TRANSFORMING BROMLEY 2024-29 YEAR TWO MID-YEAR REPORT 2026/27

Noted Executive 1 paper

AI summaryBromley Executive notes 99.7% of £32.173m 2026/27 transformation savings on track at mid-year; £106k not expected to deliver, with continued corporate oversight of amber savings endorsed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCouncil noted the 2026/27 transformation programme position
Money£32.067m on track (99.7%)of £32.173m programme target, with £106k rated Red
What happens nextCOE Transformation Board continues oversightof £6.582m amber savings across five key proposals
Who it affectsAdult social care, children's services, housingconcentration of amber-rated demand-led savings

What was decided

The Executive noted that £32.067m, or 99.7% of the £32.173m programme value, is on track to deliver, with £25.485m Green and £6.582m Amber, and £106k Red not expected to deliver in year. Report 4.2, 4.7

The Executive endorsed continued corporate oversight of the five amber-rated proposals through the COE Transformation Board chaired by the Chief Executive. Report 4.5, 4.8

Why

Transforming Bromley is the Council's principal mechanism for delivering financial sustainability, service improvement and organisational modernisation, with £32.173m of savings agreed across seven portfolios for 2026/27. Report 4.2

Amber savings of £6.582m are concentrated in five demand-led proposals across adult social care, children's social care and housing, where delivery depends on external conditions such as provider markets, placement sufficiency and tendering timetables. Report 4.5, 4.45

The LGA Corporate Peer Challenge in March 2026 recognised Bromley as a high-performing authority with strong leadership, sound financial management and established transformation capability. Report 4.6

What happens next

Delivery will continue to be monitored bi-monthly by the Corporate Transformation Hub using Red, Amber and Green assessment, with escalation to the COE Transformation Board chaired by the Chief Executive. Report 4.8

Recovery actions are in train for each of the seven amber proposals, including reviews of one-to-one and double-handed care in domiciliary services, continued placement market work, and timing adjustments for IT and Legal restructures. Report P45

Replacement savings will be sought through the 2027/28 pipeline for the £50k lane rental scheme and £16k withdrawn advertising boards proposal. Report P49

The money

  • £32.173m total 2026/27 transformation programme savings target across seven portfolios Report 4.2, P7
  • £32.067m amount on track to deliver at mid-year (99.7% of programme) Report 4.2, 4.7
  • £25.485m savings rated Green (79.2% of programme value) Report 4.7
  • £6.582m savings rated Amber (20.5% of programme value), requiring active management Report 4.7, 4.44
  • £106k savings rated Red (0.3% of programme value), not expected to deliver in 2026/27 Report 4.3, 4.7
  • £12.954m corporate and technical adjustments within the programme, including £9.3m pension fund contribution adjustment, £3m council tax surplus and £634k energy savings Report 4.4
  • £19.219m genuine service transformation savings portion of the programme Report 4.4
  • £2,500k Right Sizing Domiciliary Care Programme (largest amber item) Report 4.5, P45
  • £1,380k Reduction in children looked after (amber, Children, Education and Families) Report 4.5, P45
  • £1,000k 0-25 transformation (amber, Children, Education and Families) Report 4.5, P45
  • £500k Fifteen-year temporary accommodation lease arrangement (amber, Housing) Report 4.5, P45
  • £310k Merger of THRIVE and Staying Together specialist children in care teams (amber) Report 4.5, P45
  • £5m per annum Recurring savings target from right sizing domiciliary care, plus proportionate care for residents Report 4.16
  • £2.7m per annum Expected annual savings from Family Hubs four-hub model from 2027/28 Report 4.22
  • £411k per annum Expected annual savings from Solace Rise children's home, alongside better lived experience for children with complex needs Report 4.22
  • £1.2m Delivered by Encompass specialist foster carer provision, improving continuity of care Report 4.22
  • £1.3m per annum Expected annual savings from the Corporate Review of Housing action plan Report 4.29, 4.32
  • £11m Expected mitigation and future growth reduction by 2030/31 from the Corporate Review of Housing Report 4.32
  • £3.4m Proposals generated through the Ideas Aloud staff engagement initiative in the current programme Report 4.42

Implications

  • Financial: Programme on track to deliver 99.7% of £32.173m savings target, providing strong support to the Medium-Term Financial Strategy. Report 4.2, 4.7
  • Financial: Roughly £12.954m of the total programme arises from corporate and technical adjustments (pension fund, council tax surplus, energy), with £19.219m representing genuine service transformation. Report 4.4
  • Financial: Corporate Reviews to date have generated proposals worth £3.5m rising to £6m per annum, with two further reviews in train covering discretionary services and third-party payments for 2027/28 and beyond. Report 4.41
  • Risk: The £6.582m amber savings are concentrated in five demand-led proposals, meaning the position could move materially on the outcome of a handful of decisions about tenders, placement markets, housing supply and inspection timetables. Report 4.5, 4.44, 4.45
  • Risk: Three red-rated proposals totalling £106k are not expected to deliver in 2026/27: the £50k lane rental scheme depends on a London Councils timetable now pointing to October 2027, £16k roadside advertising boards has been withdrawn due to national policy restrictions, and the £40k closure of Royston Contact Centre has been removed from the savings programme by the Chief Executive. Report 4.3, P49
  • Risk: Bromley has the largest elderly population of any London borough and a substantial self-funder market, both of which make demand-led savings in adult social care harder to realise. Report 4.15
  • Staffing: Evidence from the programme shows 81% of staff able to cite examples of transformation and 91% understanding how to contribute ideas, with strong engagement at the July 2026 Staff Transformation Roadshow. Report 4.42, 4.53
  • Equalities: Service changes in adult social care are designed to support residents to remain at home and at a lower level of care intensity, with assistive technology such as Intelligent Lilli supporting independent living and earlier intervention. Report 4.14, 4.16
  • Equalities: Solace Rise (the Council's first children's home) and the Encompass specialist foster carer arrangements bring provision in-house, giving the Council direct control over quality and cost and keeping more children in placements closer to home. Report 4.20, 4.22
  • Climate: LED retrofitting is expected to deliver a 40% reduction in electricity use across the Council's estate, producing financial and carbon benefits together. Report 4.37

Who and where

  • Adult Care and Health department (£8.483m programme, on track to deliver in full) Report P7, 4.12
  • Children, Education and Families department (£7.809m programme, £7.769m on track, £40k red) Report P7, 4.18
  • Resources, Commissioning and Contracts Management department (£6.961m programme, on track in full) Report P7, 4.24
  • Renewal, Recreation and Housing department (£3.941m programme, on track in full) Report P7, 4.29
  • Environment and Public Protection department (£2.588m programme, £2.522m on track) Report P7, 4.34
  • Chief Executive's and corporate portfolio (£1.991m, all on track) Report P7, 4.39
  • Public Health (£400k of additional grant funding, all on track) Report P7, 4.39
  • Households in temporary accommodation, which fell from 1,803 in September 2025 to 1,469 in August 2026 Report 4.32
  • Adult social care residents receiving reablement, learning disability community support, and assistive technology such as Intelligent Lilli and Magic Notes AI transcription Report 4.16

Timeline

  • September 2025 to August 2026: Households in temporary accommodation fell from 1,803 to 1,469 Report 4.32
  • Mid-year 2026/27: Mid-year position reported to the Executive, with delivery on track for 99.7% of programme value Report 4.2, 4.7
  • March 2026: LGA Corporate Peer Challenge recognised Bromley as a high-performing authority Report 4.6
  • July 2026: Annual Staff Transformation Roadshow 2026 held and positively received Report 4.53
  • March 2027: Anticipated completion date for Legal services staff restructure (full saving from 2027/28) Report P45
  • 2027/28 onwards: Family Hubs and Families First four-hub model expected to deliver £2.7m per annum Report 4.22
  • October 2027: Anticipated start date for the London Councils lane rental scheme Report 4.3, P49
  • By 2030/31: Corporate Review of Housing expected to deliver around £11m of mitigation and future growth reduction Report 4.32

Plain English for the jargon

  • RAG rating: Red, Amber, Green assessment used to track savings delivery: Green is on or ahead of plan, Amber has a realistic path to recovery through active management, Red is significantly behind target with low confidence of delivery.
  • COE Transformation Board: Corporate Officer Executive Transformation Board chaired by the Chief Executive, which oversees delivery of the Transforming Bromley programme.
  • Right Sizing Domiciliary Care Programme: Transformation programme to ensure residents receive care proportionate to need, with reviews of one-to-one and double-handed care, designed to deliver £5m per annum on a recurring basis.
  • Solace Rise: The Council's first in-house children's home, now open, delivering £411k per annum alongside better lived experience for children with complex needs.
  • Family Hubs / Families First: Programme to integrate children and family centres and youth hubs into a four-hub model aligned with the Integrated Care Board, expected to deliver £2.7m per annum from 2027/28.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item33

Resolved

That 1. It be noted that £32.067m, or 99.7% of the programme value, is on track to deliver, £25.485m is rated Green (79.2%) and £6.582m rated Amber (20.5%) with realistic recovery plans in place. £106k is rated Red (0.3%) and is not expected to be delivered in year. 2. It be noted that the Amber value requiring active management is concentrated in five proposals within adult social care, children's social care and housing, and the continued corporate oversight of these through the COE Transformation Board be endorsed.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive

Executive summary

4.2Transforming Bromley is the Council's principal mechanism for delivering financial sustainability, service improvement and organisational modernisation. For 2026/27 the programme carries £32.173m of savings agreed across seven portfolios. At the mid-point of the year the programme is on track to deliver £32.067m, or 99.7% of its target.

4.3Only £106k, or 0.3% of the programme value, is rated Red. Three proposals account for this shortfall: the closure of Royston Contact Centre at £40k, which the Chief Executive has agreed will be removed from the savings programme; the lane rental scheme at £50k, dependent on a London Councils timetable now pointing to October 2027; and roadside advertising boards at £16k has been withdrawn due to national policy restrictions. None is individually material to the Medium-Term Financial Strategy.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TRANSFORMING BROMLEY 2024-29 YEAR TWO MID-YEAR REPORT 2026/27Report 239 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
CS
Councillor Colin SmithChairman, present
KL
Councillor Kate LymerVice-Chairman, present
JA
Councillor Jonathan AndrewsCommittee Member, present
YB
Councillor Yvonne BearCommittee Member, present
JC
Councillor Josh Coldspring-WhiteCommittee Member, present
SF
Councillor Simon FawthropCommittee Member, present
AP
Councillor Angela PageCommittee Member, present
DS
Councillor Diane SmithCommittee Member, present
RM
Councillor Ruth McGregorGuest, in attendance
SS
Councillor Shaun SlatorGuest, in attendance
AD
Councillor Andy DourmoushGuest, in attendance

On this subject at Bromley

Search all
  1. TRANSFORMING BROMLEY 2024-29 YEAR TWO MID-YEAR REPORT 2026/27This decision
  2. Transforming bromley 2024-2028 two year progress report 2025-26Noted
  3. Transforming bromley 2024-28 year one progress report 2024/25Noted
  4. Transforming bromley 2024-28Noted
  5. Transforming bromley 2019--2023: first two yearsNoted
  6. Transforming bromley 2019 - 2023: first two yearsNoted

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open