Cabinet, Tuesday 4 February 2020 at 4.00pm

Temple Island - scheme content and development agreement

Approved Executive 6 papers

Cabinet approved this item on Tuesday 4 February 2020. Below is the council's own wording, with the papers it was decided on.

Item16

Resolved

Cabinet approved: 1. the Council entering into conditional agreements and an agreement for lease with Legal & General, based on the principles set out in the Heads of Terms contained within the exempt Appendix I. Cabinet authorised: 2. the Executive Director for Growth and Regeneration, in consultation with the Deputy Mayor Finance Governance and Performance, the S.151 Officer, and Director of Legal Services to finalise the terms and conclude all necessary legal agreements between the parties. Cabinet approved: 3. the allocation of £2m to the G&R Directorate to support the development of the project in line with the financial Appendix G – including further site investigation and scheme development work, whilst funding is sought to deliver the full extent of enabling works. 4. the repurposing of EDF funding as per Appendix G, and the development and submission of funding applications of up to £32m to WoE LEP to enable BCC to implement enabling works to support the delivery of the Temple Island mixed use scheme and subject to Joint Committee approve and acceptance of the award incorporated into the council’s capital programme. Cabinet noted: 5. The proposed Memorandum of Understanding between the Council and L&G (at Appendix A.2) to support broader joint working within the TQEZ. 6. Officers will keep the G&R scrutiny Commission informed and updated regarding the progress of the overall scheme.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Cabinet

Decision Pathway – Report

PURPOSE: Key decision

MEETING: Cabinet

DATE: 04 February 2020

TITLE Temple Island – conditional disposal of land interest to L&G and associated office building lease

Ward(s) Windmill Hill and Lawrence Hill

Author: Colin Molton Job title: Executive Director, Growth & Regeneration. Cabinet lead: Cllr Cheney Executive Director lead: Stephen Peacock Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: nd At the 2 July 2019 Cabinet meeting, Cabinet received an update on proposals for Temple Island re-development and the proposed disposal of land to Legal and General. Approval was given, in principle, to the conditional disposal of the Temple Island site to L&G on a long leasehold basis – in a way which demonstrates best consideration – and to the Council entering in to an Agreement for Lease relating to an office building not exceeding 100,000 sq ft to be constructed on the Temple Island site through a first phase of works. Cabinet further approved a project budget of up to £0.5m to support the development of proposals for the Temple Island site. This report provides a further update on progress with L&G on Temple Island project within the context of the wider growth and regeneration plans for Bristol and seeks approval to (i) enter in to all necessary legal documentation to take the project forward (ii) for funding to continue progression of the scheme (including on site investigations), and (iii) for the development and submission of funding applications to WECA to support enabling works. Evidence Base:

Bristol is a world leading city with a strong vision for the future. The city is leading the way in delivering innovative new housing solutions and is seeking to ensure that the city is more inclusive, well connected, sustainable and successful for everyone who lives, works and studies in Bristol.

Regionally, the city has been working in close partnership with both neighbouring authorities and with partners within the wider region; forming the Western Gateway partnership which will be focused on creating a cross-border economic partnership to the benefit of its citizens and businesses.

Looking across the city, several physical regeneration projects and programmes are progressing which support this ambitious agenda including those within the Temple Quarter; Bedminster and Hengrove. Between these major projects, development will be delivered which will create new homes for existing and future residents; deliver new workspace to support economic growth in the city, and; deliver modern-fit for purpose transport infrastructure which will support sustainable, efficient and cost-effective local and regional travel.

At the same time, the city is continuing to look forward and to innovate; development at Frome Gateway, Western Harbour and proposals for a new Mass Rapid Transit for the system are all demonstrating how the city intends to grow in a more sustainable and inclusive manner and account for the needs of future generations, as well as existing residents and businesses. The Mass Rapid Transit will see connections from key hubs, enabling the movement of significant numbers of people between key destinations within the city – including Temple Meads.

In the Temple Quarter; proposals plan to build on the success of projects such as the Engine Shed and on the growth delivered through the Enterprise Zone. The city now has an opportunity to capitalise on emerging opportunities and BCC, working in close partnership with other public sector bodies including Network Rail, WECA and Homes England, is actively seeking to facilitate the development of a new city quarter within Temple Quarter; somewhere that realises the Mayor’s Vision of a “new city quarter 1 Version April-2018 that is welcoming to all – to live, work, study, enjoy leisure time and build on Bristol’s strengths as a world class city”

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App A.1 FINAL_KPMG Temple Island VFM AssessmentAppendix 19 MB Download
PDF
App A2: Draft Memorandum of Understanding between BCC and LGAppendix 184 KB Download
PDF
App A3 CBRE letter (redacted)Appendix 614 KB Download
PDF
App D Temple Island risk register summary version updatedAppendix 133 KB Download
PDF
Temple Island EqIAAppendix E 458 KB Download
PDF
Temple Island: scheme content and development agreementReport 500 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
MR
Marvin ReesCommittee Member, present
NB
Councillor Nicola BeechCommittee Member, apologies
CC
Councillor Craig CheneyCommittee Member, present
AC
Councillor Asher CraigCommittee Member, present
KD
Councillor Kye DuddCommittee Member, present
HG
Councillor Helen GodwinCommittee Member, present
HH
Councillor Helen HollandCommittee Member, present
AK
Councillor Anna KeenCommittee Member, apologies
PS
Councillor Paul SmithCommittee Member, present
SP
Councillor Steve PearceCommittee Member, present
RA
Rachel AbbaOfficer, expected
SM
Sara ManixOfficer, expected

All 14 on the meeting page

On this subject at Bristol

Search all
  1. Temple Island - scheme content and development agreementThis decision
  2. Temple Island: Agreement for Lease (AFL) Variation and Delivery FundingApproved
  3. Temple Island UpdateNoted
  4. Temple Island - update on proposals and disposal arrangementsDecided
  5. Temple IslandApproved

More from Bristol Cabinet

All decisions
MeetingDecisionOutcome
9 Apr 2024 Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... Decided Open
9 Apr 2024 Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... Approved Open
9 Apr 2024 Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... Noted Open
9 Apr 2024 TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... Approved Open
9 Apr 2024 Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies