That Cabinet approved: 1. The realignment of Capital budgets in 2022/23 following the release of £3.3m council capital contingency and return for future capital spending pressures (see Appendix A1 section 6.1.4.). 2. The recommendation to utilise the Council Tax Reduction additional support scheme £0.885m in full in 2023/24 to assist households in receipt of Council Tax Reduction support (see Appendix A2). That Cabinet notes: 3. The General Fund risk adjusted forecast overspend of £11.3m, noting the position will continue to be closely monitored and mitigations explored; however, it is likely that a further Supplementary Estimate may be required prior to the end of the financial year and should this be required appropriate approvals will need to be sought from Cabinet / Council. 4. The forecast overspend of £8.0m within the HRA (with actual end of year position being funded by a transfer to or from the HRA general reserve). 5. The forecast in-year deficit of £18.5m accumulating to a total £43.5m carried forward deficit in the DSG for 2023/24, and that the Council and the Schools Forum are developing a mitigation plan which will seek to address the High Needs overspend. 6. The forecast £15.2m underspend (including corporate contingencies and funds) within the General Fund against the latest approved Capital Programme’s Budget. 7. The submission of a bid for £5.6m funding from the Combined Authority for the development of the Western Harbour Masterplan and Infrastructure Delivery Plan project. If the bid is successful, notification of award will come back to Cabinet under separate report as a key decision.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
TITLE 2022/23 P9 Finance Exception Report Ward(s) n/a Author: Jemma Prince Job title: Finance Business Partner - Planning Cabinet Lead: Cllr Craig Cheney – Deputy Mayor Director Lead: Denise Murray – Director of Finance and Cabinet Member for Finance, Governance and Performance Proposal origin: Other Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: This report is to make Cabinet aware of any material finance changes that have occurred since the detailed Period 8/Quarter 3 report was presented. It covers Period 9 (December 2022 extrapolated). The report also serves as a mechanism for any finance approvals or adjustments that are required on the Council’s approved budget.
Evidence Base: Since the Q3/P8 Finance exception report to Cabinet, there are several changes in the 2022/23 financial position to bring to the attention of Cabinet and as such this report includes:
General Fund summary 1. General Fund is currently forecasting a risk adjusted overspend of £11.3m, 2.6%, on the approved gross budget of £431.1m. This reflects a deterioration of £1.7m in the period. Adults and Children and Families account for £1.6m of this new pressure.
2. General Fund savings programme of £24.4m for 2022/23 as agreed by Council reports £3.5m, 14%, at risk (£3.7m/15% at P8/Q3). A number of these saving delivery risks are captured in the forecast outturn above and or directorate risk and opportunities log; however, it should be noted that not all risks are formally acknowledged in the outturn and as such this represents an underlying additional risk.
The Ring-fenced Accounts summary 3. Housing Revenue Account (HRA) is forecasting an £8.0m, 7.1%, adverse variance in forecast against its £112.6m net expenditure budget (no change since P8/Q3). 4. Dedicated Schools Grant (DSG) net budget is forecasting an £18.8m, 4.4%, adverse variance against its £423.4m ring-fenced budget in-year (no change since P8/Q3) taking the total accumulated carry forward opening deficit for 2023/24 to £43.5m. 5. The Public Health Grant allocation for 2022/23 is £34.6m and no variation is forecast (again in line with the forecast at P8/Q3).
Capital Programme 6. The Capital programme forecast variation is a net underspend of £13.9m (6.0%). This comprises a £4.1m underspend within the Growth and Regeneration directorate and £11.1m against corporate contingencies and funds offset by a £1.3m overspend against the HRA. 7. Following the transfer of Heat Networks to the partner for City Leap partner, £3.3m of capital funding has been released. It is proposed to realign budgets so that £3.3m of council capital contingency is returned for future capital spending pressures.
1 Version April 2021 Other Recommendations 8. Following the Department for Levelling Up, Housing and Communities (DLUHC)’s award to Bristol of £0.885m to assist c.13,000 households in receipt of Council Tax Reduction support, it is proposed to direct this award in full (both the discretionary element as well as the mandatory element) to those households eligible.
External Funding Decisions 9. The council has submitted a bid for £5.6m funding from the Combined Authority for the development of the Western Harbour Masterplan and Infrastructure Delivery Plan project.
Cabinet Member / Officer Recommendations: That Cabinet approves: 1. the realignment of Capital budgets in 2022/23 following the release of £3.3m council capital contingency and return for future capital spending pressures (see Appendix A1 section 6.1.4.). 2. the recommendation to utilise the Council Tax Reduction additional support scheme £0.885m in full in 2023/24 to assist households in receipt of Council Tax Reduction support (see Appendix A2).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.