Bristol City Council
Cabinet, Tuesday 3 March 2020 at 4.00pm

Heat Networks Special Purpose Vehicle

Agreed Executive 5 papers

Cabinet agreed this item on Tuesday 3 March 2020. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

Authorised the Executive Director for Growth and Regeneration, in consultation with the Cabinet Member for Transport and Energy and the Green New Deal, the Cabinet Member for Finance, Governance and Performance the Chief Finance Officer to a) establish and operate two (2) special purpose vehicles in order to accept the HNIP capital grant funding and establish the competitive heat commercial model in action; and b) transfer to the SPVs the following heat network assets in line with HNIP grant funding applications: i . Redcliffe heat network Phase 2; ii. Old Market heat network Phase 1; 2. Delegated authority to the Chief Finance Officer (S.151 Officer) in consultation with the Cabinet Member for Finance, Governance and Performance to transfer and agree the terms of the previously approved Prudential funding, to the SPVs, via onward lending loan agreement (in the region of £6.21m).
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Cabinet

Decision Pathway – Report Template

PURPOSE: Key decision

MEETING: Cabinet

DATE: 3rd March 2020

TITLE Bristol Heat Networks – Establishment of 2 Special Purpose Vehicles (SPVs)

Ward(s) All Author: Paul Barker Job title: Energy Infrastructure Programme Manager Cabinet lead: Cllr Kye Dudd Executive Director lead: Stephen Peacock Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: To seek approval for the creation of Special Purpose Vehicle companies (SPV’s) required to receive grant funding from the Heat Network Investment Project (HNIP), for the continued development of the Bristol heat network programme.

The case for the continued development of heat networks has been made previously and in September 2019 Cabinet (see background documents) approved funding for the Old Market and Redcliffe Heat networks and support for the application for grant funding from HNIP. That Cabinet report noted the need for the creation of SPV’s to hold HNIP grants.

The creation of the SPV’s also facilitates the creation of a competitive heat market consistent with the City Leap heat strategy. Evidence Base: HNIP Grant Funding and the requirement to establish an SPV Heat networks are central to achieving the Mayor’s commitment to Bristol being a carbon neutral city by 2030 as well as helping to tackle fuel poverty by providing heat to residents at lower prices. However, as heat networks are relatively capital intensive, to deliver on these objectives requires the council to apply for appropriate grant funding when available.

The Energy Service has been successful in being awarded HNIP (Heat Network Investment Project) government grant funding for the Redcliffe heat network and the Old Market heat network of £10.2m in total. The grant funding will help deliver a financially viable heat network and support Bristol becoming a carbon neutral city by 2030.

BEIS (Business, Energy & Industry Strategy), the UK government Dept. responsible for the funding, require BCC to set- up a Special Purpose Vehicle (SPV – a limited company) prior to the City Council drawing down the funding. Any successful HNIP grant award will have the same requirement for funding to be drawn down by an SPV.

City Leap, competitive heat and Multiple SPVs In order to ensure that residents of Bristol pay fair prices for the heat supplied by the district heating network, City Leap wishes to implement competitive heat retail and competitive heat generation across the heat network. The competitive heat commercial model is described in more detail in the Business Case Document in Appendix I (exempt).

There is now an opportunity to use the HNIP requirement to set up an SPV/s as the basis for setting up the first

1 Version May 2019 example of the competitive heat model in action. The set up of the competitive heat model requires us to separate what would ordinarily be contained in one SPV into two SPVs: a ‘Generation Company’ and a ‘Pipe Company’. For future successful HNIP grants we seek approval to establish further ‘Generation Companies’ around each generator, as required, on the same basis as the first.

Further financial details on these companies, their revenues, costs, operations, is contained in Appendix I (exempt).

The first two (2) SPV’s will sit under Bristol Holdings Limited (BHL). BHL have been fully briefed on the new structure, and we continue to work with them on establishing the operational and governance aspects.

Considerations and conclusions with regard to the set-up, operation and eventual sale of the SPV’s are highlighted in the below financial and legal sections and supported by opinions from the City Leap financial and legal advisors. Cabinet Member / Officer Recommendations: In accordance with Bristol City Council’s Financial Regulations:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Further essential background on the proposal: Business CaseAppendix A 870 KB Download
PDF
September Cabinet AppendixAppendix A 225 KB Download
PDF
EqIA Heat Networks SPV redacted signatureAppendix E 329 KB Download
PDF
Eco Impact AssessmentAppendix F 123 KB Download
PDF
Heat Networks Special Purpose VehicleDecisions 432 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
MR
Marvin ReesCommittee Member, present
NB
Councillor Nicola BeechCommittee Member, apologies
CC
Councillor Craig CheneyCommittee Member, present
AC
Councillor Asher CraigCommittee Member, present
KD
Councillor Kye DuddCommittee Member, present
HG
Councillor Helen GodwinCommittee Member, present
HH
Councillor Helen HollandCommittee Member, present
AK
Councillor Anna KeenCommittee Member, present
PS
Councillor Paul SmithCommittee Member, present
SP
Councillor Steve PearceCommittee Member, apologies
RA
Rachel AbbaOfficer, expected
SM
Sara ManixOfficer, expected

All 14 on the meeting page

On this subject at Bristol

Search all
  1. Heat Networks Special Purpose VehicleThis decision
  2. Transfer of Heat Network assets from the Council to Bristol Heat Networks LimitedApproved
  3. Delivery of Heat Networks for Bedminster and TempleApproved
  4. Bristol Heat NetworksDecided
  5. Bristol Heat Networks (heat network expansion and utilisation of the floating harbour to provide low carbon heat)Approved
  6. Bristol Heat Networks – 2018 update on progress and proposed expansionApproved

More from Bristol Cabinet

All decisions
MeetingDecisionOutcome
9 Apr 2024 Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... Decided Open
9 Apr 2024 Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... Approved Open
9 Apr 2024 Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... Noted Open
9 Apr 2024 TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... Approved Open
9 Apr 2024 Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies