Homes and Housing Delivery Policy Committee, Friday 10 April 2026 at 10.00am

Amendments to the Tackling Homelessness Full Business Case

Approved Committee 4 papers

AI summaryBristol City Council approves drawing down £2,039,587 from the transformation fund to continue its Tackling Homelessness Programme into 2026/27, targeting £3,424,305 in recurring annual savings.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAmended full business case for Tackling Homelessness Programme
Money£2,039,587 from transformation fundTargeted £3,424,305 recurring savings in 2026/27
What happens nextMay 2026Final approval needed from Strategy and Resources Committee
Who it affectsHouseholds at risk of homelessnessPeople currently in temporary accommodation

What was decided

The committee approved the amended full business case to continue the programme until December 2026, and in principle approved drawing £2,039,587 from the transformation fund, subject to approval by the Strategy and Resources Committee in May 2026. Report P1, P12

The Executive Director for Housing was authorised, in consultation with the committee chair, to procure and award contracts within the total programme budget to deliver the business case. Report P101

The committee noted a further decision will be sought from the Strategy and Resources Committee on funding to set up a council-owned Registered Provider once that business case is developed. Report P102

Why

The programme aims to cut the council's subsidy loss on temporary accommodation and improve outcomes for people at risk of or experiencing homelessness, who the council has a legal duty to house. Report P3

Demand for temporary accommodation rose sharply, with the council forecasting a potential £8.9m pressure in 2024/25 and ending 2023/24 with a £3m declared budget pressure against £13m of subsidy loss spending. Report P3, P5

The original 2025/26 business case was approved only until March 2026, but the MMC leaseback and demand management projects have been re-scoped to run into 2026/27, so the programme closure date has been pushed to 31 December 2026. Report P12

What happens next

The Executive Director for Housing will procure and award contracts to deliver the programme, with project-level decisions on Partnership Housing, Private Finance Leasing and the Small Sites Aggregator going to future committee meetings. Report P22, P52, P54, P56

A further report will go to the Strategy and Resources Committee in May 2026 to confirm the transformation fund allocation, and later in 2026 to set up a council-owned Registered Provider. Report P102, P112

Programme performance, including whether committed savings can be achieved, will be monitored monthly at the programme board and reviewed in the 2027/28 budget setting process. Report P70

The money

  • £2,039,587 Transformation fund drawdown to deliver the programme in 2026/27 Report P101, P122
  • £3,424,305 Recurring annual savings targeted in 2026/27 Report P101, P68
  • £4,476,067 Revenue cost already approved for 2023/24 to 2025/26 Report P122
  • £34,016,190 Capital cost already approved for 2023/24 to 2025/26 Report P122
  • £9,003,000 Programme savings delivered in 2025/26 as at 26/03/2026 Report P5
  • £4,799,000 Programme savings delivered in 2024/25 Report P5
  • £1,829,000 Programme savings delivered in 2023/24 against a £2,123,000 target Report P3
  • £13m Council spend on temporary accommodation subsidy loss in 2023/24 Report P3
  • £3m Declared budget pressure on subsidy loss at end of 2023/24 Report P3
  • £8.9m Potential forecast pressure on subsidy loss in 2024/25 if no action taken Report P5

Options considered

  • Chosen: Continue the programme into 2026/27 as set out in the amended business case. Required to deliver committed savings and avoid worsening temporary accommodation outcomes Report P99
  • Rejected: Stop the programme. Savings would not be realised, projects would halt and households would be placed in hotels Report P99
  • Rejected: Take forward only some of the new projects. Individual projects can still be halted at their own committee decisions, so this remains available without a programme-level choice Report P99

Implications

  • Financial: The £2,039,587 revenue request from the transformation fund depends on approval at the Strategy and Resources Committee in May 2026, and delivers expected £3,424,305 of recurring annual savings in 2026/27. Report P101, P124
  • Legal: Any procurement using the approved funding must comply with the Procurement Act 2023 and the council's own procurement rules, with legal services advising on contracts. Report P127
  • Risk: The MMC Leaseback project is delayed, with developers concerned about site remediation risk, and the Demand Management and Prevention project is re-scoped after savings fell short in 2025/26. Report P25, P26, P28, P29
  • Equalities: An Equality Impact Assessment is appended at Appendix B; the programme is expected to improve outcomes for households in temporary accommodation, including mental health, education and work prospects. Report P19, P135
  • Climate: An Environmental Impact Assessment is appended at Appendix C; the programme supports the council's carbon neutral objective by working with suppliers to reduce emissions when refurbishing or building properties. Report P104, P105, P106, P136
  • Staffing: Most HR-related activity has already been completed earlier in the programme, and the remainder has no obvious HR implications. Report P132

Who and where

  • People experiencing or at risk of homelessness placed in temporary accommodation, including families previously housed in hotels Report P3, P5
  • Households placed with Registered Providers under supported exempt arrangements Report P7, P25
  • Private rented sector tenants and landlords taking part in the BEAM and private lettings work streams Report P14, P15
  • Council housing and homelessness services staff, with new team structures under the re-designed Housing Options service Report P28, P31

Timeline

  • 28 February 2025: BCC website refocused from homelessness to housing needs (M1 complete) Report P35
  • 4 April 2025: Original full business case approved by Homes and Housing Delivery Committee Report P111
  • 30 April 2025: First draft of Tackling Homelessness dashboard live (M2 completed June 2025) Report P36
  • 18 July 2025: Approval given to enter 10 to 11 year leases on up to 700 Emergency Accommodation Framework properties Report P22, P111
  • 31 March 2026: Original programme closure date under the 2025/26 business case Report P12
  • May 2026: Strategy and Resources Committee to consider approving the transformation fund drawdown Report P124
  • June 2026: Homes and Housing Delivery Committee to consider Partnership Housing Delivery decision Report P22, P52
  • July 2026: Strategy and Resources Committee to consider Private Finance Leasing Arrangement and Small Sites Aggregator decisions Report P22, P54, P56
  • 31 December 2026: New programme closure date, with 3 to 4 projects continuing as standalone projects Report P12, P48

Plain English for the jargon

  • Subsidy loss: The gap between what the council pays for temporary accommodation and what it recovers from central government, which since 2011 has been capped at Local Housing Allowance rates.
  • Temporary accommodation (TA): Short-term housing the council provides to people who are legally homeless and vulnerable while longer-term housing is found.
  • Registered Provider (RP): A social housing landlord, usually a housing association, that lets homes to people in need; placements with RPs carry no subsidy loss for the council.
  • Transformation Fund: Bristol City Council's internal funding pot used to pay for change programmes that generate future revenue savings.
  • MTFP: Medium Term Financial Plan, the council's multi-year budget and savings plan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

It was RESOLVED that the Committee for Homes and Housing Delivery (Unanimously FOR): 1. Approved the amended full business case for continued delivery of the Tackling Homelessness Programme into 2026/27 at Appendix A. 2. Approved in principle the drawing down of £2,039,587 from the transformation fund to deliver the Tackling Homelessness Full Business Case, to deliver recurring annual savings of £3,424,305 in 2026/27, pending the approval of the Transformation Fund at the Committee for Strategy and Resources in May 2026. 3. Authorised the Executive Director for Housing, in consultation with the Chair of the Homes and Housing Delivery Committee, to take all steps required to carry out all decisions and actions necessary to deliver the full business case appended (including procuring and awarding contracts over the key decision threshold), within the total budget envelope of the programme, including contingency (with approval from CLB), as outlined in the Full Business Case. Note: 4. Noted that there will be a further decision sought from the Strategy and Resources Committee on behalf of the New Uses of Registered Providers project, which will request the funding to set up a council-owned RP once the full business case and outline business plan has been developed.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Homes and Housing Delivery Policy Committee

Purpose of report

1. To note that additional scope brought into the Tackling Homelessness Programme in 2025 means that the programme will continue until December 2026, and to approve the programme budget for 2026/27, to be funded by the council’s Transformation Fund.

Evidence Base

1. The Tackling Homelessness programme aims to reduce the council’s use of expensive temporary accommodation (TA), and to provide better outcomes for families and individuals at risk of, or experiencing, homelessness. 2. The council has a legal obligation to house people who are legally homeless and vulnerable. They’re placed in temporary accommodation while longer-term housing is found. 3. Because there’s not enough affordable housing, the council often rents costly privately managed temporary accommodation. Some of this cost is refunded by the government, but only up to a limit based on Local Housing Allowance rates set in 2011. Anything above this limit is a loss for the council, called a subsidy loss. 4. The programme’s key driver is to reduce the amount of spend against the council’s subsidy loss budget, and to secure sufficient accommodation of a range of types for people who are experiencing homelessness or at risk of homelessness. 5. In January 2023, the Temporary Accommodation Project was launched, with the aim of providing cheaper temporary accommodation, and a cashable savings target of £2,123,000 in 2023/24. 6. The project achieved £1,829,000 in savings, but demand increased substantially over the financial year, and at the end of 2023/24 there were over 1600 people in TA, and around 130 families in hotels. In 2023/24, the council spent £13m on subsidy loss and ended the financial year declaring a budget pressure of £3m.

Template approved October 25

OFFICIAL 7. This was mitigated using a one-off grant from national government. However, demand was rising at such a rate that the service was forecasting a potential pressure of up to £8.9m in 2024/25 if no steps were taken to mitigate this. 8. In 2024/25 the programme delivered £4,799,000 savings. It achieved this by: • allocating some general needs housing to use as TA • converting and letting 24 flats leased by the hospital trust for use as TA • using placements with registered providers who joined our registered provider frameworks for families and single people experiencing homelessness • leasing TA from private landlords. 9. The programme also re-commissioned the council’s emergency accommodation framework, setting a cap on the cost of this type of accommodation, with managed inflationary uplifts, to help the council gain some control over expenditure. 10. In 2025/26, the programme has delivered £9,003,000. This is the position on 26/03/2026 and is subject to year-end validation.

Scope

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Amendments to the Tackling Homelessness Full Business CaseReport 306 KB DownloadRead as text
PDF
Tackling Homelessness PROGRAMME BUSINESS CASE V1_03Appendix A 724 KB Download
PDF
Equality Impact Assessment: Tackling homelessness programme V1.1Appendix B 368 KB Download
PDF
Environmental Impact Assessment: TH ProgrammeAppendix C 174 KB Download

At this meeting

Whole meeting

Who was there

9 of 17 attended
BP
Councillor Barry ParsonsChair, present
RE
Councillor Richard EddyVice-Chair, present
PG
Councillor Paul GogginCommittee Member, apologies
CG
Councillor Caroline GoochCommittee Member, present
RL
Councillor Rob LoganCommittee Member, present
ZP
Councillor Zoë PeatCommittee Member, present
LS
Councillor Lisa StoneCommittee Member, present
JT
Councillor Jerome ThomasCommittee Member, present
AA
Councillor Al Al-MaghrabiCommittee Member, present as substitute
ST
Councillor Sibusiso TshabalalaCommittee Member, apologies
KB
Councillor Kerry BailesCommittee Member, present as substitute
DM
David McNultyOfficer, in attendance

All 17 on the meeting page

More from Bristol Homes and Housing Delivery Policy Committee

All decisions
MeetingDecisionOutcome
18 Sep 2026 Q1 (P03) Finance UpdateThe Committee Decided Open
18 Sep 2026 Q1 Corporate Performance UpdateThe Committee RESOLVED : To note the Performance progress report. Noted Open
18 Sep 2026 Housing & Consumer Standards Programme and Compliance UpdateThe Committee RESOLVED : To note the Housing Consumer Standards Programme update (see section 1). To note the July 26... Noted Open
18 Sep 2026 Asset Management StrategyThe Committee (unanimously) Decided Open
18 Sep 2026 Annual Cladding Remediation UpdateThe Committee Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies