Greater Brighton Economic Board
Investment Programme Update 85
Report
16th July 2019 Contents Item 1 Highlight Summary Page 3 2 Burgess Hill Strategic Growth Programme Page 4 3 Central Research Laboratory - Brighton Page 6 4 Circus Street- Brighton Page 7 5 Decoy Farm - Worthing Page 8 6 Digital Catapult- Brighton Page 9 7 Eastside South - Newhaven Page 10 9 Heritage Centre Stage - Brighton Page 11 10 New England House - Brighton Page 12 11 New Monks Farm – Shoreham By Sea Page 13 86
12 Flood Alleviation Scheme - Newhaven Page 14 13 Port Access Road - Newhaven Page 15 14 Railway Quay - Newhaven Page 16 15 Springman House - Lewes Page 17 16 Teville Gate - Worthing Page 18 17 Union Place - Worthing Page 19 18 Valley Gardens - Brighton Page 20 19 Waterfront Brighton Page 21 20 Western Harbour Arm – Shoreham-By-Sea Page 22
2 Investment Programme Update July 2019 Highlight Summary
PROJECT DELIVERY PARTNERS REPORT HIGHLIGHT Northern Arc: An outline planning decision for the first phase of the development (Freeks Farm) is anticipated to be issued imminently. The main Northern Arc outline planning application (which encompasses the remainder of the Burgess Hill Mid Sussex District Council, Homes England, West site) is anticipated to be determined in October 2019. A delivery development partner has been appointed by Strategic Sussex County Council, Burgess Hill Town Council, Homes England to deliver Freeks Farm and a reserved matters application is anticipated to be submitted to Mid Growth Coast to Capital, Department of Transport, Sussex District Council in July, with works scheduled to begin on this phase later in the year. The first housing is Programme developers (including New River and Glenbeigh anticipated to be delivered in 2020.
Construction of the CRL building, recently rebranded ‘Plus X’, continued in line with the programme, with the concrete frame now at full height and ‘topping out’ planned for late June. Installation of curtain wall glazing and Central M&E works is underway and the coloured exterior cladding is to commence in August 2019. The target completion Research Brighton & Hove City Council (Delivery Body), U+I date for Plus X remains December 2019. In terms of the comprehensive redevelopment, construction of the student Laboratory Group Plc (Developer) and University of Brighton (PlusX) blocks on the barracks site commenced in December 2018 and is now up to level 4, completion of which is planned 87
for summer 2020. Work on the first residential blocks is due to start in July 2019, and completion of the full development is scheduled for the end of 2022
The 5G Brighton test bed has taken its first full cohort of 5 businesses through the 5G-accelerator programme and they have all now developed their applications to proof-of-concept stage. These include Cynapse, who use 5G to enhance their AI image engagement application, and Mnemoscene, who create high-quality virtual models of museum artefacts and tested 5G as a way of sharing them internationally. The open call for the second cohort of 7 Wired Sussex & University of Brighton, University Digital Catapult businesses has now closed and the successful companies will be announced shortly. An extension of the 5G Brighton of Sussex, BHCC, American Express programme to include the Brighton Dome and Corn Exchange is underway, and at launch this will be the most significant testing of 5G applications in a performance space in the UK.
Secretary of State resolved not to call in the planning application in May 2019. New Monks Farm Development Ltd, Highways New Monks England, West Sussex County Council and Adur Adur DC, West Sussex CC, and developers looking to finalise the Section 106 agreement and other land acquisition Farm District Council. issues in June/July 2019 and will formally issue the planning permission
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Progress update on Greater Brighton Investment Programme APX. n 1Report | 1.7 MB | DownloadRead as text |
PDF |
Progress update on Greater Brighton Investment ProgrammeReport | 446 KB | Download |
PDF |
View item 9. as HTML 37 KBReport | 37 KB | Download |
Follow Greater Brighton Economic Board at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Apr 2025 | Sussex Energy UpdateView the decision text for item 20. | Decided | Open |
| 2 Apr 2025 | Greater Brighton Operational Arrangements 2025/26View the decision text for item 21. | Decided | Open |
| 2 Apr 2025 | Strategic Workplan 2025/26View the decision text for item 22. | Decided | Open |
| 16 Oct 2024 | Sussex Energy UpdateView the decision text for item 9. | Decided | Open |
| 16 Oct 2024 | Admission of New Member to the BoardView the decision text for item 10. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.