That Cabinet: 1. Approved, subject to meeting the programme requirements, and any associated grant conditions, the acceptance of £1m from the Department for Education to fund the implementation of reforms. 2. Authorised the Executive Director for Children and Education, in consultation with the Cabinet Member for Children’s Services, Education and Equalities to take all steps required to accept and spend the funding including procuring and awarding contracts (including any individual contracts over £500k) necessary for the implementation of the programme from October 2022 to March 2025, in-line with the maximum budget envelopes outlined in this report. 3. Noted the submission of a grant application on 1 February 2023 to Department for Education (DfE) for the Delivering Better Value in SEND grant.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
TITLE Delivering Better Value in SEND Programme Grant Allocation
Ward(s) All wards Author: Richard Hanks Job title: (Interim) Director Education & Skills Cabinet lead: Cllr Asher Craig, Cabinet Member for Executive Director lead: Abi Gbago, Executive Director Children Children’s Services, Education and Equalities and Education Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report:
To seek approval to accept and spend a Department for Education (DfE) Delivering Better Value in SEND grant in the sum of £1m to support the implementation of reforms to manage and mitigate identified cost drivers within the SEND high needs system.
Evidence Base:
1. Over recent years, rising demand and other pressures have contributed to many local authorities accruing deficits on their Dedicated Schools Grant (DSG) and the Covid pandemic has exacerbated these issues. In Bristol, the overspend on the DSG High Needs Block budget (i.e. the funding that supports provision for pupils and students with SEND) has been increasing year-on-year to the point at which it has become unsustainable. The forecast deficit for the current financial year is approx. £44m. The DfE is running some intervention programmes to assist local authorities with deficits to achieve high needs spend sustainability.
2. Bristol was invited to participate in the DfE’s ‘Delivering Better Value in SEND (‘BCC’) (DBV) support programme in February 2022. The DBV programme provides dedicated support and funding to 55 local authorities with substantial deficit issues to reform their high needs systems. Bristol joined the first tranche of local authorities starting DBV in September 2022.
3. The DBV is a 3-year transformation programme run as follows: • Pre-engagement strategy period (February to July 2022): Bristol met with the DfE to discuss the programme in detail, the nature of support the DfE would be providing and how Bristol will best work with the DfE to drive and achieve the objectives of the programme. • Phase 1, 6 months (September 2022 to March 2023): The DfE provides project and change management capacity to support Bristol in engaging with its key stakeholders and conducting a diagnostic process to identify the underlying cost drivers of its high needs system and potential reforms to manage/mitigate these cost drivers more effectively. And, support to produce an evidence-based grant application using the outputs of the diagnostic process. • Phase 2, 30 months (est. April 2023 onwards): Implementation of the agreed reforms with ongoing support and challenge by DfE officials.
1 Version April 2021 4. The DBV programme sits alongside and complements existing and ongoing work within Bristol City Council (‘BCC’) to manage the DSG deficit. A summary of the current indicative DSG mitigations was presented to Bristol Schools Forum in September 2022. A further report on the DBV Programme went to Bristol Schools Forum in January 2023 (see Background Documents below)
5. The DBV grant application will include: • Summary of the findings of the diagnostic • Breakdown of how the grant money will be used • Expected return on investment (i.e., the sum of target opportunity areas) • Risks to not realising the expected return on investment
6. These proposals are subject to EQIAs. Those that are already in progress have full EQIAs that are updated regularly. Those that are proposed have draft EQIAs in progress that will be shaped as the work progresses. All EQIAs will be available as part of the engagement and consultation process and will evolve based on feedback from stakeholders. Cabinet Member / Officer Recommendations:
That Cabinet:
1. Approve, subject to meeting the programme requirements, and any associated grant conditions, the acceptance of £1m from the Department for Education to fund the implementation of reforms.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.