That Cabinet: 1. Authorised the Executive Director, Growth and Regeneration, in consultation with the Cabinet Member for Transport and the S151 Officer to approve and submit the FBC for the Old City & King Street Pedestrianisation Scheme to WECA for funding of up to £2.5m, as outlined in this report. 2. Noted the submission of the OBC to WECA in April 2022 for approval in June 2022 and the development costs for the OBC to date of £344k. 3. Noted the total cost of £2.5m includes the development costs from OBC to FBC as outlined in this report. 4. Authorised, in the event that the bid is successful, the Executive Director for Growth and Regeneration, in consultation with the Cabinet Member for Transport and the S151 officer to take all steps required to procure and award all necessary contracts up to the value of £2.5 million (including any individual contracts over £500k) to deliver the schemes as outlined in this report. 5. Authorised Executive Director, Growth and Regeneration to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report. 6. Authorised the Head of Strategic Procurement & Supplier Relations to approve appropriate procurement routes to market where these are not yet fully defined in the report, or if changes to procurement routes are subsequently required.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Bristol City Council Equality Impact Assessment Form (Please refer to the Equality Impact Assessment guidance when completing this form)
Name of proposal Bristol Streetspace: Old City & King St & WECA Feasibility & Development Fund Directorate and Service Area Strategic City Transport, Economy Of Place Name of Lead Officer James Morvan/Ben Hanna
Step 1: What is the proposal?
Please explain your proposal in Plain English, avoiding acronyms and jargon. This section should explain how the proposal will impact service users, staff and/or the wider community.
1.1What is the proposal? The Covid-19 pandemic and subsequent lockdown conditions has had a dramatic effect on Bristol’s transport network - challenging deeply ingrained travel patterns and behaviour in a way that we’ve never seen before.
Following a central government directive in 2020, Strategic City Transport was directed to identify measures that would help protect public transport services and ensure that residents could practice social distancing safely. This included providing opportunities for increasing space for walking and cycling at local high streets in more detail.
Funding was allocated to several high streets and core routes across Bristol through a Streetspace budget (emergency active travel funding). The support and funding under this budget were primarily aimed at supporting the development of a TTRO and temporary measures; but with the aim of moving towards a permanent scheme and formal TRO.
The area of focus includes:
The Old City area is the historic city core of Bristol and is characterised by many small establishments with very limited space for social distancing. With new central government advice on how many customers can use each establishment, this area is a key priority for the Council’s Streetspace schemes.
The proposal is laid out in greater detail in a separate design document, but the principles behind the scheme were clear: to create a pedestrian-priority area in the Old City with vehicle access limited (except bicycle users) to specified times of day for deliveries or other access needs.
There was an impact on many vehicle users, including disabled users, requiring changes to be put in place around the pedestrianisation area including further provision for disabled users and careful use of delivery schedules. However, the proposal was designed to significantly improve safety for non-motorised users, as well as the key benefit of enabling safe use of the area with space for social distancing.
King St is an important commercial street with limited numbers of residents, with a high percentage of hospitality organisations that have been affected by the Covid crisis. The proposal includes the suspension of parking bays and the pedestrianisation of the area between King William Avenue and Queen Charlotte St.
The proposals did manage access to the area for delivery vehicles and disabled users and stimulated the need to review local provision, facilities and the experience of place on a door to door journey for disabled users. As a constrained space for pedestrians and vehicles and a large number of hospitality organisations, King St was identified as a high priority for the release of space for social distancing. Making changes that increase availability of space for pedestrians was designed to have a significant positive impact both on safety in the Covid crisis and the commercial viability of the area.
Additional funding has now been secured through WECAs Feasibility & Development Fund to resource design work and research to support walking and cycling. This supersedes the Streetspace scheme and comes at a time when social distancing measures and the impact of the pandemic in the UK is subsiding. The aims and objectives remain the same; with the addition of public realm design work being proposed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.