Trial Park & Ride

Decided Committee 4 papers

Environment, Transport & Sustainability Committee decided this item on Tuesday 15 March 2022. Below is the council's own wording, with the papers it was decided on.

Item87

Resolved

View the decision text for item 87.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Environment, Transport & Sustainability Committee

Budget Equality Impact Assessment Template 2021/22 – Service-Users

Economy, Environment and Culture: City Transport - Traffic Management 1. Service Area 2. EIA Group

3. Head of Service Andrew Westwood

What is the proposal?

Trial Park & Ride using Mill Road

The intention is to allow the Bus Operator to run a Park & Ride service from June to September using Mill Road. 4. Budget Proposal The road will be closed to normal traffic to facilitate the operation. The road has approximately 450 spaces available for parking cars.

The trial will be operated by the Bus Operator, so the running costs will be met by them. The council’s bid to the 395

Bus Service Improvement Plan will fund the physical elements and signing costs of £70,000

Highlight the most significant disproportionate impacts on groups

Disproportionate impacts identified on the following characteristics: Age (older people), Disability

The trial P&R will operate in the same manner as the football operation with dedicated stopping points and 5. Summary of marked disabled parking bays at the bottom. This will require some physical improvements to the stopping impacts points to improve access.

Closure of the road to allow the P&R to operate will offer an opportunity to consider the long term use of Mill Road, as it is currently used as a short cut by some local drivers to avoid using a section of the A27. However, a national cycle route also cuts across Mill Road at the eastern end and any closure will help to improve the access for cycling. Those with mobility have to use the spaces at the bottom of the road and this may have limited availability. The footway is not very wide and will reduce access for those in wheelchairs and those with push chairs.

6. Assess level of impact (1= low; 5= 2 high)

What actions are planned to reduce/avoid negative impacts and increase positive impacts?

The Traffic Order has a 12 week objection period and will enable anyone the opportunity to express their views on the trial. This will allow the impact on disadvantaged groups to be assessed.

Mill Road is currently successfully used as a Park & Ride scheme on matchdays for Brighton & Hove Albion so it 7. Key actions to is currently run with the same constraints. The council’s investment will improve the bus stopping points and reduce negative access from the blue badge parking area. This will not only enable the trial to operate, but also help the football 396

impacts park and ride operation for those with mobility issues.

The closure will be managed by stewards who will be able to direct and manage the parking for those with mobility issues.

Publicity will be targeted by the bus operator to ensure anyone using the trial will be aware iof the access limitations. They will use signing to direct people to the correct parking spaces.

8. Full EIA? Not required at this stage as it is a trial and permeant scheme will be subject to a full EIA.

How will you monitor the impact of this proposal and the success of your mitigating actions on these groups over the coming year (or more)? 9. Monitoring and Evaluation The bus operator will be managing the P&R and will have staff on site that will enable the monitoring of the scheme for Blue Badge holders and people with mobility issues. The bus operator will be reviewing the scheme as it progresses.

A new Traffic Order will be required to allow the use as a P&R.

The trial will be operated by the Bus Operator and promoted widely to target those not served by public transport rather than compete with established services. It will be signed strategically, in partnership with National Highways

Parking surveys of the Westdene area will be carried out to monitor any potential impact on surrounding residential areas.

Might related proposals from other service areas (or other changes) worsen or mitigate impacts from your proposal? 10. Cumulative 397

impacts There will be no impact from other services on this proposal. 398

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Trial Park & Ride APX. n 1Report 293 KB DownloadRead as text
PDF
Trial Park & RideReport 331 KB Download
PDF
View as HTML (87./2) 19 KBReport 19 KB Copy on its way
PDF
View item 87. as HTML 44 KBReport 44 KB Copy on its way

More from Brighton and Hove Environment, Transport & Sustainability Committee

All decisions
MeetingDecisionOutcome
14 Mar 2023 Official Feed and Food Controls Service Delivery Plan 1 April 2023 - 31 March 2024View the decision text for item 86. Decided Open
14 Mar 2023 Public Toilet UpdateView the decision text for item 87. Decided Open
14 Mar 2023 City Environment Improvement Programme UpdateView the decision text for item 88. Decided Open
14 Mar 2023 Local Transport Plan 2023/24 Capital ProgrammeView the decision text for item 89. Decided Open
14 Mar 2023 Mini Holland feasibility study - Wish & WestbourneView the decision text for item 90. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies