AI summaryBrighton and Hove Cabinet approved accepting up to £20 million of Pride in Place government funding for Whitehawk over 10 years, with the council acting as accountable body for a new community-led Neighbourhood Board.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCouncil will be accountable body for the fund
MoneyUp to £20m over 10 years67% capital, 33% revenue; £0.420m to set up Board
What happens nextChair appointment by April 2026Further Cabinet report due January 2027
Who it affectsWhitehawk neighbourhood residents and groupsPlus ward councillors and local MP

What was decided

Cabinet approved acceptance of the Pride in Place funding award from the Ministry of Housing, Communities and Local Government, and agreed the council will act as the Accountable Body for the programme. Report 2.1, P2

Cabinet delegated authority to the council's S151 Officer, working with the Leader, to set up the Neighbourhood Board and administer the grant funding in line with guidance and legal duties. Report 2.3

Cabinet noted that the ward councillors for Whitehawk are intended to be appointed to the Neighbourhood Board by full Council at its May 2026 AGM, and that a further report will come to Cabinet in January 2027. Report 2.4, 2.5

Why

Whitehawk was selected by the government as a 'doubly disadvantaged' area, based on high deprivation levels and weak social infrastructure, to receive long-term community-led investment. Report 3.2, 3.5

The funding gives local people power over how investment is used in their neighbourhood, with a Neighbourhood Board required to set priorities, guide spending and ensure transparency. Report 3.1, 3.8, P15

Officers judged there were no realistic alternative options because the Pride in Place guidance and requirements are highly prescriptive. Report 4.1, 4.2

What happens next

Recruit an independent Chair for the Neighbourhood Board by April 2026, with a stakeholder panel drawn from local community and resident groups. Report 3.10, 3.11

Recruit and appoint the Neighbourhood Board between April and July 2026, with a deadline of 17 July 2026 to tell MHCLG the proposed membership. Report 3.32, P43

Submit the 10-year Regeneration Plan to MHCLG by November or December 2026, with the main funding programme starting in April 2027. Report 3.32, P43, 3.22

The money

  • up to £20 million over a 10- year period Total Pride in Place investment for Whitehawk Report 3.1
  • 67% capital funding and 33% revenue funding Split of the £20m over 10 years
  • £0.150m Forward revenue capacity funding received January 2026 Report 3.26
  • £0.270m Further revenue funding in two tranches over 2026/27 Report 3.26
  • £0.120m Capital funding provided for 2026/27 ahead of main programme Report 3.27
  • £0.420m Funding to resource set-up and ongoing operation of the Neighbourhood Board Report 6.1

Options considered

  • Chosen: Accept the Pride in Place funding and act as Accountable Body. Long-term funding is an opportunity for Whitehawk, and the council will need to support the programme Report 2.1, P2, 4.2, 4.3
  • Rejected: Consider an alternative model. No alternative considered because the programme guidance and requirements are highly prescriptive Report 4.1

Implications

  • Legal: As accountable body, the council must ensure grants are legally compliant, including Subsidy Control, Public Sector Equality Duty, environmental assessments, procurement rules and transparency duties. Report 7.1, 7.2, 7.3, 7.4
  • Financial: Further Cabinet approval will be needed before the full funding programme starts in April 2027, and the S151 Officer will administer the funding. Report 6.2, 6.3, 3.22
  • Risk: Tight timetable for producing the 10-year plan by end of 2026, plus risks around community expectations and ensuring adequate council resourcing across the 10-year period. Report 8.1, 8.3, 8.4
  • Staffing: Adequate resourcing within the council will be needed to support the Board and act as accountable body; a Communities Delivery Unit in MHCLG will support the Board's transition to a community-led model by year three. Report 3.15, 3.19, 3.20

Who and where

  • Residents and community groups in the Whitehawk neighbourhood Report 3.2, 3.5, 3.13
  • Whitehawk ward councillors and the local MP Report 3.7, 2.4
  • Brighton and Hove City Council, acting as Accountable Body Report P2, 7.1
  • Future Neighbourhood Board members (at least 51% living or working in the area) Report 3.13

Timeline

  • Late September 2025: Pride in Place strategy and programme launched by the Prime Minister Report 3.1, 3.4
  • January 2026: First tranche of funding (£0.150m) allocated to the council Report 3.26, P43
  • February to March 2026: Advertisement and recruitment for the Chair role Report 3.10, P43
  • March 2026: Cabinet report seeking delegations for the Pride in Place programme Report P43
  • April 2026: Appointment of the Neighbourhood Board Chair Report 3.10, P43
  • May 2026: Whitehawk ward councillors intended to be appointed to the Board at full Council AGM Report 2.4
  • April to July 2026: Recruitment and appointment of the Neighbourhood Board Report P43
  • 17 July 2026: Deadline to tell MHCLG of proposed Neighbourhood Board membership and any boundary changes Report 3.18, P43
  • July to November 2026: Community engagement and development of the long-term plan Report P43
  • November or December 2026: Neighbourhood Board to submit the plan to MHCLG Report P43
  • January 2027: Further Cabinet report on governance and administration arrangements Report 2.5
  • April 2027: 10-year funding and plan commences Report 3.22, P43

Plain English for the jargon

  • MHCLG: Ministry of Housing, Communities and Local Government, the government department providing the funding
  • S151 Officer: The council's chief finance officer, with statutory responsibility for financial administration
  • Accountable Body: The local authority that holds and administers public funds on behalf of a programme, ensuring legal and proper use
  • Neighbourhood Board: A community-led body that decides how Pride in Place funding is spent in the local area
  • Subsidy Control: Rules under the Subsidy Control Act 2022 that govern when public funding to organisations may be allowed
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item152

Resolved

View the decision text for item 152.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Cabinet, 10 pages

Recommendations

2.1That Cabinet approves the acceptance of the Pride in Place funding award by the Ministry of Housing, Communities and Local Government (MHCLG) as set out in section 3 of this report.

375 2.2 That Cabinet agrees that the Council shall provide support to the Pride of Place Programme in the terms specified by MCHLG, including acting as the Board’s Accountable Body, in accordance with the obligations and requirements of the Programme.

2.3That Cabinet delegates authority to the Council’s S151 Officer, in liaison with the Leader of the Council, to take all actions necessary to support the establishment of the Neighbourhood Board, including appropriate governance arrangements, and to oversee the administration of all Pride in Place grant funding received from the MHCLG in accordance with published guidance and legal responsibilities.

2.4That Cabinet notes the intention for the ward councillors for Whitehawk ward to be appointed by full Council at its AGM in May 2026 as members of the Neighbourhood Board.

2.5That Cabinet notes a further report will come to Cabinet in January 2027 to update on the governance and administrative arrangements that have been put in place with the Neighbourhood Board and to report on the long-term plan.

3. Context and background information

3.1The Pride in Place Strategy and Programme was launched by the Prime Minister in late September 2025. The initiative is a long-term, community-led programme that gives local people power over how investment is used in their neighbourhood. Investment funding will be up to £20 million over a 10- year period.

3.2An area broadly described as Whitehawk was selected in the Pride in Place Programme by government. Please see the initial boundary map at Appendix 1. Locations were selected by criteria described as those that are ‘doubly disadvantaged’ by both the highest deprivation levels and weakest social infrastructure. The government has used ‘needs metrics’, such as the Index of Multiple Deprivation, to identify areas for funding awards. Further detail of the data can be found here. Background document 1 - Pride in Place Programme_ FAQ - GOV.UK

3.3The recently announced Pride in Place programme is referred to as Phase 2, with the previous ‘Plan for Neighbourhood’ initiative, now referred to as Phase 1 of Pride in Place.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PIPP Whitehawk Boundary MapAppendix 1 2 pages Download
PDF
Pride in PlaceReport 10 pages DownloadRead as text
PDF
View as HTML (152./2) 13 KBAppendix 13 KB Copy on its way
PDF
View item 152. as HTML 103 KBReport 103 KB Copy on its way

More from Brighton and Hove Cabinet

All decisions
MeetingDecisionOutcome
15 Oct 2026 Royal Pavilion Gardens Restoration ProjectView the decision text for item 56. Decided Open
15 Oct 2026 Advertising and SponsorshipView the decision text for item 57. Decided Open
15 Oct 2026 Black Rock Future Vision and meanwhile use.View the decision text for item 58. Decided Open
15 Oct 2026 Streetlighting Contract ExtensionView the decision text for item 59. Decided Open
15 Oct 2026 Targeted Budget Management (TBM) 2026/27 Month 5 (August)View the decision text for item 60. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies