmenyn and Bryncethin, BridgendAgreed
  5. P/22/756/FUL - Land at Bridgend Police Station & former Cheapside multi- storey car park, Bridgend, CF31 1BZRefused
  6. P/22/484/FUL - Land at Primrose Stables, Old Coachman’s Lane Court Colman, Bridgend, CF31 4NGAgreed

More from Bridgend Development Control Committee

All decisions
MeetingDecisionOutcome
19 Oct 2023 Site VisitsThat a date for any site visits agreed by the Committee or identified in advance of the next meeting by the Chairpers... Agreed Open
19 Oct 2023 Approval of MinutesThat the Minutes of a meeting of the Development Control Committee dated 7 September 2023, be approved as a true and ... Approved Open
19 Oct 2023 Amendment SheetThe was accepted by the Chairperson as an urgent item under Part 4, paragraph 4 of the Council Procedure Rules. Decided Open
19 Oct 2023 Development Control Committee GuidanceThat the report of the Corporate Director – Communities, outlining the be noted. Noted Open
19 Oct 2023 P/23/147/FUL - Rear of 82 Merthyr Mawr Road, Bridgend, CF31 3NSThat the above application be granted, subject to the Conditions contained in the report of the Corporate Director – ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies