Resolved – That the status and progress of the Property Programme be noted.
Audit Committee noted this item on Monday 29 January 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the status and progress of the Property Programme be noted.
Note the status and progress of the Property Programme.
This report intends to provide the committee with an update on the goals of the Property programme, and status/progress against these.
The significant issues in the report are:
- Governance arrangements - Progress to date - Key risks - Anticipated next steps Name of Meeting – Report
Policy
1. This programme is well aligned to Corporate Strategy Theme 7 Effective development organisation: • Development and implementation of Corporate Landlord function will support ‘One Council’ approach - ED02 • Disposals and review of retained assets will support right sizing of the estate - ED06
2. Internal Not applicable
3. External Not applicable
Context
4. The context and drivers for the programme are as follows:
4.1The council is facing a significant financial challenge, with unsustainable demand for some council services adding significant pressures to budgets. The Council needs to deliver significant savings over the course of MTFP (£37m in 23/24, and further in 24/25+), as well as continue to manage and mitigate wider risks and new pressures as these arise. 4.2. In addition to revenue savings required, there is a need to continue delivering capital receipts in order to part-fund the Capital Programme as well as transformation activities. 4.3. Bristol City Council is the owner and occupier of a diverse and valuable property estate with a book value of over £1bn, covering a mix of asset types such as operational, investment and development. The estate carries a financial cost in terms of running and maintaining these sites and ensuring that they are safe, compliant and fit for purpose. 4.4. The effective and efficient use of the council’s extensive estate is fundamental to continued delivery of public services, but also for supporting the achievement of the council’s corporate objectives, enabling new/future ways of working, delivering savings, as well as providing an opportunity to generate receipts (which are required to fund Capital programme and further transformation activities). 4.5. Additionally, in 2020 Cabinet approved a Corporate Property Strategy and agreed to establish and embed a Corporate Landlord function and approach, designed to enable the Council to utilise its assets to deliver better, more effective services to communities. The model has only partially been implemented. 4.6. At present, both budgets and activities normally carried out by a central land and property function remain somewhat fragmented across the Council; the result being lack of transparency of the asset base regarding the total cost (both capital and revenue) to the Council, reduced efficiency to leverage full value, and high levels of maintenance backlog across the estate which carries an inherent risk. 4.7. Covid-19 also affected the way that teams work, reducing the need for the same level of office space and changing the requirements of central office spaces. Changes in working practices and Name of Meeting – Report
the use of technology brought on because of the pandemic in 2020 then afforded the Council a much more immediate move to agile/flexible working which had a material impact on the estate requirements and its management.
Proposal
5. The proposal is as follows.
5.1The Property Programme was approved by Cabinet June 2023 (ModernGov - bristol.gov.uk). This programme ultimately aims to deliver the revenue savings and capital receipts stated within that report, as well as implement the model and approaches to support longer term sustainability.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Property Management Programme UpdateReport | 615 KB | DownloadRead as text |
Follow Audit Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 May 2026 | Minutes of Previous Meeting held on 24th March 2026RESOLVED – that the minutes of the meeting held on 24 th March 2026 be approved as a correct record and signed by the... | Approved | Open |
| 28 May 2026 | Work ProgrammeRESOLVED –that thereport benoted. | Decided | Open |
| 28 May 2026 | Internal Audit Annual Report 2025/26Decision Notices would be subject to reaudit in the first half of 2026/27. ACTION: Officersto (1)improve accessibilit... | Decided | Open |
| 28 May 2026 | Annual Fraud Report 2025/26Resolved – That the annual fraud report be noted. | Noted | Open |
| 28 May 2026 | Draft Annual Governance Statement 2025/26Resolved (unanimously) – That the Annual Governance Statement be approved subject to the amendments and clarification... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.