Greater Brighton Economic Board decided this item on Tuesday 6 February 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 26.
2.1The Board is asked to note the contents of this report.
3. GREATER / BRIGHTON INVESTMENT PROGRAMME HIGHLIGHTS
Flood Alleviation Scheme (Newhaven)
3.1With the completion of the flood defences on the west bank of the Ouse in October 2017, the focus is now on the 2.5km of flood wall on the industrial east bank of the river.
3.2Some sections of the east bank works are complete or close to completion, including a 350m earth embankment from the A26 to the railway line and 200m
45 of flood wall north of the Swing Bridge. However, other sections of the planned defence are proving complex from a design and buildability perspective, due to the presence of various waste and recycling sites, interactions with an operational port and interactions with Network Rail assets.
3.3We continue to work through these challenges and still expect the overall programme completion deadline of autumn 2019 to be met.
Port Access Road (Newhaven)
3.4Tenders for the second phase of the Port Access Road (from Pargut roundabout and over Mill Creek) were received back on 20 Dec 2017 and are being evaluated. We are also exploring various value engineering suggestions proposed by the preferred contactor to give a more cost effective design.
3.5Alongside that East Sussex County Council (ESCC) is still working with the Department for Transport (DfT) on the business case and we have recently had two very productive meetings with them around the requirements. The business case will focus on the economic and regeneration benefits delivered by the scheme.
3.6ESCC will be continuing to submit draft information to DfT for comment, however as previously stated, final submission cannot occur until there is an agreed tender price. Value engineering work with the preferred contractor is planned to be concluded by end February 2018, following which final submission of the business case is anticipated in March.
3.7DfT have advised that 8-10 weeks will be needed for their approval process which will involve a ministerial decision. Assuming a favourable funding decision, main construction is anticipated to start in early summer 2018. Construction is then expected to take 19 months to complete.
3.8In preparation for main construction, advance vegetation clearance works will start at the end of January and will be followed by the construction of a new badger sett, and the translocation of newts.
Enterprise Zone (Newhaven)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Progress update on Greater Brighton Investment ProgrammeReport | 379 KB | DownloadRead as text |
PDF |
View item 26. as HTML 41 KBReport | 41 KB | Download |
Follow Greater Brighton Economic Board at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Apr 2025 | Sussex Energy UpdateView the decision text for item 20. | Decided | Open |
| 2 Apr 2025 | Greater Brighton Operational Arrangements 2025/26View the decision text for item 21. | Decided | Open |
| 2 Apr 2025 | Strategic Workplan 2025/26View the decision text for item 22. | Decided | Open |
| 16 Oct 2024 | Sussex Energy UpdateView the decision text for item 9. | Decided | Open |
| 16 Oct 2024 | Admission of New Member to the BoardView the decision text for item 10. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.