Resolved
APPROVED
Plans Sub-Committee No. 1 approved this item on Thursday 14 April 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
APPROVED
SECTION ‘2’ – Applications meriting special consideration
Application No : 11/00140/VAR Ward: Cray Valley East
Address : Bournewood Sand And Gravel Swanley Bypass Swanley BR8 7QH
OS Grid Ref: E: 550231 N: 168274
Applicant : Bournewood Sand And Gravel Ltd Objections : YES
Description of Development:
Variation of conditions 1,12,13 and 16 of 00/02071 and condition 1 of 08/03444 to allow infilling only of existing quarry with inert waste and restoration with associated access, buildings and structures to continue/ remain until 14 January 2018
Proposal
• This application in simple terms seeks an extension of time within which to complete the infilling only at this site, the permission for which expired on 14th January 2011. • In procedural terms this involves the variation of three conditions from a permission granted in 2000 for the works, and one condition from a permission granted in 2008 for buildings at the site in connection with the works, all of which impose a time limit on aspects of the development:
Condition 01 of 00/02071 requires that “The use hereby permitted shall cease on or before the 14th January 2011. The repair shed, security compound comprising 3m high palisade fence around perimeter of the compound, caravan for overnight accommodation for security guard, storage container, mess hut, two storey office/inspection and 3 metre high palisade fence along the northern boundary of the site facility and any associated structures or materials shall be removed from the site on or before the 14th January 2011.”;
Condition 12 of 00/02071 requires that “The use of the means of access to the A20(T) included in the development hereby permitted shall be discontinued, the works and structures removed and the site restored on or before the 14th January 2011.”;
Condition 13 of 00/02071 requires that “The signs approved under reference 99/02071, and more specifically shown on drawing No. 98023/4 shall be maintained as such to the satisfaction of the Traffic Director for London for the duration of the development and removed on or before the 14th January 2011.; and
Condition 01 of 08/03444 requires that All of the buildings and structures hereby permitted shall be completely removed from the land on or before 14th January 2011.
• The period requested for the extension of time is 7 years to 14th January 2018 • The application supporting documents explain that it is submitted on the basis that it is now not possible to adhere to the original timescale due to progress on site, in particular in order to restore the land within the current timescale would involve sourcing material from a wide area and excessive vehicle trips. • It is stated that the current economic conditions mean that the amount of material available for infilling has been much reduced. • It is further stated that delays in achieving the required licence from the Environment Agency effectively meant that the infilling was delayed by approximately 7 years, only commencing in December 2007.
A further letter setting out the situation at the site was received on 30th March 2011. This letter is from a Minerals Consultant and explains the volume of the remaining void as of 25th March and the average annual tonnage to be filled over the next 7 years, which is 93,400 tonnes per year. This is considered by the consultant to be reasonable based on historic inputs and anticipated economic conditions at this time.
Location
The site is located to the eastern edge of the Borough, between the A20 and railway line on the east and south sides and open land to the north and west. The site is already a working quarry with vehicular access directly onto the A20.
Comments from Local Residents
A number of concerns have been raised by local residents regarding the site and proposal, and additionally activities on land adjacent to the site. Amongst the concerns raised are:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
(11/00140/VAR): Bournewood Sand & Gravel, Swanley Bypass, Swanley.Plan | 61 KB | DownloadRead as text |
Follow Plans Sub-Committee No. 1 at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Aug 2026 | Apologies for absence and notification of substitute membersApologies were received from Councillor Kevin Kennedy Brooks and Councillor Ryan Thompson attended as substitute. Apo... | Decided | Open |
| 13 Aug 2026 | Declarations of interestCouncillor Ryan Thompson declared an interest as a member of Crystal Palace Community Trust and also as a member and ... | Decided | Open |
| 13 Aug 2026 | Confirmation of minutes of meeting held on 18th june 2026The minutes of the meeting held on the 18th of June 2026 were agreed as a correct record. | Agreed | Open |
| 13 Aug 2026 | (26/00815/NOT) - 15 Wickham Road, Beckenham. BR3 5JSPERMISSION GRANTED | Decided | Open |
| 13 Aug 2026 | (26/01021/RES) - Crystal Palace Park, Thicket Road, Penge, London, SE20 8DTAPPROVED | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.