Old City/Queen Charlotte St/King St - funding reallocation

Approved Committee 6 papers

Transport & Connectivity Policy Committee approved this item on Thursday 15 May 2025. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

That the Committee for Transport and Connectivity approved the reallocation of £882k of EDF to complete the works of the Old City/Queen Charlotte St/King St improvement project.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Transport & Connectivity Policy Committee

Committee Report

PURPOSE: Final Decision Report

KEY OR NON-KEY DECISION: Key decision over £500k

COMMITTEE: Transport and Connectivity Committee

DATE: 15 May 2025

TITLE: Old City/Queen Charlotte St/King St - funding reallocation Ward(s): Central

Officer presenting the report: Adam Crowther Job title: Head of City Transport

Committee Chair: Cllr Ed Plowden Executive Director lead: John Smith: Executive Director for Growth & Regeneration

Proposal origin: BCC Staff

Purpose of Report: To seek approval for reallocation of funds in order to complete the Old City/Queen Charlotte St/King St improvement project.

Evidence Base / Options to consider:

1. This project comprises a series of pedestrian and cycle improvements in the Old City, Queen Charlotte St and King St area of Bristol. The scheme has been funded through the Active Travel Fund 4 and is currently in the construction phase. Plans can be seen in Appendices A1 to A4.

2. Upon beginning construction, the project immediately hit a delay due to incomplete utility information. New utility searches had to be scheduled, and the programme was delayed due to utility providers not attending site until their invoices have been paid. This has caused a large increase in the cost of construction (see table below). Please see Appendix E for more information.

3. There was initially scope-creep due to automatic gates (in the Old City area) being requested by the previous administration. This was not budgeted for and had to be installed before alternative funding could be allocated. These automatic gates came out of this project’s budget and resulted in an installation cost of £247k with a further £19k of maintenance.

4. Utility searches have now taken place and construction is currently ongoing. However, progress continues to be slow due to a lack of workforce supplied by the contractor, partly as a result of limited site availability. Please see Appendix E for more information.

5. The overall budget pressure is £882k, as illustrated below. Please see Appendix E for more information. 1 Version January 2024

OFFICIAL 6. Various sources were investigated as to whether they could provide the required additional funding: a. The project team enquired if CRSTS funding could be used, but this was not supported by the Mayoral Combined Authority. b. The project team considered that there was very little possibility of Strategic CIL providing the budget. c. A bid has also been prepared to use funding generated by the CAZ via the Clean Air Fund, although this is considered somewhat unlikely. d. Up to £60k of developer contribution is available from the Old Market Gap scheme.

7. Most recently, the possibility of using £1m of EDF (CRSTS match-funding) no longer required by the Bristol Temple Quarter team has been identified as the source to use. The BTQ team confirmed the cost for their scheme was approximately £12m. The project has £13.1m of EDF allocated for this so it is suggested we seek a Change Request to move £1m of EDF from BTQ to City Centre and to then include this element in the CRSTS programme. This means no impact on CRSTS funding or the DfT element.

8. An Officer Decision Notice is currently being drawn up to seek approval for the reallocation of £450k of ITB to allow the works to continue while a complete solution is identified, this will then be repaid by the funding secured by this decision.

9. If funding is not reallocated to this project work will have to stop. This will result in an incomplete project as construction is currently underway. This would be unsafe for the public and would also mean increased future costs when work is required to begin again. This would create major potential reputational damage.

10. As a result of these above issues, there will be a Lessons Learnt report created at the end of this project.

Officer Recommendations:

That the Committee for Transport and Connectivity: 2 Version January 2024

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Scheme drawing 1Appendix A1 1.2 MB Download
PDF
Scheme drawing 2Appendix A2 1.3 MB Download
PDF
Scheme drawing 3Appendix A3 1.1 MB Download
PDF
Scheme drawing 4Appendix A4 1.5 MB Download
PDF
Equality Impact Assessment (v8)Appendix B 503 KB Download
PDF
Old City/Queen Charlotte St/King St: funding reallocationReport 152 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 19 attended
EP
Councillor Ed PlowdenChair, present
GM
Councillor Graham MorrisVice-Chair, present
DA
Councillor Donald AlexanderCommittee Member, present
RB
Councillor Rob BryherCommittee Member, present
NC
Councillor Nicholas CoombesCommittee Member, present
TR
Councillor Tim RippingtonCommittee Member, present
EE
Councillor Emma EdwardsCommittee Member, present
KS
Councillor Kaz SelfCommittee Member, present
DW
Councillor David WilcoxCommittee Member, present
JS
John SmithOfficer, expected
AH
Alex HearnOfficer, expected
PM
Patsy MellorOfficer, expected

All 19 on the meeting page

On this subject at Bristol

Search all
  1. Old City/Queen Charlotte St/King St - funding reallocationThis decision
  2. Response to Full Council Golden Motion Make Bristol the UK’s Most Accessible CityApproved
  3. Old City & King Street Pedestrianisation Scheme Full Business CaseApproved

More from Bristol Transport & Connectivity Policy Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 Supply and maintenance of Urban Traffic Management and Control systemsThat the Committee for Transport and Connectivity: 1. Approved the proposal for the procurement of a new contract for... Approved Open
17 Sep 2026 Procurement of Highway Condition and AI Digital Safety Inspections ContractsThat the Committee for Transport and Connectivity 1. Authorised the Executive Director for Growth and Regeneration in... Decided Open
17 Sep 2026 Supported Bus Services Task and Finish GroupThat the Committee for Transport and Connectivity 1. Agreed to establish a task and finish group on Supported Bus Ser... Agreed Open
17 Sep 2026 Q1 Corporate Risk Report 2026/27The Transport and Connectivity Committee noted the report. Noted Open
17 Sep 2026 2026/27 Quarterly Finance Report: P3/Q1The Committee for Transport and Connectivity noted the contents of the report on the Q1 (P3) forecast. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies