Bristol City Council
Harbour Committee, Tuesday 20 January 2026 at 10.00am

Harbour Master Report

Decided Committee 2 papers

AI summaryBristol Harbour Committee notes update covering 88% mooring occupancy, £2 million Environment Agency grant for sluice repairs, and a fatal drowning in November 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedNo formal resolution, information item
Money£2 million Environment Agency grantFor Underfall Yard sluice and culvert repairs
What happens nextMultiple capital projects in 2026Capricorn Quay installation, sluice repairs
Who it affectsHarbour users, vessel owners, residents354 mooring spaces, 313 in active use

What was decided

The Committee noted the Harbour Master's report covering operations, capital projects, moorings, and safety incidents. Report P81

The Committee received an information report on harbour activity, with no alternative options considered as the report was for noting only. Report P79, P81

Why

The report provided an operational update on harbour patrols, infrastructure maintenance, and safety compliance for committee oversight. Report P1, P3, P4

It covered progress on engineering and capital projects, mooring occupancy, the Ports and Marine Facilities Safety Code, and Marine Safety Management System KPIs. Report P4, P23, P25

What happens next

Capricorn Quay permanent pontoon installation is expected by the end of 2026, with 36 new moorings and a marketing campaign to follow a demand study. Report P31, P32, P15

Underfall Yard sluice and culvert repairs, funded by a £2 million Environment Agency grant, are scheduled for completion by December 2026. Report P34

Prince Street Bridge refurbishment and Pero's Bridge structural repairs are both expected to complete in 2026; a moorings demand and facilities study is being procured. Report P22, P38, P41

The money

  • £2 million Environment Agency grant for Underfall Yard sluice and culvert repairs Report P34
  • £800k From Frome culverts available in 2026/7 Report P34
  • circa £900k Further bid to Environment Agency in 2026/7 Report P34

Options considered

  • Chosen: Not applicable. Report was for information only Report P79, P81

Implications

  • Financial: Capital projects depend on approval of the Medium-Term Financial Plan by full council, alongside grants and external funding at various stages of progression. Report P93
  • Financial: Capricorn Quay development, subject to funding approval, is expected to generate additional harbour income supporting the Harbour Authority Business Plan. Report P93
  • Legal: No specific legal implications arise from this report; it is for the Committee to note the Harbour Master's update. Report P96
  • Risk: Three serious incidents reported, including a fatal drowning of an off-duty police officer on 28 November 2025 and a body recovered on 14 December 2025, both under police investigation. Report P49, P50
  • Staffing: Training delivered during the quarter included JESIP, IOSH Managing Safely, Oil Spill Response Refresher, Duty Holder, and Water Safety courses. Report P68
  • Equalities: An Equality Impact Assessment is appended as Appendix B. Report P103

Who and where

  • Vessel owners and harbour users Report P19, P21
  • Residents and visitors to Bristol Harbourside Report P62
  • Cabot Cruising Club and Bristol Packet vessel operators Report P48
  • Marine facilities providers, including Bristol Marina and Underfall Yard Trust Report P55
  • Hire scooter and bicycle users (Dott scheme) Report P15

Timeline

  • 18 September 2025: Water Safety Partnership meeting held Report P64
  • 23 September 2025: Harbourside Forum Meeting held aboard the Balmoral Report P62
  • 28 September 2025: Vessel collision between Cabot Cruising Club member and Flower of Bristol at Bristol Bridge Report P48
  • Mid-November 2025: Howards Lock South outer gate repair work completed Report P9
  • November 2025: Entrance Lock North and South gate repairs completed; off-duty police officer drowned near the Arnolfini Report P36, P49
  • 14 December 2025: Body recovered from St Augustines Reach, ending search for missing person Report P50
  • May 2026: Canal and River Trust expects Kelston Lock repairs to complete Report P13
  • End of 2026: Capricorn Quay permanent pontoon installation expected Report P31
  • December 2026: Underfall Yard sluice and culvert major repairs scheduled for completion Report P34

Plain English for the jargon

  • JESIP: Joint Emergency Services Interoperability Principles
  • IOSH: Institution of Occupational Safety and Health
  • AIP: Approval in Principle, used in structural engineering design
  • WECA: West of England Combined Authority
  • MTFP: Medium-Term Financial Plan, requiring full council approval
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

The Committee
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Harbour Committee

Purpose of report

1. To report for information on the work of the Harbour Master.

Evidence Base

1. This report aims to provide an update on the following:

• Harbour Operations • Engineering and Capital Projects Update • Moorings and Occupancy Update • Engineering and Capital Projects • The Ports and Marine Facilities Safety Code • The Marine Safety Management Systems KPIs

Harbour Operations Harbour Patrols and Inspection Routines

2. The Harbour Team continues to carry out daily patrols across the Harbour, ensuring that hazards to users are identified and remedied. As part of these patrols, routine inspections take place, with repairs required undertaken and essential safety equipment, such as life rings checked and maintained. Flotsam is also removed daily, either by a dedicated craft or during routine patrols, helping to keep the waterway clear, navigable, and safe.

Template approved October 25

OFFICIAL Locking Services

3. Work on the outer gates at Howards Lock has now been completed. After repairs to the North gate were finished, attention turned to the South outer gate. Stripping the box section that connects the top plate to the gate back to bare metal revealed corrosion similar to that found on the North gate. The degraded material was removed and replaced with new plating to restore structural integrity. The work was completed in mid-November, allowing the full locking schedule to resume. These essential repairs will help maintain operational continuity until the gates are fully replaced under the Bristol Avon Flood Strategy.

Pero’s Bridge Love Lock Removal

4. Lock removal at the site has been completed. To support ongoing maintenance, inspections of the bridge and removal of any newly added locks will now form part of the Harbour Team’s weekly work programme. A full structural survey of Pero’s Bridge is scheduled, which will provide a clear assessment of the works required to ensure its continued functionality.

Harbour Movements and Navigation

5. A vessel fire at Kelston Lock in Saltford caused severe damage to the lock gates, leaving several vessels stranded on the downstream side and unable to travel through Bath and onto the Kennet and Avon Canal system. In response, the Harbour Authority has increased the availability of winter moorings, with 8 vessels taking up the offer of a safe and secure place to stay. The Canal and River Trust estimates that repairs to Kelston Lock may not be completed until May 2026, at which point full functionality is expected to be restored.

Dott Scooter Recovery

6. The Operations Team is currently collaborating with Dott to develop a recovery plan for hire scooters and bicycles that have been discarded into the Floating Harbour, New Cut, and the Feeder Canal. The recovery operation will rely on the expertise of commercial divers due to the nature and location of the submerged vehicles. This marks the second partnership between the Harbour Authority and a hire scooter provider. In 2021, Voi, in collaboration with the West of England Combined Authority (WECA), funded a similar recovery initiative which successfully retrieved 85 scooters from the Harbour. Template approved October 25

OFFICIAL Repurposing of the Ballast Seed Garden Barge

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Equality Impact Assessment: Harbour Masters ReportAppendix B 135 KB Download
PDF
Harbour Master ReportReport 2.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 16 attended
AB
Councillor Andrew BrownChair, present
PM
Councillor Patrick McAllisterVice-Chair, present
AT
Councillor Ani TownsendCommittee Member, present
KD
Councillor Kye DuddCommittee Member, present
GM
Councillor Graham MorrisCommittee Member, present
ST
Councillor Sibusiso TshabalalaCommittee Member, present
ZP
Councillor Zoë PeatCommittee Member, apologies
KD
Kathryn DavisCo-Optee, present
AB
Andy BrigdenCo-Optee, apologies
KM
Kevin MowatCo-Optee, present
WS
Will StanleyCo-Optee, present
PM
Patsy MellorOfficer, apologies, sent representative

All 16 on the meeting page

On this subject at Bristol

Search all
  1. Harbour Master ReportThis decision
  2. Harbour Master ReportNoted
  3. Harbour Master ReportNoted
  4. Harbour Master reportNoted
  5. Harbour Master ReportNoted
  6. Western Harbour Master Plan and Infrastructure Delivery PlanAgreed

More from Bristol Harbour Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Harbour Master ReportAt the conclusion of the discussion, the Chair moved the report recommendations. The Harbour Committee noted the cont... Noted Open
15 Sep 2026 Ports & Marine Facilities Safety Code, Bristol City Docks - Audit 2025At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Noted Open
15 Sep 2026 Harbour Asset Management Plan 2026 - 2031At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Approved Open
15 Sep 2026 Bristol City Docks Marine Safety PlanAt the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Approved Open
15 Sep 2026 Finance report updateAt the conclusion of the discussion, the Chair moved the report recommendations. The Harbour Committee noted the cont... Noted Open