2.1 That Committee delegates authority to the Executive Director for Housing, Neighbourhoods and Communities to procure and award a contract for construction through an existing framework process. 2.1 That Committee delegates authority to the Executive Director for Housing, Neighbourhoods and Communities to procure and award a contract for construction through an existing framework process.
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
2.1That Committee delegates authority to the Executive Director for Housing, Neighbourhoods and Communities to procure and award a contract for construction through an existing framework process.
167 3. Context and background information
3.1The Frederick Street scheme is a small development of four new council homes on a tight infill site, financed by a combination of HRA borrowing, right to buy receipts and Commuted Sums.
3.2The scheme achieved planning in April 2020. The infill nature of the site has its own constraints and challenges. The site is deemed too small for the Strategic Construction Partnership. Two other procurement routes were considered – the Orbis Construction Framework and Open Tender.
3.3The Procurement report to Committee in January 2021 outlined the advantages and disadvantages of each and recommended an open tender process. This route was chosen hoping to ensure several bids would be received and provide a comparison across the market.
3.4Contractors were invited to submit a tender via Brighton and Hove City Council’s online portal using the Open Tender procedure. The tender return date was 21 April 2021.
3.5Only one tender was received. On review, the price submission exceeded the Pre-Tender Estimate by 18.89% and on quality lacked the depth of information needed to demonstrate the capability to undertake a project of this nature. The post tender report prepared by contract administrators Faithorn Farrell Timms LLP (FFT) concluded, taking price and the 60% quality weighting into account, the tender did not demonstrate value for money and recommended re-tendering.
3.6The open tender process was unsuccessful, part due to the lack of interest in a small, complex infill site at a time when contractors are in demand and can be selective. The site was also tendered during a period of economic uncertainty resulting in some contractors feeling unable to deliver the project. Procurement reported some other open tenders were struggling to gain traction within the contractor market.
3.7In response, and to progress the project post Planning consent, Procurement advised on a new Invitation to Tender via In-Tend published as a mini competition via an existing framework. The close of tender was 18 January 2022.
3.8The re-tender has produced one submission, scoring significantly more highly than the first on both quality and cost. FFT recommend approving. The post tender report is being finalised and will require approval. The project remains within budget and construction works can start this year.
4. Analysis and consideration of alternative options
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Management Area Panel Review2.1 Approves the revised Terms of Reference for Housing Area Panels in Appendix 1. 2.2 Recommends to Policy & Resourc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.