Transport & Connectivity Policy Committee approved this item on Thursday 11 September 2025. Below is the council's own wording, with the papers it was decided on.
That the Committee for Transport and Connectivity: 1. Approved the spend of £500,000 to Assess the bridge and design the works required to keep safely operational, ensuring the Authority is discharging its statutory duty in this matter. Refer to evidence base for full details. 2. Approved the proposal to undertake a full category 3 structural assessment of the Avon Fixed Bridge as outlined in this report. 3. Authorised the Executive Director Growth and Regeneration in consultation with the Chair of Transport and Connectivity Committee to take all steps required to the spend the funding to undertake the full category 3 structural assessment for the and designing the subsequent required works, including procuring and awarding contracts which may be over the key decision threshold, as outlined in this report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee, 6 pages
Committee Report
KEY DECISION OR FOR INFORMATION: Key decision over £500k
COMMITTEE: Transport and Connectivity Committee
DATE: 11 September 2025
TITLE: Avon Fixed Bridge
Ward(s): Hotwells and Harbourside, Bedminster and Southville
Officer presenting the report: Shaun Taylor Job title: Head of Service – Highways and Transport
Committee Chair: Councillor Ed Plowden – Committee Member for Transport
Executive Director lead: John Smith: Executive Director for Growth & Regeneration
Proposal origin: BCC Staff
Purpose of Report: Avon Fixed Bridge, which carries Brunel Way (A3029), over the river Avon was constructed using what has subsequently found to be high-risk in-built design features, which are now known to be in a poor structural condition, based on a recent Principal Inspection. Consequently, the structure, which forms part of Bristol City Council’s adopted highway, ultimately requires replacement. This £500,000 allocation of capital funding will allow the Highway Authority to assess the current structural capacity of the bridge and then to undertake the necessary required design work for the temporary works to undertake these structural repairs to keep the bridge safely operational in the immediate future. With additional funding, these essential repairs will be undertaken. Parallel to this, the strategic planning continues for the proposed Western Harbour redevelopment works, to ultimately replace the bridge.
Evidence Base: This bridge carries Brunel Way (A3029, as part of the Cumberland Basin complex), over the river Avon. This bridge is post-tensioned and has two central precast concrete drop-in span decking, with a half-joint detail. This method of construction is no longer approved in the UK for new highway structures. This type of design detail (half-joints), is prone to sudden failure and access to these elements, for inspection, maintenance or repair is generally impossible without removal of the drop-in precast concrete deck span.
Following the recent Principal Inspection, carried out in late 2024, Bristol City Council must now undertake a full structural assessment of the bridge to understand its current load carrying capacity and begin to address the essential structural monitoring and critical maintenance which is now required, to prolong the working life of this bridge. The structure is a critical element of the main strategic city-centre transport infrastructure, providing a high-capacity transport links between the north and south sides of the river Avon on the A3029 primary route and linking the southwest motorway networks.
Template approved March 25
OFFICIAL The findings of the Principal Inspection are detailed and included in Appendix A. The evidence for continuing this critical work is summarised below:
1. This bridge, particularly the bridge deck half-joints were found to be in a poor structural condition and will ultimately limit the working life of the bridge, with the structure eventually requiring replacement.
2. To keep Avon Fixed Bridge safely operational now, an assessment of the bridge’s structural capacity must now be urgently undertaken, in accordance with DMRB standard CD454, together with setting up a new structural monitoring regime(s) and an urgent capital programme of subsequent targeted critical repairs, as defined in the recent Principal Inspection report.
3. The original defective drainage design and subsequent ongoing urgent maintenance remains an issue on the structure and is contributing negatively to the deterioration of the reinforced concrete around the half-joints, which are critical elements to the structure.
4. Following consultation, the Western Harbour masterplan proposes to retain the existing Brunel Way A3029 alignment route. Providing a crossing of the Avon at this location is essential to the future connectivity of the city and the regeneration of the Western Harbour area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.