Authorised the Executive Director for Growth and Regeneration, in consultation with the Cabinet Member for Transport and Energy and the Green New Deal, the Cabinet Member for Finance, Governance and Performance the Chief Finance Officer to a) establish and operate two (2) special purpose vehicles in order to accept the HNIP capital grant funding and establish the competitive heat commercial model in action; and b) transfer to the SPVs the following heat network assets in line with HNIP grant funding applications: i . Redcliffe heat network Phase 2; ii. Old Market heat network Phase 1; 2. Delegated authority to the Chief Finance Officer (S.151 Officer) in consultation with the Cabinet Member for Finance, Governance and Performance to transfer and agree the terms of the previously approved Prudential funding, to the SPVs, via onward lending loan agreement (in the region of £6.21m).
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
TITLE Bristol Heat Networks – Establishment of 2 Special Purpose Vehicles (SPVs)
Ward(s) All Author: Paul Barker Job title: Energy Infrastructure Programme Manager Cabinet lead: Cllr Kye Dudd Executive Director lead: Stephen Peacock Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: To seek approval for the creation of Special Purpose Vehicle companies (SPV’s) required to receive grant funding from the Heat Network Investment Project (HNIP), for the continued development of the Bristol heat network programme.
The case for the continued development of heat networks has been made previously and in September 2019 Cabinet (see background documents) approved funding for the Old Market and Redcliffe Heat networks and support for the application for grant funding from HNIP. That Cabinet report noted the need for the creation of SPV’s to hold HNIP grants.
The creation of the SPV’s also facilitates the creation of a competitive heat market consistent with the City Leap heat strategy. Evidence Base: HNIP Grant Funding and the requirement to establish an SPV Heat networks are central to achieving the Mayor’s commitment to Bristol being a carbon neutral city by 2030 as well as helping to tackle fuel poverty by providing heat to residents at lower prices. However, as heat networks are relatively capital intensive, to deliver on these objectives requires the council to apply for appropriate grant funding when available.
The Energy Service has been successful in being awarded HNIP (Heat Network Investment Project) government grant funding for the Redcliffe heat network and the Old Market heat network of £10.2m in total. The grant funding will help deliver a financially viable heat network and support Bristol becoming a carbon neutral city by 2030.
BEIS (Business, Energy & Industry Strategy), the UK government Dept. responsible for the funding, require BCC to set- up a Special Purpose Vehicle (SPV – a limited company) prior to the City Council drawing down the funding. Any successful HNIP grant award will have the same requirement for funding to be drawn down by an SPV.
City Leap, competitive heat and Multiple SPVs In order to ensure that residents of Bristol pay fair prices for the heat supplied by the district heating network, City Leap wishes to implement competitive heat retail and competitive heat generation across the heat network. The competitive heat commercial model is described in more detail in the Business Case Document in Appendix I (exempt).
There is now an opportunity to use the HNIP requirement to set up an SPV/s as the basis for setting up the first
1 Version May 2019 example of the competitive heat model in action. The set up of the competitive heat model requires us to separate what would ordinarily be contained in one SPV into two SPVs: a ‘Generation Company’ and a ‘Pipe Company’. For future successful HNIP grants we seek approval to establish further ‘Generation Companies’ around each generator, as required, on the same basis as the first.
Further financial details on these companies, their revenues, costs, operations, is contained in Appendix I (exempt).
The first two (2) SPV’s will sit under Bristol Holdings Limited (BHL). BHL have been fully briefed on the new structure, and we continue to work with them on establishing the operational and governance aspects.
Considerations and conclusions with regard to the set-up, operation and eventual sale of the SPV’s are highlighted in the below financial and legal sections and supported by opinions from the City Leap financial and legal advisors. Cabinet Member / Officer Recommendations: In accordance with Bristol City Council’s Financial Regulations:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.