2.1 That Committee agrees the recommendation to Policy & Resources Committee to approve the increase of £0.600m in the Design Competition budget allowance to deliver the Rotherfield Crescent scheme for three, three-bedroom homes based on the Pre-Tender Estimate £1.192m. 2.2 That Committee delegates authority to the Executive Director for Housing, Neighbourhoods and Communities to procure and award a contract for construction via an existing Framework (the preferred route) or other compliant route . 2.1 That Committee agrees the recommendation to Policy & Resources Committee to approve the increase of £0.600m in the Design Competition budget allowance to deliver the Rotherfield Crescent scheme for three, three-bedroom homes based on the Pre-Tender Estimate £1.192m. 2.2 That Committee delegates authority to the Executive Director for Housing, Neighbourhoods and Communities to procure and award a contract for construction via an existing Framework (the preferred route) or other compliant route .
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
HOUSING & NEW HOMES Agenda Item 24 COMMITTEE Brighton & Hove City Council
Subject: New Homes For Neighbourhoods – Rotherfield Crescent – Scheme Approval Date of Meeting: 19 September 2018 – Housing and New Homes Committee 11 October 2018 – Policy, Resources & Growth Committee Report of: Executive Director Economy, Environment & Culture
1.1Building new homes on council land is a council priority and essential if City Plan housing targets are to be met and the city’s housing crisis tackled. The council’s New Homes for Neighbourhoods (NHFN) programme addresses this undersupply by identifying suitable vacant land and infill sites to develop new homes across the city. To date, 159 council homes for affordable rent have been completed under the New Homes for Neighbourhoods programme, 12 are on site and will be completed in May 2019, with over 100 more homes in the pipeline.
1.2The Royal Institute of British Architects (RIBA) Design Competition held in 2015/16 was one of a number of pilot projects identified in the Small Site Strategy (agreed by Housing Committee, March 2014) to deliver housing units on the smaller sites within the NHFN programme. The Rotherfield Crescent scheme on the former garages site is one of four designs which have been taken forward for further design development work.
1.3The design proposals and scheme costings for the Rotherfield Crescent site drawn up by the architects, Innes Associates, were presented to Members at the Housing and New Homes Committee meeting on 15 November 2017. At this meeting, members expressed concerns about the scheme costs presented in the Part 2 report. They felt that the costs were high and that officers should explore ways in which these costs could be reduced through identifying possible savings. It was consequently decided that the report be deferred for consideration at a future Housing & New Homes Committee.
1.4This report presents five options for consideration by members. It identifies a preferred option (Option 1) and recommends that this is taken forward to the detailed design stage.
61 2. RECOMMENDATIONS:
2.1That the Housing & New Homes Committee note the options and associated risks presented in paras 4.1-4.2. of this report.
2.2That the Housing & New Homes Committee agrees Option 1 and approves:
i. The proposed scheme of four new council homes at Rotherfield Crescent, Brighton under the New Homes for Neighbourhoods programme;
ii. The procurement of a development partner and professional services for the delivery of the project and give delegated authority to the Executive Director, Environment, Economy and Culture in consultation with the Executive Director, Finance and Resources to award the contract following completion of the procurement process;
iii. The scheme rent levels at 37.5% of Living Wage, in line with the New Homes Rent Policy;
2.3That the Housing and New Homes Committee recommend to Policy, Resources & Growth Committee to:
iv. Appropriate the Rotherfield Crescent former garages site for planning purposes and delegate authority to the Executive Director of Environment, Economy and Culture to appropriate for housing once the development is complete.
3. CONTEXT/ BACKGROUND INFORMATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Management Area Panel Review2.1 Approves the revised Terms of Reference for Housing Area Panels in Appendix 1. 2.2 Recommends to Policy & Resourc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.