Brighton and Hove City Council
Cabinet, Thursday 19 March 2026 at 2.00pm

Modernising our recycling centre

Decided Executive 2 papers

AI summaryBrighton and Hove Cabinet approves £2.3m upgrade at the Hollingdean Materials Recovery Facility, with Veolia installing a new optical sorter and supporting equipment.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedVeolia to install new optical sorter, chutes, conveyors, bays
Money£2.3m capitalFunded by PWLB borrowing, annual cost £0.130m
What happens nextProcure and install equipmentContract variations with Veolia to be finalised
Who it affectsRecycling facility and residentsHollingdean MRF serving Brighton and Hove

What was decided

Cabinet approved procurement and installation by Veolia of a new optical sorter, chutes, conveyors and bays at the Hollingdean Materials Recovery Facility, along with associated adaptation works. Report 2.1

Cabinet approved a capital budget of £2.3m to be funded by PWLB borrowing. Report P2

Cabinet delegated authority to the Corporate Director for City Operations, in consultation with the Lead Member for Environment and Net Zero, to finalise contractual amendments and Deeds of Variation with Veolia. Report 2.3, P4

Why

The facility, built in 2008, now processes around 17,500 tonnes of dry mixed recyclables a year, a higher quantity and more diverse range of materials than originally designed, including new streams required under the Separation of Waste (England) Regulations 2024. Report 3.3, 3.4, P9

Existing equipment relies heavily on manual picking, which increases health and safety risks, limits throughput and constrains the ability to add new materials. Report 3.6, P11

Officers assessed that basic adaptation with an optical sorter offers strong benefits in safety, environmental performance, compliance and value for money compared with full replacement or status quo options. Report 4.4, P17

What happens next

Complete the legal work to vary the deed of contract with Veolia, design facility equipment requirements in detail, procure the new equipment and arrange installation. Report 4.5, P19

Borrowing costs for the first two financial years will be met by the Waste PFI Reserve, with ongoing financing costs incorporated in the General Fund budget from 2028/29. Report 6.2

An annual contribution of around £0.580m over five years from 2028/29 will be required to clear an estimated £2.9m reserve deficit by 2033 when the Waste PFI contract ends. Report 6.4

The money

  • £2.3m Capital budget for optical sorter and equipment upgrades, funded by PWLB borrowing Report P2, 6.1
  • £0.130m Estimated annual financing cost over 25 years at assumed 4.5% interest rate Report 6.1
  • £0.180m Annual cost to fund six manual pickers, from Waste PFI Reserve until 2032/33 Report 6.3
  • £2.9m Estimated Waste PFI Reserve deficit by 2033 under the borrowing-led approach Report 6.4
  • £0.580m Annual contribution over five years from 2028/29 needed to clear the deficit Report 6.4
  • £5.3m Projected reserve deficit by 2033 if the £2.3m were funded directly from the reserve instead Report 6.5
  • £1.060m Higher annual contribution required under the alternative reserve-funded scenario Report 6.5
  • £0.480m Annual increase compared with the proposed borrowing-led approach Report 6.5

Options considered

  • Rejected: Maintain current infrastructure with no investment. Would prevent the introduction of new recyclable materials required by law and risk non-compliance with statutory obligations Report 4.1
  • Rejected: Add more manual pickers in existing cabins to sort new materials. Significant health and safety risks and additional ongoing operational costs, not feasible within space constraints Report 4.2, P14
  • Rejected: Full adaptation replacing all equipment within current space. Not value for money as most equipment is still within operational life, and would require significant facility downtime Report 4.3
  • Chosen: Basic adaptation: procure and install new optical sorter, conveyors, chutes and bays. Strong benefits in safety, environmental performance, compliance and value for money, with limited downtime Report 4.4, P17

Implications

  • Financial: Capital cost of £2.3m funded by PWLB borrowing, with annual financing of around £0.130m and an estimated £2.9m reserve shortfall to be addressed by 2033. Report P2, 6.1, 6.4
  • Legal: New materials required by the Separation of Waste (England) Regulations 2024 constitute a Qualifying Change in Law under the PFI contract, allowing a contract variation with Veolia. Report 7.3, 7.4
  • Equalities: Reducing manual handling and improving equipment reliability will support safer, more accessible working conditions for all staff at the facility. Report 9.1, P35
  • Climate: Modernisation is expected to improve recycling capture rates, reduce carbon emissions from disposal of contaminated materials and produce higher quality recyclate. Report 10.1, P37
  • Risk: Reduces risks of equipment failure and contamination-related disposal costs, and improves resilience to rising tonnages and new materials. Report 8.1, 4.4
  • Staffing: Six manual pickers to be funded at £0.180m per annum from the Waste PFI Reserve until 2032/33, after which the General Fund will need to absorb the cost. Report 6.3

Who and where

  • Veolia, as PFI and Integrated Waste Management Services contractor Report 3.1, 7.3
  • East Sussex County Council, as PFI partner Report 3.1
  • Staff at the Hollingdean Materials Recovery Facility Report 9.1
  • Brighton and Hove residents presenting materials for recycling Report 4.1

Timeline

  • June 2025: BHCC began collecting pots, tubs and trays; additional picking staff introduced
  • 2026/27: Borrowing costs and picker funding met by Waste PFI Reserve Report 6.2, 6.3
  • 2028/29: Ongoing financing costs incorporated in General Fund and annual reserve replenishment contributions start Report 6.2, 6.4
  • 2032/33: Waste PFI Reserve stops funding the six manual pickers; General Fund to absorb the cost Report 6.3
  • 2033: Waste PFI contract concludes; reserve must be in balance Report 6.4

Plain English for the jargon

  • MRF: Materials Recovery Facility, where dry mixed recyclables are sorted at Hollingdean
  • PWLB: Public Works Loan Board, the government body from which councils can borrow
  • PFI: Privately Financed Initiative, the funding arrangement used to build the original Hollingdean facility
  • QCiL: Qualifying Change in Law, a contract mechanism allowing variations to the PFI contract when law changes
  • General Fund: The council's main revenue budget for day-to-day services
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item144

Resolved

View the decision text for item 144.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Cabinet, 6 pages

Recommendations

2.1That Cabinet approves the procurement and installation by Veolia of a new optical sorter, chutes, conveyors and bays, along with the associated adaptation works required at the Hollingdean Materials Recovery Facility.

9 2.2 That Cabinet approves a capital budget of £2.3m to be funded by PWLB borrowing.

2.3That Cabinet delegates authority to the Corporate Director for City Operations, in consultation with the Lead Member for Environment and Net Zero , to finalise, approve and enter into any required contractual amendments with Veolia, including agreeing detailed terms of all necessary Deeds of Variation.

3. Context and background information

3.1The Hollingdean MRF was constructed in 2008 under the Privately Financed Initiative and Integrated Waste Management Services Contract with East Sussex County Council and Veolia. A comprehensive suite of technical documents produced during the original development of the Hollingdean Integrated Waste Facility provides a robust evidence base confirming that the site remains the most suitable location for the city’s materials recovery operations. The site was selected following an extensive site-search and shortlisting process undertaken as part of the initial procurement and planning stages. This included a detailed assessment undertaken by Veolia, which examined multiple alternative locations against operational, spatial, environmental and logistical criteria. The shortlisting process was transparent, methodical and grounded in measurable requirements. Further independent assessment by Jacobs, examined the feasibility of an alternative location, also concluded that Hollingdean offered clear advantages in terms of deliverability and operational suitability.

3.2The site was specifically designed to accommodate the operational needs of a modern MRF, including the capacity to adapt to evolving waste streams. Its configuration allows for efficient vehicle movements, appropriate separation and processing areas.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Modernising our recycling centreReport 6 pages DownloadRead as text
PDF
View item 144. as HTML 58 KBReport 58 KB Copy on its way

More from Brighton and Hove Cabinet

All decisions
MeetingDecisionOutcome
15 Oct 2026 Royal Pavilion Gardens Restoration ProjectView the decision text for item 56. Decided Open
15 Oct 2026 Advertising and SponsorshipView the decision text for item 57. Decided Open
15 Oct 2026 Black Rock Future Vision and meanwhile use.View the decision text for item 58. Decided Open
15 Oct 2026 Streetlighting Contract ExtensionView the decision text for item 59. Decided Open
15 Oct 2026 Targeted Budget Management (TBM) 2026/27 Month 5 (August)View the decision text for item 60. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies