Resolved
Resolved – That the progress made on the Temporary Accommodation Programme be noted.
Audit Committee noted this item on Monday 29 January 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the progress made on the Temporary Accommodation Programme be noted.
That the Audit Committee note progress made on the Temporary Accommodation Programme
This report seeks to provide the Audit Committee with a high-level update on the Temporary Accommodation Programme.
The significant issues in the report are:
Governance arrangements on the Temporary Accommodation Programme Progress to date on the Temporary Accommodation Programme Issue of rising demand for TA and increase to number of placements Plans to bring on additional work streams to try to increase supply of accommodation Audit Committee – Temporary Accommodation Report
1. Policy
1.1The programme is aligned to the following Corporate Priorities:
• Development and Delivery Principle: specifically, ED05 Good Governance
• HC2 - Low or zero carbon homes: new builds and refurbishments will increase the number of low
carbon homes.
• HC3 - Homelessness: Cost effective Temporary Accommodation for people who are homeless will
increase.
2.1Internal Not applicable
2.2External Not applicable
3. Context
3.1Programme Overview:
3.2Our project goal is to reduce the Housing Benefit subsidy loss which is the main cost to the council from Temporary Accommodation, by providing more Council-owned TA, and increasing the amount of supported exempt accommodation available.
3.3Our key outcomes are:
• Cashable savings of £2.94m, of which £2.1m is committed for delivery in 23/24
• A more stable portfolio of TA, so that costs can be more easily controlled
• More supported housing.
• Medium term plan to significantly reduce subsidy loss for TA
3.4This project will benefit the city in the following ways:
a). Reduction in subsidy loss will enable a balanced budget, contributing to the financial sustainability of the council
b). An increase in supported housing from Registered Providers will mean that more people are placed in accommodation that meets their support needs Audit Committee – Temporary Accommodation Report
c). More suitable temporary and emergency accommodation for those who need it, with less reliance on the use of hotels
3.5The Temporary Accommodation Programme is made up of the following workstreams:
• Allocation of some general needs housing for use as Temporary Accommodation – this is only a temporary fix to help us balance budgets in the short term and will be reversed as other work streams deliver more housing supply • Increased use of supported exempt accommodation • Delivery of new build homes, conversions from the council’s disposal list, and accelerated new builds on small sites. • Conversion of properties leased from the hospital trust • Increasing direct lettings with private landlords at a cheaper rate than our Emergency Accommodation costs
3.6Emergency Accommodation Framework
3.7In addition to the above work streams which make up the TA Programme the council has recommissioned its Emergency Accommodation Framework, as it will expire in February 2024. This framework is where we secure properties on a spot and block basis with private providers of emergency TA. This is our most expensive type of TA. The above work streams should mean that we use less of this type of TA, but we do need to use some, and the newly commissioned framework helps us to limit and forecast increases in pricing. 3.8 Project financials:
3.9The project needs to deliver cashable savings of £2.1m in 23/24 and £821,000 in 24/25. The service has
been carrying an ongoing budget pressure of £5m, so to reduce this we will need to aim for a higher target in
terms of cost avoidance, to enable us to deliver our committed cashable savings in 23/24. Audit Committee – Temporary Accommodation Report
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Temporary Accommodation Programme UpdateReport | 792 KB | DownloadRead as text |
Follow Audit Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 May 2026 | Minutes of Previous Meeting held on 24th March 2026RESOLVED – that the minutes of the meeting held on 24 th March 2026 be approved as a correct record and signed by the... | Approved | Open |
| 28 May 2026 | Work ProgrammeRESOLVED –that thereport benoted. | Decided | Open |
| 28 May 2026 | Internal Audit Annual Report 2025/26Decision Notices would be subject to reaudit in the first half of 2026/27. ACTION: Officersto (1)improve accessibilit... | Decided | Open |
| 28 May 2026 | Annual Fraud Report 2025/26Resolved – That the annual fraud report be noted. | Noted | Open |
| 28 May 2026 | Draft Annual Governance Statement 2025/26Resolved (unanimously) – That the Annual Governance Statement be approved subject to the amendments and clarification... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.