Resolved
REFUSED
Plans Sub-Committee No. 2 refused this item on Thursday 6 January 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
REFUSED
SECTION ‘2’ – Applications meriting special consideration
Application No : 10/00657/VAR Ward: Cray Valley East
Address : Bournewood Sand and Gravel Swanley Bypass Swanley BR8 7QH
OS Grid Ref: E: 550231 N: 168274
Applicant : Bournewood Sand and Gravel Ltd Objections : YES
Description of Development:
Variation of conditions 1,12 and 13 of 00/02071 and condition 1 of 08/03444 to allow extraction of Thanet Sand, restoration and recontouring with inert waste and associated access, buildings and structure to continue/ remain until 14th Jan 2018
Proposal
This application in simple terms seeks an extension of time within which to complete the permitted extraction and filling at this site, which is currently required to end and the land be restored by 14th January 2011.
In procedural terms this involves the variation of three conditions from a permission granted in 2000 for the works, and one condition from a permission granted in 2008 for buildings at the site in connection with the works all of which impose a time limit on aspects of the development:
Condition 01 of 00/02071 requires that “The use hereby permitted shall cease on or before the 14th January 2011. The repair shed, security compound comprising 3m high palisade fence around perimeter of the compound, caravan for overnight accommodation for security guard, storage container, mess hut, two storey office/inspection and 3 metre high palisade fence along the northern boundary of the site facility and any associated structures or materials shall be removed from the site on or before the 14th January 2011.”;
Condition 12 of 00/02071 requires that “The use of the means of access to the A20(T) included in the development hereby permitted shall be discontinued, the works and structures removed and the site restored on or before the 14th January 2011.”;
Condition 13 of 00/02071 requires that “The signs approved under reference 99/02071, and more specifically shown on drawing No. 98023/4 shall be maintained as such to the satisfaction of the Traffic Director for London for the duration of the development and removed on or before the 14th January 2011.”; and
Condition 01 of 08/03444 requires that “All of the buildings and structures hereby permitted shall be completely removed from the land on or before 14th January 2011.”
• The period requested for the extension of time is 7 years – to 14th January 2018. • The application supporting documents explain that it is submitted on the basis that it is now not possible to adhere to the original timescale for the excavation and restoration of the land due to progress on site, in particular in order to restore the land within the current timescale would involve sourcing material from a wide area and excessive vehicle trips. • It is stated that the current economic conditions mean that the amount of material available for infilling has been much reduced. • It is further stated that delays in achieving the required licence from the Environment Agency effectively meant that the infilling was delayed by approximately 7 years, only commencing in December 2007.
The application has been the subject of lengthy and detailed negotiations since first submission, and the views of a specialist minerals consultant have been sought to inform this report and the recommendation. He has visited the site. Since the commencement of discussions further information has been submitted. This information informs the headed sections below regarding the primary issues for consideration.
Location
The site is located to the eastern edge of the Borough, between the A20 and railway line on the east and south sides and open land to the north and west. The site is already a working quarry with vehicular access directly onto the A20.
Comments from Local Residents
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
(10/00657/VAR): Bournewood Sand and Gravel, Swanley Bypass, Swanley.Plan | 74 KB | DownloadRead as text |
Follow Plans Sub-Committee No. 2 at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | Apologies for absence and notification of substitute membersApologies received from Cllrs Burden & Phillips. Cllrs Turrell & Barnes attended as respective Substitutes. | Decided | Open |
| 10 Sep 2026 | Declarations of interestNone received. | Decided | Open |
| 10 Sep 2026 | Confirmation of minutes of meeting held on 16th july 2026Confirmed. | Decided | Open |
| 10 Sep 2026 | (25/03676/FPA) - Eltham College, Grove Park Road, Mottingham, London, SE9 4QFREFUSED | Refused | Open |
| 10 Sep 2026 | (25/04904/LDC) -7 Jail Lane, Biggin Hill, Westerham, TN16 3SAREFUSED | Refused | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.