AI summaryCabinet considered the 2025/26 Council Plan progress update [D]. The report shows an overspend of around £7.8 million, £5.7 million of savings at risk and 11 indicators needing intervention [P31] [P256].
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
View the decision text for item 104.
Creating the conditions for the right people, with the right information to drive delivery of our Council Plan
Providing timely evidence and insight on
Mid-year performance to enable decisive action
Council Plan Identifying opportunities for experimentation and innovative 47
delivery to improve the lives of our
performance residents
Providing a framework to foster an
update inclusive and diverse workforce and services that meet the needs of our city's communities.
2025/26 Creating a sense of clarity, purpose, and stability for our staff to empower them to perform at their highest Appendix 1: Supporting information potential 1 Contents
A better Performance Management Framework 03
Corporate Leadership Plan 06
Brighton Corporate Peer Challenge 21
Corporate Key Performance 32
& Hove Indicators 48
Customer insight 38
for all Other elements of the Performance Management Framework 48
Housing safety and compliance 71
2 Corporate Leadership Plan 2025/26 Performance Management Framework
Performance management The primary purpose of performance management is to define our
is fundamental to ensuring intended outcomes and then monitor our progress and performance in delivering them. Where progress or performance is not as expected, this is highlighted to allow the council to take the council delivers its corrective action.
intended outcomes Best Value Authorities are under a general Duty of Best Value to “make arrangements to secure continuous improvement in the way in which its functions are exercised, having regard to a combination of economy, efficiency and effectiveness.” 49
The eight elements of the Performance Management Framework are key to our Corporate Governance and allow us to understand the performance of the council which provide us with a better context in which we are operating. The elements are inter-related; most services contribute to every element in the framework.
The Performance Management Framework sets out to ensure: • strong leadership at all levels that is consistent, fair, and challenges blame culture • commitment to the accountability that has been assigned to individuals • the right information reaching the right people at the right time so that suitable decisions are made and actions are taken • ongoing evaluation, review and learning to help improve future performance • the ability to identify and commitment to rectify poor performance at an early stage 3 Mid-year Council Plan performance update 2025/26 Delivering the Council Plan: The Golden Thread
Ensuring all council activities are aligned with Council Plan outcomes 50
4 Mid-year Council Plan performance update 2025/26 Introduction
Data in this report A better Brighton & Hove for all The progress status, results and data in this report relate to the period of 1st April to 30th September 2025.
Any data included outside of this period will be highlighted and only relate to that specific information.
Data is collected from a range of sources across the council, and where appropriate included within the report. Where a RAG rating has been included this is detailed except for the following three pages.
Page 43: Savings monitoring is rated as follows: • Red: Forecast overspend of 5% or more or £0.250m The Corporate Leadership Plan ensures a Connected Council view of whichever is lower • Amber: Forecast overspend of less than 5% of strategic delivery of our Council Plan. Alongside other performance insight, 51
budget or £0.250m, whichever is lower such as Key Performance Indicators, customer data, strategic risks, it • Green: Breakeven or forecast underspend. serves as the tool for monitoring delivery of the Council Plan.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2025/26 Mid-year Council Plan progress update APX. n 1Report | 74 pages | DownloadRead as text |
PDF |
2025/26 Mid-year Council Plan progress update APX. n 2Report | 32 pages | Download |
PDF |
2025/26 Mid-year Council Plan progress updateReport | 20 pages | Download |
PDF |
View item 104. as HTML 3 MBReport | Download |
Follow Cabinet at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Oct 2026 | Royal Pavilion Gardens Restoration ProjectView the decision text for item 56. | Decided | Open |
| 15 Oct 2026 | Advertising and SponsorshipView the decision text for item 57. | Decided | Open |
| 15 Oct 2026 | Black Rock Future Vision and meanwhile use.View the decision text for item 58. | Decided | Open |
| 15 Oct 2026 | Streetlighting Contract ExtensionView the decision text for item 59. | Decided | Open |
| 15 Oct 2026 | Targeted Budget Management (TBM) 2026/27 Month 5 (August)View the decision text for item 60. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.