Cabinet Approved the re-purpose of Traffic and Highways Maintenance capital out of existing capital budgets to complete all works on the West End MSCP repairs project, for the reasons set out in this report. Approved a maximum Funding envelope of £1.360m by way of a virement from the Traffic and Highways Maintenance budgets identified to keep the West End MSCP project on track. Authorised the Executive Director for Growth and Regeneration in consultation with the cabinet member for Transport, to take all necessary decisions within the funding envelope to proceed with the works needed including any decisions above £500K. Noted that these actions would enable the car park to be re-opened to the general public in March/April 2022. Noted the Officer Executive Decision taken on the 20th December 2021 to enable the works to continue without incurring additional abortive costs to the Council.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Author: David Bunting Job title: Service Manager, Traffic & Highways Maintenance Cabinet lead: Cllr Alexander, Cabinet Member Executive Director lead: Stephen Peacock, Executive Director Transport Growth & Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report:
1. To update Cabinet on the progress of the structural repairs being undertaken on West End multi-storey car park (MSCP); and to seek approval to re-purpose £1.360k of Traffic and Highways Maintenance capital out of existing capital budgets to complete all works on the West End MSCP repairs project, for the reasons set out in this report.
Evidence Base:
Two of the Council’s multi-storey car parks were subject to structural condition surveys in 2017 as both were well over 50 years old. Following receipt of these surveys, a Cabinet Report was submitted on 3rd September 2019 to undertake the necessary repairs in order to extend their working lives by a minimum of 10 years.
Works commenced in October 2019 and Temple Gate car park repairs have been completed without any major issues at a cost of c£600k which was in line with its budget.
West End MSCP however has proved to be much more problematic for a number of reasons. The main issues can be summarised as follows:
The original survey and specification produced by the consultants underestimated the scale of deterioration in the condition of the car park and the original contingency figure of 22% was inadequate. During the course of the repairs it came to light that the car park was not built to the correct specification and substantial additional costs were incurred due to propping and support. These were not expected or budgeted. A tenant had to be removed from their unit in West End Car Park due to unforeseen repairs to their roof which incurred an additional £250k cost. There are significant costs and pressures in delaying the project in terms of demobilisation (c£200k) and loss of parking revenue (c£100k per month) if the re-opening of the car park is delayed.
This project has been very challenging and £1.36m of additional capital (which includes a £300k) contingency is required to fully complete the West End works and re-open the car park to the general public. The worst affected areas of the car park (the lower levels) have been repaired and c80% of the works are now deemed to have been completed at a cost to date of c£2.5m. There is a very strong level of confidence that the latest estimates are sufficient to complete all of the works. At the end of January 2022 it is forecast that there will be c£700k of scheduled works still to be completed.
In order for the works to continue on site an OED was taken by the Executive Director for G&R on the 20th December 2021
1 Version April 2021 approving additional payments of c£484k. This amount is included in the £1.36m of additional capital to be approved by Cabinet.
It is recommended that the existing delegated Traffic and Highways Maintenance capital budget is adjusted and repurposed to cover the additional cost of completing this project. Allocation of the additional funding would enable the project to complete this financial year and allow the car park to reopen from April 2022, generating a net revenue income of c£1m a year.
The car park is strategically placed between the city centre (CPZ) and a couple of RPZ’s, where there is very high demand for on street parking. The car park alleviates this pressure by providing off street parking for up to 750 vehicles and is often full when events and university open days take place in the city. There are currently 6 electric charge points in the car park and the Council are looking to expand this as demand increases.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.