Cabinet Noted the outcomes of soft services benchmarking exercises undertaken on the Bristol Schools Ltd PFI contracts. Authorised the Director of Finance, in consultation with the Deputy Mayor and Cabinet member for Finance, Governance & Performance to accept, subject to complying with obligations in the Academy agreements, the proposal to reduce the annual unitary charge by £98kpa, (1.07% of the total contract value of £9,142,964.55 for 2021/22, which is subject to RPIX) (a whole life contract saving of £1,010,243.56 (subject to RPIX), and instruct the necessary financial adjustments to bring into effect all associated savings. Noted that the Director of Finance, in consultation with the Deputy Mayor and Cabinet member for Finance, Governance & Performance, will progress further initiatives with the SPV which give rise to net savings to the Council and/or Schools thereby further reducing the PFI affordability gap, and where necessary seek approval from Cabinet. Authorised the Director of Finance, in consultation with the Director of Legal and Democratic Services to negotiate, agree and enter into all necessary documents to give effect to recommendation 2.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
TITLE PFI Benchmarking Outcome for Bristol Schools Ltd
Ward(s) n/a Author: Lee Hannan Job title: Strategic Supplier Relations Manager Cabinet lead: Cllr Cheney Executive Director lead: Mike Jackson Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report:
To advise members on the outcome of the soft services (catering, caretaking, cleaning and grounds maintenance provision) benchmarking exercise concluded on the Bristol Schools Ltd Private Finance Initiative (PFI) and the impact the results will have on the annual unitary charge payable by the Council with effect from each contract review date.
Seek agreement to accept the final proposal and secure a reduction to the annual unitary charge (UC) and to vary aspects of the contractual and commercial documentation in place in order to realise savings and other benefits from the PFI contract from 1 April 2021, subject to any discussions with and, where applicable, any consents required from DFE and/or the relevant PFI Academy schools under the terms of the Schools Agreements and Principal Agreements.
Evidence Base:
About the Bristol School Ltd PFI Contract
The Bristol Schools Ltd PFI agreement is one of 3 PFI agreements held by Bristol City Council. This agreement is managed by Bristol Schools Ltd (Special Purpose Vehicle) (SPV) and was mobilised over a staggered service availability programme over 2005/2006. The contract is due to end in 2031. The contract (as amended) covers the construction and ongoing manged facilities service for the following education and leisure buildings:
Blaise High School (Academy) Oasis Academy Brightstowe Kingsweston School Brightstowe (LA Community School) Bedminster Down School (Academy) Orchard Academy Filton Avenue at Orchard (Academy) Henbury Leisure Centre.
We are currently in year 15 of a 25 year contract. The annual fee (unitary charge or UC) payable to the PFI contractor is built up of a number of different cost elements, including repayment of the original construction costs, insurance costs, utilities costs, building asset lifecycle costs and provision of Facilities Management Services for the duration of the 25 year contract. All amounts payable to the SPV and the FM Provider are part indexed annually and elements of the contract, notably Soft Services are subject to bench-marking / market testing arrangements every 5 years 1 Version April 2021 throughout the contract term.
About Benchmarking & Market Testing
The benchmarking exercise is aimed at ensuring that the quality and competitiveness of the soft facilities management services within the UC is reflective of the market rate and offers up an opportunity to test the comparative costs of the current service provision to ensure continued value for money. This is achieved by comparing the standards and prices of the Benchmarked Services and the costs of providing them with the standards and prices of equivalent services.
The results indicate the extent (if any) that the comparable rates differ to those paid by Bristol City Council. Where the market costs sit within a +/- 5% tolerance of the current charge, no change shall be made to the charge. Where the Market Costs sit outside a +/- 5% tolerance of the current charge the parties shall agree any changes to be made to the Unitary Charge. If no agreement is reached the Contractor shall undertake actual Market Testing. The council has the option of proceeding to Market Testing but the option is unlikely to improve on the outcome of the benchmarking exercise. Further information on the Market Testing option is included in Appendix I: [Exempt Information].
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.