MAJOR PROJECTS & REGENERATION TEAM PROJECT UPDATE – January 2013 219 Team Objectives:
The Major Projects & Regeneration Team manages, together with public and private sector partners, the implementation of key regeneration and infrastructure projects that support the city’s economic growth and contribute to the transformation of the city for all, including the development of key employment sites. Successful delivery of these major projects provides new business space and employment opportunities, new homes, and community and leisure facilities. Development can also act as a regenerative catalyst encouraging further investment in the city.
Each of our projects contributes towards a vision of shaping the city by developing and sustaining the economy, preserving and promoting our heritage, growing our cultural offer and improving the quality of life for our residents, visitors and businesses. All projects consider the importance of good urban 220
design and public realm, and also ensure that new development has the minimum possible environmental impact. Generally the projects do not receive direct capital investment from the city council and are dependent upon development partners providing external investment.
The Team:
Richard Davies x6825 Mark Jago x1106 Katharine Pearce x2553 Max Woodford x3451 Joanne Hussey x2705
Project Update for Economic Development & Culture Committee – 10 January 2013 Project Name & Officer Background and current project Impacts & Outputs Current project timetables Description Lead status and milestones Black Rock Director: Policy & Resources Committee on The final longer term objectives for Cross party Project Board set Geoff Raw 12 July 2012 agreed with the this site will be considered in the up: April 2012. New procurement recommendation of the Black Rock context of their full financial, exercise to start in 2013 Project Project Board to end the legal economic, social and Temporary uses taken to following research and Mgr: agreement with the previous environmental impact. Project Board: 4th October feasibility work with the Katharine developer of the Black Rock Site 2012. Project Board to agree Pearce (Brighton International Arena Ltd). procurement route and (permanent EDCC approval to negotiate overarching objectives. procureme The cross party Black Rock Project A formal evaluation process will be terms for temporary 3 year nt) Board will have a role in evaluating conducted and the criteria for term for Sand Sculpture Temporary Uses to be proposals and making a evaluating bids will be agreed in proposal [terms currently in procured immediately for Toni recommendation to EDCC and advance with the Black Rock final stages of negotiation a Manuel/ Policy & Resources Committee Project Board. and led by seafront team]. Leisure use for a minimum Adam regarding future long term 3 year term. Bates proposals. Project Board in Spring 2013 will meet to take forward permanent Development 221
Brief for site following options appraisal process.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Major Projects UpdateReport | 174 KB | DownloadRead as text |
PDF |
View item 63. as HTML 217 KBReport | 217 KB | Download |
Follow Economic Development & Culture Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Mar 2017 | Supporting a Vibrant Tourist EconomyRESOLVED - That the Committee note the work undertaken to support a vibrant tourism economy in the City and agrees th... | Noted | Open |
| 9 Mar 2017 | Developing a new Strategic Framework for Arts & Culture in the CityRESOLVED - That the Committee agrees that the City Council works with the Arts & Creative Industries Commission to de... | Agreed | Open |
| 9 Mar 2017 | Houses of Multiple Occupation - Response to matters raised at full CouncilRESOLVED – That the report be deferred. | Deferred | Open |
| 9 Mar 2017 | s106 Developer Contributions Technical Guidance - Updatei) That the Committee approves the updated Developer Contributions Technical Guidance attached as Appendix 1. ii) Tha... | Approved | Open |
| 9 Mar 2017 | Old Town Conservation Area Character StatementRESOLVED – That the Old Town Conservation Area Character Statement be approved (Appendix 1). | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.