Resolved
View the decision text for item 109.
AI summaryBrighton and Hove City Council's Cabinet delegated urgent electrical contract awards for six high rise council housing blocks, with an estimated total contract value of £1.5m [2.1] [D]. The work is intended to prevent prolonged power failure and address fire safety risks [3.2] [3.3] [P12].
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
View the decision text for item 109.
Brighton & Hove City Council
Cabinet Agenda Item 109
Subject: Urgent work for Incoming & Lateral Electrical Mains Replacement in Council Housing
Date of Decision: Thursday, 22 January 2026
Report of: Cabinet Member for Housing
Lead Officer: Corporate Director Homes & Adult Social Care
Contact Officer: Martin Reid. Director, Homes & Investment Mikila Beck. Head of Housing Repairs & Maintenance.
Email: [email protected]
Ward(s) affected: Whitehawk & Marina, Kemptown
Key Decision: Yes
Reason(s) Key: Expenditure which is, or the making of savings which are, significant having regard to the expenditure of the City Council’s budget, namely above £1,000,000 and Is significant in terms of its effects on communities living or working in an area comprising two or more electoral divisions (wards).
Exempt from call-in
Note: Reasons for urgency
Due to the special circumstances outlined below, and in accordance with Regulation 10 of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012, compliance with the requirement to provide 28 days’ notice has not been possible. The urgency of the matter has been agreed upon by the Corporate Director of Homes & Adult Social Care, and Chair of Overview and Scrutiny, and it is deemed necessary to consider this item without delay, due to the urgency to award a contract/s to ensure a specialist contractor can be procured to address the issues identified in this report at the earliest practical opportunity and risks mitigated.
1. Purpose of the report and policy context
1.1Resident safety and the safety of those who visit and work on our council homes is our key priority. Since August 2025 the Council have been working in partnership with UK Power Networks (UKPN) to carry out proactive testing on the incoming and lateral electrical mains to our high-rise blocks where the Council is unable to isolate the block supply to enable testing, as it falls under the ownership of UKPN. This testing is in order that we can understand the state of the installations and plan a programme of
9 works. The proactive testing programme followed an earlier Strategic Overview Report on the condition of electrical intake services to high rise residential blocks. This visual inspection report has now been followed by a detailed condition survey of each site. It has not been possible to conduct the survey programme without the involvement of UKPN to isolate the electrical supply to the blocks to allow testing and inspection.
1.2This proactive testing programme has identified significant safety risks that concern the infrastructure to the electrical power supply, rising and lateral mains, at six identified high rise residential blocks in the City, being Wiltshire House, Hereford Court, Warwick Mount. Viscaria (Bristol Estate), Cherry (Bristol Estate), and Allamanda (Bristol Estate). These risks warrant urgent works to be completed so that the risks are reduced.
1.3Some installations are at imminent risk of failure, which could leave residents, including vulnerable households, without power. Due to related fire safety concerns, waking watches are in place in three of these blocks (Allamanda, Viscaria & Cherry). Two of these waking watches were put in place, at Viscaria and Allamanda, to mitigate some of the risk identified by the testing programme.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Urgent Work for Incoming & Lateral Electrical Mains Replacement in Council HousingReport | 10 pages | DownloadRead as text |
PDF |
View item 109. as HTML 109 KBReport | Download |
Follow Cabinet at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Oct 2026 | Royal Pavilion Gardens Restoration ProjectView the decision text for item 56. | Decided | Open |
| 15 Oct 2026 | Advertising and SponsorshipView the decision text for item 57. | Decided | Open |
| 15 Oct 2026 | Black Rock Future Vision and meanwhile use.View the decision text for item 58. | Decided | Open |
| 15 Oct 2026 | Streetlighting Contract ExtensionView the decision text for item 59. | Decided | Open |
| 15 Oct 2026 | Targeted Budget Management (TBM) 2026/27 Month 5 (August)View the decision text for item 60. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.