Harbour Committee, Tuesday 17 March 2026 at 3.30pm

Harbour Capital Projects 2026/27

Approved Committee 3 papers

AI summaryBristol Harbour Committee approves capital spending on eight harbour projects including £1,800,000 for a structural assessment and £1,350,000 to repair Pero's Bridge.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAll nine recommendations passed
MoneyEight capital projectsLargest is £1,800,000 for inspections
What happens nextProcure and award contractsWithin approved budget envelopes
Who it affectsHarbour users and the publicFerry operators, bridge and lock users

What was decided

Repair the Cascade Steps Landing Stage and Viewing Platform for £900,000, repair Pero's Bridge for £1,350,000, and spend £225,000 on Prince Street Bridge, so the structures can stay in use.

Accept £1,290,000 of Environment Agency grant aid for Underfall Yard sluice gates and a replacement harbour control system, and add £900,000 of council funding for Underfall Yard culvert repairs once dive inspections have set the scope. Any unspent council funds will be returned.

Spend £600,000 on Netham Lock gates, £580,000 on Harbour Entrance Lock Gates, and £1,800,000 on a whole harbour structural assessment inspection. Authorise the Executive Director for Growth and Regeneration, with the Harbour Committee chair, to procure and award the contracts and approve extensions within the budgets set.

Why

Defects were found at Cascade Steps and Pero's Bridge that need fixing to keep the structures open for the ferry operators and the public.

The Environment Agency is funding the Underfall Yard sluice gates work as Grant in Aid, and the council is funding the culvert repairs alongside it.

The Harbour Entrance Lock Gates work is an interim fix to keep them safe until the Avon Riverside 2100 Strategy delivers a longer term replacement.

What happens next

Carry out imminent dive inspections at Underfall Yard to identify the culvert repair scope.

Procure and award the contracts within the approved budget envelopes, in consultation with the Harbour Committee chair.

Return any surplus council funds from the Underfall Yard culvert project if the full £900,000 is not needed.

The money

  • £900,000 Cascade Steps Landing Stage and Viewing Platform repairs
  • £1,350,000 Pero's Bridge repairs
  • £1,290,000 Environment Agency Grant in Aid for Underfall Yard sluice gates and harbour control system
  • £900,000 BCC funding for Underfall Yard culvert repairs
  • £600,000 Netham Lock gate repairs and reseating
  • £580,000 Harbour Entrance Lock Gates inspections and repairs
  • £225,000 Prince Street Bridge repairs
  • £1,800,000 Harbour Structural Assessment Inspection

Implications

  • Equalities: An Equality Impact Assessment is included as Appendix B. Report P2
  • Climate: An Environmental Impact Assessment is included as Appendix C. Report P3
  • Risk: The Harbour Entrance Lock Gates work is a temporary measure until the Avon Riverside 2100 Strategy delivers a replacement.

Who and where

  • Ferry operators using the Cascade Steps Landing Stage
  • Members of the public using Pero's Bridge and Prince Street Bridge
  • Boat users on the harbour affected by Netham Lock and Harbour Entrance Lock Gates

Timeline

  • 2026-03-17: Harbour Committee decision
  • Imminent: Dive inspections at Underfall Yard to set the culvert repair scope
  • Avon Riverside 2100 Strategy: Longer term replacement of Harbour Entrance Lock Gates expected

Plain English for the jargon

  • Grant in Aid: Funding given by the Environment Agency to the council for the sluice gates work.
  • Sluice gates: Movable gates at Underfall Yard that control water flow in the harbour.
  • Culvert: An underground water channel at Underfall Yard whose condition needs dive inspections.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17

Resolved

That the Harbour Committee (unanimous vote in favour): 1. Approves the request to spend £900,000 to repair the defects found with Cascade Steps Landing Stage and Viewing Platform, allowing it to continued unrestricted use by the ferry operators and public. 2. Approves the request to spend £1,350,000 to repair the defects found with Pero’s Bridge, allowing it to be brought back into full, unrestricted use by the public. 3. a. Approves the request to accept a further £1,290,000 Grant In Aid funding from the Environment Agency and spend the funding to repair Underfall Yard Sluice Gates and install a replacement harbour control system. b. Approve £900,000 BCC funding to carry out repairs to the culverts at Underfall Yard, the scope of which will be identified by the imminent dive inspections. In the event not all funds are required, the surplus will be returned. 4. Approves the request to spend £600,000 to repair and reseat the gates at Netham Lock. 5. Approves the request to spend £580,000 to carry out inspections and repairs to Harbour Entrance Lock Gates to enable safe operation until Avon Riverside 2100 Strategy delivers a replacement solution. 6. Approves the request to spend £225,000 to repair Prince Street Bridge. 7. Approves the request to spend £1,800,000 on a Harbour Structural Assessment Inspection to determine structures requiring essential repair/maintenance. 8. Authorises the Executive Director Growth and Regeneration in consultation with Chair of the Harbour Committee to procure and award contracts required for the projects described above, in line with the procurement routes and maximum budget envelopes outlined in this report. 9. Authorises the Executive Director Growth and Regeneration in consultation with Chair of the Harbour Committee to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Harbour Committee

Committee Report

KEY DECISION OR FOR INFORMATION: Key decision over £500k spend/save & impacts more than 2 wards

COMMITTEE: Harbour committee DATE: 17 March 2026

TITLE: Harbour Capital Projects 2026/27

Ward(s): Hotwells and Harbourside, Central, Lawrence Hill, Brislington East, Brislington West, St George’s Troopers Hill, and Southville

Officer presenting the report: David Lockwood, Director - Bristol Harbour Authority/Harbour Master

Committee Chair: Councillor Andrew Brown

Executive Director lead: John Smith: Executive Director for Growth & Regeneration

Proposal origin: BCC Staff

Purpose of Report: To seek approval to accept and spend authorised capital funding for the following harbour capital projects:

1. Cascade Steps Landing Stage and Viewing Platform. £900,000 2. Pero’s Bridge. £1,350,000 3. Underfall Yard Sluice Gates. (Environment Agency Grant In Aid) £1,291,000 4. Underfall Yard Culvert Repair. £900,000 5. Netham Lock. £600,000 6. Harbour Entrance Lock Gates. £580,000 7. Prince Street Bridge. £225,000 8. Harbour Structural Assessment Inspection. £1,800,000

Evidence Base

Bristol floating harbour was established as a commercial port over 200 years ago. It is now primarily focussed on leisure and recreational activities, but the original, ageing infrastructure must still be maintained to ensure the harbour remains safe and reliable for users and visitors. The Harbour Authority is committed to ensuring the Harbour Assets are managed well and are proposing a further investment in excess of £7,000,000 to ensure bridges and other structures remain safe to use and operate for the benefit of boaters, commercial operators and harbour visitors. These capital works have been approved by the Capital Investment Board on February 17th.

1. Cascade Steps Landing Stage and Viewing Platform The Cascade Steps ferry landing stage pontoons and raised viewing platform were installed as part Template approved October 25

OFFICIAL of the Centre Promenade regeneration project in 2000. Over the past 3 years there has been an increasing need to repair localised sections of the timber decking and support beams on this structure where it has rotted and become unstable. The structure is now considered end of life and must be replaced to maintain compliance with Health and Safety regulations. A professional engineering survey has been carried out on the structures and identified that the entirety of timber deck and support beams are in a poor condition and beyond repair, recommending they are replaced with suitable composite materials.

The survey also established that the steel frame structure of the pontoons and viewing platform were in general good condition, although it did highlight there may be a need to carry out some repair and preservation work as part of the project. When further details of the work are known, the Duty Holder and Stakeholder group will be updated. We will engage with effected business in due course to minimise impact.

Alternative options considered: There was no option to not fully remove the deck and supporting beams due to poor unrepairable condition. The alternative to replace like for like with hard wood timber was considered but rejected as this was more expensive and less future proof - composite being much longer lasting. If the landing platform is not replaced, the existing ferry landing will need to be closed, preventing visitors from boarding a ferry in the heart of the city.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Equality Impact Assessment: Engineering Repair Projects 2026_27 signedAppendix B 263 KB Download
PDF
Environmental Impact Assessment: Harbour Capital ProjectsAppendix C 147 KB Download
PDF
Harbour Capital Projects 2026/27Report 300 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 14 attended
AB
Councillor Andrew BrownChair, present
PM
Councillor Patrick McAllisterVice-Chair, present
KD
Councillor Kye DuddCommittee Member, present
RE
Councillor Richard EddyCommittee Member, apologies
AT
Councillor Ani TownsendCommittee Member, apologies
ST
Councillor Sibusiso TshabalalaCommittee Member, present
KD
Kathryn DavisCo-Optee, present
AB
Andy BrigdenCo-Optee, present
KM
Kevin MowatCo-Optee, present
WS
Will StanleyCo-Optee, apologies
JS
John SmithOfficer, apologies
PM
Patsy MellorOfficer, in attendance

All 14 on the meeting page

On this subject at Bristol

Search all
  1. Harbour Capital Projects 2026/27This decision
  2. Harbour Infrastructure Improvements and Technologies - Capital Investment ProgrammeApproved

More from Bristol Harbour Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Harbour Master ReportAt the conclusion of the discussion, the Chair moved the report recommendations. The Harbour Committee noted the cont... Noted Open
15 Sep 2026 Ports & Marine Facilities Safety Code, Bristol City Docks - Audit 2025At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Noted Open
15 Sep 2026 Harbour Asset Management Plan 2026 - 2031At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Approved Open
15 Sep 2026 Bristol City Docks Marine Safety PlanAt the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Approved Open
15 Sep 2026 Finance report updateAt the conclusion of the discussion, the Chair moved the report recommendations. The Harbour Committee noted the cont... Noted Open