Bristol City Council
Cabinet, Tuesday 18 January 2022 at 4.00pm

City Leap Energy Partnership – procurement update

Noted Executive 2 papers

Cabinet noted this item on Tuesday 18 January 2022. Below is the council's own wording, with the papers it was decided on.

Item20

Resolved

That Cabinet: Noted the successful conclusion of the ITT stage of the City Leap Energy Partnership Procurement with the receipt of two bids which are in the process of being evaluated. Authorised the drawdown of additional expenditure of up to £880k to fund the Procurement, which will include the project team and extension of the external legal and financial advisors’ contracts (referred to in recommendations 3 and 4 set out below), through to appointment of the Preferred Bidder and obtaining Cabinet authority to enter into the City Leap contracts with the Preferred Bidder. This sum will to be funded from the Climate & Ecological Emergency Reserve, as well as any in-year underspends within the Growth & Regeneration Directorate. Authorised the Executive Director for Growth and Regeneration in consultation with Cabinet Member for Finance, Governance and Performance to extend the City Leap Procurement legal services contract, to appointment of the Preferred Bidder and obtaining Cabinet authority to enter into the City Leap contracts with the Preferred Bidder, to an estimated value of circa £1,356k in total. Authorised the Executive Director for Growth and Regeneration in consultation with Cabinet Member for Finance, Governance and Performance, to extend the City Leap Procurement financial services contract, to appointment of the Preferred Bidder and obtaining Cabinet authority to enter into the City Leap contracts with the Preferred Bidder, to an estimated value of circa £1,112k in total.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Cabinet

Decision Pathway – Report

PURPOSE: Key decision

MEETING: Cabinet

DATE: 18 January 2022

TITLE City Leap Energy Partnership – procurement update

Ward(s) City-wide Author: David White Job title: Head of City Leap Cabinet leads: Cllr Beech, Cabinet Member for Executive Director lead: Stephen Peacock, Executive Director, Climate, Ecology, Waste and Energy Growth and Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: This Report is to: 1. Update Cabinet on the City Leap Energy Partnership procurement (the Procurement); 2. Seek authorisation of additional funding of £880k to complete the Procurement following an extension to the previously estimated timeline; and 3. Seek authorisation of extensions to the current legal and financial services contracts in relation to the Procurement. Evidence Base:

Procurement update

The City Leap Energy Partnership is a project to appoint a City Leap Strategic Partner to enter into a 20-year joint venture with the council with the aim of delivering up to £1bn of investment in low carbon energy infrastructure in Bristol and support the aim of Bristol becoming a carbon neutral city by 2030.

Following the approval by Cabinet in July 2020 of the Cabinet Report, ‘Revised City Leap Energy Partnership’, to restart the City Leap Energy Partnership procurement, a Concession Notice was published in the Official Journal of the European Union on 3 August 2020 to commence the current procurement.

Following an initial Selection Questionnaire stage, three Bidders were shortlisted to participate in the next stages of the Procurement, as follows:

 Ameresco Limited, with Vattenfall Heat UK Limited as an Essential Sub-Contractor;  E.ON UK PLC and Marubeni Corporation (acting as a consortium);  ENGIE Services Holding UK Ltd and Sumitomo Corporation (acting as a consortium).

Following the shortlisting, the next stage of the Procurement commenced in November 2020 which involved weekly dialogue meetings with each of the shortlisted Bidders. The council’s City Leap team, supported by colleagues from across the council and external advisors, met with each of the Bidders for over 150 hours to discuss a wide range of issues, including the opportunities for low carbon energy infrastructure projects on the council’s estate, community energy, local job creation, social value and legal matters. The team, supported by 1 Version Jan 2020 officers from across the council, answered over 1,800 clarification questions from the Bidders during the course of the Procurement.

Separately to the Procurement, we are also aware of the significant efforts that Bristol’s vibrant local community energy sector has made to engage with the City Leap Bidders, with the aim of providing them with a clear understanding of Bristol’s rich tapestry of community organisations and the opportunities that the partnership could create for them. We also understand that many other organisations in Bristol have engaged with or been engaged by the Bidders over the course of the past year.

This stage of the Procurement was originally envisaged to end in April 2021 with the publication of the Invitation to Tender inviting Bidders to submit final bids. However, due to the City Leap Energy Partnership being an entirely new, strategic approach to city-scale decarbonisation, this stage of the Procurement was extended to mid-August 2021 to allow for sufficient time for discussions with each of the Bidders, and internal discussions within the Council, regarding key matters.

The Invitation to Tender was published on 16 August 2021 and two bidders subsequently submitted Tenders on 17 December 2021 which are currently in the process of being evaluated. It is currently anticipated that Cabinet approval to enter into the City Leap contracts with the winning bidder will be sought in April 2022, which will be subject to the satisfactory completion of a subsequent Preferred Bidder stage.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
City Leap Energy Partnership: procurement updateReport 785 KB DownloadRead as text
PDF
Equality Impact Assessment: City Leap January 2022 FINALReport 908 KB Download

At this meeting

Whole meeting

Who was there

7 of 12 attended
MR
Marvin ReesCommittee Member, apologies
DA
Councillor Donald AlexanderCommittee Member, present
NB
Councillor Nicola BeechCommittee Member, present
CC
Councillor Craig CheneyCommittee Member, present
AC
Councillor Asher CraigCommittee Member, present
HH
Councillor Helen HollandCommittee Member, present
EK
Councillor Ellie KingCommittee Member, present
TR
Councillor Tom RenhardCommittee Member, present
HE
Hugh EvansOfficer, expected
SP
Stephen PeacockOfficer, expected
JD
Jonathan DowningCouncil Staff, expected
LD
Louise deCordovaOfficer, expected

On this subject at Bristol

Search all
  1. City Leap Energy Partnership – procurement updateThis decision
  2. Decarbonisation and the role of City LeapNoted
  3. City Leap Power Purchase AgreementAgreed
  4. City LeapAgreed
  5. Establishing the City Leap Energy PartnershipAgreed
  6. Appointment of preferred bidder for City Leap Energy PartnershipNoted

More from Bristol Cabinet

All decisions
MeetingDecisionOutcome
9 Apr 2024 Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... Decided Open
9 Apr 2024 Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... Approved Open
9 Apr 2024 Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... Noted Open
9 Apr 2024 TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... Approved Open
9 Apr 2024 Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies