Homes and Housing Delivery Policy Committee, Friday 17 July 2026 at 10.00am

Tackling Homelessness Transformation Programme (quarterly)

Decided Committee 2 papers

AI summaryBristol City Council's Homes and Housing Delivery Committee noted a quarterly update on the Tackling Homelessness Transformation Programme, which has over-delivered on savings targets. The 2026/27 revenue budget is £1,906,960 and the programme will now close in December 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedTwo recommendations to note financial objectives and revenue budget
Money£1,906,960 revenue budget for 2026/27Plus £245,000 contingency held centrally by Transformation Board
What happens nextProgramme closes December 2026Council-Owned RP business case due November 2026
Who it affectsNot stated

What was decided

The Committee noted that the programme's financial objectives include £4,145,000 of recurring subsidy loss reduction in 2026/27. Report P52

The Committee noted that the programme's revenue budget for 2026/27 is £1,560,425, plus a rollover of £346,535 from 2025/26, totalling £1,906,960, with £245,000 contingency held centrally by the Transformation Board. Report P52

Why

The programme aims to reduce the council's use of expensive temporary accommodation and improve outcomes for people at risk of or experiencing homelessness, while addressing a subsidy loss where the council pays above 2011 Local Housing Allowance rates. Report P3

The programme has over-delivered on savings in recent years: £4.7m against a £4.2m target in 2024/25 and £9m against an £8.2m target in 2025/26, with forecasts suggesting further over-delivery in 2026/27. Report P10

Demand for temporary accommodation is rising and costs are no longer sustainable long-term without limiting demand, prompting a renewed focus on the Demand Management and Prevention project. Report P10

What happens next

The Council-Owned Registered Provider outline business plan and full business case will go to the Strategy and Resources Committee in November 2026. Report P17, P60

A joint Policy Committee Chairs Briefing on the delayed Private Finance Leasing arrangement will be held on 9 October, once legal advice is finalised. Report P47

The general fund acquisitions programme is aiming for all 91 plus target properties to be occupied by the end of August 2026, and the Supported Housing joint commissioning plan for young people will be implemented in April 2027. Report P12, P24

The money

  • £4.7m Actual savings in 2024/25 against a £4.2m target Report P10
  • £9m Actual savings in 2025/26 against an £8.2m target Report P10
  • £1,906,960 Total revenue budget for the programme in 2026/27 Report P41, P52
  • £245,000 Contingency fund held centrally by the Transformation Board for this programme Report P41, P52
  • £4,145,000 Recurring subsidy loss reduction target in 2026/27 Report P44, P52
  • £1,560,425 New revenue spend required to deliver the programme in 2026/27 Report P41, P52
  • £346,535 Underspend from 2025/26 rolled forward into 2026/27 Report P41, P52
  • £27,530,400 Capital borrowing for acquisitions Report P37
  • £9,791 Capital costs of children's commissioning spend for 50 modular homes Report P37
  • £5,853,000 Capital budget for general fund acquisitions in 2026/27 Report P40
  • £165,000 Capital budget for MMC leaseback in 2026/27 Report P39

Options considered

  • Chosen: Lease properties from the Emergency Accommodation Framework for 10 to 11 years instead of current block contracts. More cost effective and provides a more stable supply of temporary accommodation Report P15
  • Rejected: Use a third-party company called Beam to help people into employment and match them with private rented tenancies. Contract ended by mutual agreement in December 2025 after securing 18 positive housing outcomes and 4 employment outcomes Report P19
  • Chosen: Decommission the Youth Projects service following formal consultation with staff and young people. Service objectives were met; staff redeployed and alternative placements found for young people Report P24

Implications

  • Financial: The programme has a contingency of £245,000 held centrally that would be needed if 2026/27 revenue budget of £1,906,960 is overspent. Report P41, P52
  • Financial: Private Finance Leasing arrangement savings are no longer achievable in-year and are now expected from 2027/28 onwards. Report P47
  • Financial: Cost of council homelessness service changes (HO006) cannot be accurately forecast since the new housing IT system was implemented in November 2025. Report P47
  • Equalities: An Equality Impact Assessment (Appendix A) accompanies the programme, covering the council's housing options and homelessness work. Report P64
  • Climate: Properties refurbished or built through the programme will work with suppliers to reduce emissions, contributing to Bristol's carbon neutral objective. Report P54
  • Risk: Demand for temporary accommodation could rise above programme forecasts, affecting the subsidy loss budget; the service is demand-led and partly outside council control. Report P49
  • Staffing: Recruitment and retention in housing services is below required levels, prompting recruitment of homelessness assistants as entry-level roles. Report P49

Who and where

  • Households at risk of or experiencing homelessness in Bristol Report P3
  • Young people in the youth housing pathway Report P24
  • Care leavers Report P24
  • Private rented sector tenants and landlords in Bristol Report P19
  • Bristol City Council housing services staff Report P49

Timeline

  • 2024/25: Programme saved £4.7m against a £4.2m target Report P10
  • 2025/26: Programme saved £9m against an £8.2m target; 614 households supported into private rented accommodation Report P10
  • 13 December 2024: Homes and Housing Delivery Committee approved a cap of 180 council properties per year for two years to be allocated for use as temporary accommodation Report P13
  • December 2025: Beam contract ended by mutual agreement Report P19
  • April 2026: Demand Management and Prevention project re-launched with a kick off meeting Report P21
  • As of 6 July 2026: 98 properties completed in the general fund acquisitions programme, one under offer, 41 occupied; 247 properties allocated since January 2025 Report P12, P13
  • End of August 2026: Target date for all general fund acquisitions properties to be occupied Report P12
  • 9 October 2026: Joint Policy Committee Chairs Briefing on Private Finance Leasing legal advice Report P47
  • November 2026: Council-Owned Registered Provider outline business plan and full business case to go to Strategy and Resources Committee Report P17, P60
  • December 2026: Programme is now scheduled to close, rather than the original baselined date of March 2026 Report P60
  • April 2027: Supported housing joint commissioning plan for young people to be implemented Report P24

Plain English for the jargon

  • Subsidy loss: The amount the council loses when the cost of temporary accommodation exceeds the Local Housing Allowance rate set in 2011 and refunded by government.
  • Local Housing Allowance (LHA): Government-set rates used to calculate housing benefit for private rented properties, last set in 2011.
  • Temporary Accommodation (TA): Short-term housing provided by the council to people who are legally homeless while longer-term housing is found.
  • Registered Provider (RP): A registered social housing provider, which may be a housing association or a council-owned provider.
  • Private Rented Sector (PRS): Housing owned by private landlords and let to tenants on the open market.
  • MTFP: Medium Term Financial Plan, the council's multi-year budget and savings plan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

The Committee
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Homes and Housing Delivery Policy Committee

Purpose of report

1. To provide an update on the progress of the Tackling Homelessness Transformation Programme.

Evidence Base / Context

1. The Tackling Homelessness programme aims to reduce the council’s use of expensive temporary accommodation (TA), and to provide better outcomes for families and individuals at risk of, or experiencing, homelessness. The council has a legal obligation to house people who are legally homeless and vulnerable. They’re placed in temporary accommodation while longer-term housing is found. Because there’s not enough affordable housing, the council often rents costly privately managed temporary accommodation. Some of this cost is refunded by the government, but only up to a limit based on Local Housing Allowance (LHA) rates set in 2011. Anything above this limit is a loss for the council, called a subsidy loss. 2. More details on the aims and objectives of the programme can be found in the full business case report that came to the Committee for Homes and Housing Delivery 4 April 2025, and the updated full business case report that came to the Committee for Homes and Housing Delivery 10 April 2026, both linked in the Background Documents section below. 3. The programme includes the following scope:

Area of work Objectives Scope of work

Increasing the supply of This work will increase the supply of Includes property acquisitions, some Temporary various types of temporary reallocation of properties from Accommodation accommodation, with the aim of General Needs stock, demountable development on small areas of land, 1 Version October 2025

OFFICIAL Area of work Objectives Scope of work

reducing the amount of subsidy loss and entering 11-year leases with compared to current provision. providers of emergency accommodation to stabilise supply over a longer term. New Use of Registered This work will explore how we can Includes exploring the idea of having a Providers (RPs) increase the use of Registered council-owned RP and finding more Providers (RPs), to reduce the opportunities for the council to work amount of subsidy loss incurred by with existing RPs. the council and provide support for households. Increasing Access to the Getting people into PRS tenancies Includes incentivising landlords to Private Rented Sector reduces the burden on social maintain tenancies, helping individuals (PRS) housing and temporary into employment so that they can accommodation. In addition, using afford a private rented tenancy, and the PRS to provide some TA can also encouraging some landlords to lease be better value than some of the their properties to the council to use current provision. as temporary accommodation.

Homelessness Prevention This helps the council to fulfil This includes a service redesign, and Demand housing needs before people reach changes to ways of working to Management the point of experiencing improve processes, and working with homelessness, and reduces the other services in the council and number of placements the council externally to embed a culture of needs to make into TA. homelessness prevention.

Progress to Date

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Equality Impact Assessment: Tackling homelessness programmeAppendix A 368 KB Download
PDF
Tackling Homelessness Transformation Programme (quarterly)Report 174 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 18 attended
BP
Councillor Barry ParsonsChair, present
RE
Councillor Richard EddyVice-Chair, present
KB
Councillor Kerry BailesCommittee Member, present
PG
Councillor Paul GogginCommittee Member, present
RL
Councillor Rob LoganCommittee Member, present
ZP
Councillor Zoë PeatCommittee Member, present
LS
Councillor Lisa StoneCommittee Member, apologies, sent representative
JT
Councillor Jerome ThomasCommittee Member, apologies, sent representative
ST
Councillor Sibusiso TshabalalaCommittee Member, present
AA
Councillor Al Al-MaghrabiCommittee Member, present as substitute
IR
Councillor Izzy RussellCommittee Member, present as substitute
JS
John SmithOfficer, expected

All 18 on the meeting page

On this subject at Bristol

Search all
  1. Tackling Homelessness Transformation Programme (quarterly)This decision
  2. Amendments to the Tackling Homelessness Full Business CaseApproved
  3. Tackling Homelessness Transformation Programme (quarterly)Noted
  4. Tackling Homelessness Transformation ProgrammeDecided
  5. Tackling Homelessness Transformation Programme: Approval to spend against earmarked 2025/26 budgetDecided
  6. Tackling Homelessness Transformation ProgrammeApproved

More from Bristol Homes and Housing Delivery Policy Committee

All decisions
MeetingDecisionOutcome
18 Sep 2026 Q1 (P03) Finance UpdateThe Committee Decided Open
18 Sep 2026 Q1 Corporate Performance UpdateThe Committee RESOLVED : To note the Performance progress report. Noted Open
18 Sep 2026 Housing & Consumer Standards Programme and Compliance UpdateThe Committee RESOLVED : To note the Housing Consumer Standards Programme update (see section 1). To note the July 26... Noted Open
18 Sep 2026 Asset Management StrategyThe Committee (unanimously) Decided Open