Cabinet: 1. Authorised the Executive Director for Growth and Regeneration, in consultation with the Cabinet Member for Energy, the Cabinet Member for Finance, and the s151 Officer, to apply for and accept revenue and capital grant funding from the Heat Network Investment Project (HNIP) to support the delivery of the council’s heat network projects. Note that, if accepted, Heat Network Investment Project grant award must be held by a special purpose vehicle (SPV), which is subject to a separate Cabinet approval; 2. Subject to capital grant funding of £5.3m being award by the HNIP, Approved the allocation of up to £4.9m (funded from prudential borrowing) for the next phase of the Bristol heat networks as noted in this Cabinet report, to be deployed in line with the phasing of planned development as contained in Table 1 below (revisions to this will be subject to business cases being agreed with the s151 Officer); 3. Authorised the Executive Director for Growth and Regeneration in consultation with the Cabinet Member for Energy, to: a) agree terms and approve associated waste heat supply contracts with the University of Bristol; b) agree terms and approve associated contracts for joint heat supply project(s) with Geneco /Wessex Water (sewer heat) and the Coal Authority (former mineworkings ); 4. Authorised the Executive Director for Growth and Regeneration, in consultation with the Cabinet Member for Energy, to sign heat connection agreements with customers and procure and enter into contracts for delivery of all goods, works and services (including associated operation and maintenance contracts) referenced in Appendix A to this Cabinet Report to the value of the funding agreed; 5. Cabinet to note that BCC are in the process of setting up a City Leap Joint Venture that could be the actual capital fund source for this and other related schemes rather than BCC Prudential borrowing.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Ward(s) Southville, Bedminster, Lawrence Hill Author: Paul Barker Job title: Energy Infrastructure Programme Manager Cabinet lead: Cllr Kye Dudd Executive Director lead: Stephen Peacock Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report:
Bristol City Council is installing heat networks to deliver affordable, low-carbon heat and energy to homes and businesses across the city in support of the 2030 net zero Carbon target. In order to achieve this target, the Bristol heat network needs to expand beyond central Bristol and utilise all the available sources of low and zero carbon heat the city has access to.
This report seeks approval to:
1. Develop and build phase 1 of the Temple heat network, supplying low carbon heat to new developments being built in the Temple and St Philips areas of the city. The network will make use of the waste heat generated from the new University of Bristol Temple Quarter campus cooling demands.
2. Design and develop Phase 1 of the Bedminster heat network, will initially supply low carbon heat to new developments being built in this area of the city as well as existing buildings including Bristol South Pool. An energy centre is being proposed that will utilise heat from the adjacent main sewer as well as potential waste heat from the former mineworkings in the area.
Evidence Base:
Bristol City Council has invested over £6m in its heat networks to date and supplies over 1,000 properties with low carbon heat. A comprehensive city wide heat network will be a crucial aspect of the action required if Bristol is to achieve its carbon neutral ambitions and also represents a significant investment opportunity as part of the City Leap programme. Prior to the City Leap Energy Partnership being in place, it is critically important that the council continues to support the build out of the heat network in order to: meet the connection timeframes of new developments; ensure long term financial viability of the network; and progress along the zero carbon pathway.
The Bristol heat network must also be able to supply low or zero carbon heat to connected buildings at a cost equivalent to, or lower than, mains gas so that existing buildings are incentivised to connect to the heat network. For the Temple network, this is proposed in the first phase through the use of waste heat from the University’s new Temple Quarter campus building’s cooling system.
The Bedminster network will potentially take advantage of two forms of zero carbon heat. Those from the sewer network and those from former mineworkings. Both options are being progressed in tandem as both technologies
1 Version April-2018 will need to be developed in the city to provide zero carbon heat to the city.
The sewer heat is being taken forward in collaboration with Geneco/Wessex Water who own and operate the city’s sewer system. Given the current timeframes of the networks, Bedminster is likely to be the first Bristol heat network to utilise this waste heat providing low cost, low carbon and emission free heat. In parallel, heat from mine workings is being progressed with the Coal Authority who are responsible for the UK’s former mine workings.
The Bedminster Heat Network also provides an opportunity for nearby council housing blocks of flats that are currently heated using electric night storage heating to be connected by conversion to a wet heating system. The heat network will also have the ability to connect individual homes currently connected to gas for heating and hot water. The feasibility of these and associated options appraisals will form part of the Council’s Heat Decarbonisation Delivery Plan being formulated following the development of the One City Climate Strategy, and will be part of the HRA Housing Investment Plans in future years, and are not part of this funding request.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.