CAPITAL PROGRAMME MONITORING - QUARTER 1 2026/27

Decided Scrutiny 1 paper

AI summaryBromley's Children, Education and Families committee supported the Q1 2026/27 capital programme monitoring report, with changes to be considered by the Executive on 16 September 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedRecommendations in Q1 capital monitoring report supported
Money177,994 (in £'000)Total approved scheme estimate for the portfolio
What happens nextExecutive on 16 September 2026Full financial implications to be reported
Who it affectsSchools and family servicesChildren, Education and Families portfolio schemes

What was decided

The committee supported the recommendations set out in the Q1 2026/27 capital programme monitoring report.

Changes to the Children, Education and Families capital programme will go to the Executive for consideration on 16 September 2026. Report 5.1

The committee noted that capital programme monitoring is part of the planning and review process for all services. Report 6.1, P2

Why

The capital review process requires Chief Officers to ensure bids provide value for money and match Council plans and priorities. Report 6.1, P2

Several 2025/26 schemes had underspends that are being reprofiled into 2026/27, and some 2026/27 spend is being rephased to reflect current project delivery. Report P10, P17

What happens next

The Executive will consider the financial implications in full on 16 September 2026. Report 5.1

Basic Need and capital maintenance spend in 2026/27 will be rephased to reflect current project delivery, with focus on boiler upgrades at Riverside school. Report P10

Retention monies for the new children's home are due to be paid to the contractor in January 2027, and the Transforming Children's and Family Centres project is to be closed once a final balance of 3 (£'000) is returned. Report P10

The money

  • 177,994 Total approved scheme estimate for the Children, Education and Families portfolio (£'000) Report P8
  • 116,276 Spend to 31.03.26 on the portfolio (£'000) Report P8
  • 12,855 Rephased 2026/27 estimate for the portfolio (£'000) Report P14
  • 16,971 Original 2026/27 estimate for the portfolio (£'000) Report P14
  • 1,199 Actual spend at Q1 2026/27 on the portfolio (£'000) Report P14
  • 10,076 2025/26 estimate for the portfolio (£'000) Report P18
  • 7,508 2025/26 outturn for the portfolio (£'000) Report P18
  • 2,569 2025/26 variance (underspend) reprofiled into 2026/27 (£'000) Report P18

Options considered

  • Chosen: Support the recommendations in the report. Reflects rephasing and project delivery updates for the Children, Education and Families capital programme Report P10

Implications

  • Financial: Full financial implications to be considered by the Executive on 16 September 2026. Report 5.1
  • Financial: Several 2025/26 schemes ended the year as underspends, with the totals reprofiled into 2026/27; small overspends on CEF Digital Transformation, OPR SEN Services and OPR youth centres are to be mitigated from future year budgets. Report P17
  • Other: The new children's home is complete and now occupied by Barnardo's; the Transforming Children's and Family Centres project returned an underspend of 100 (£'000) to the capital programme, with a final 3 (£'000) balance still to be returned. Report P10

Who and where

  • Children, Education and Families portfolio services in Bromley Report P8
  • School capital schemes, including Basic Need and capital maintenance Report P5, P10
  • Operational Property Review schemes covering adult education, children and family centres, SEN services and youth centres Report P6, P7
  • Barnardo's as operator of the new children's home Report P10

Timeline

  • Q1 2026/27: Reporting period for the capital programme monitoring Report P9, P14
  • 2025/26 outturn: Portfolio outturn of 7,508 against estimate of 10,076 (£'000), with 2,569 (£'000) variance reprofiled into 2026/27 Report P18
  • 16 September 2026: Executive to consider the financial implications in full Report 5.1
  • 2026/27 to 2030/31: Forward capital programme spend profile for the portfolio Report P8
  • January 2027: Retention monies due to the contractor for the new children's home Report P10

Plain English for the jargon

  • Basic Need: Government funding for additional school places
  • Devolved Formula Capital: Direct funding to schools for capital, paid as a government grant
  • DfE: Department for Education
  • OPR: Operational Property Review
  • S106: Section 106 planning obligation funding from developers
  • Rephasing: Moving planned spend from one year to a later year in the capital programme
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item23b

Resolved

That the recommendations in the report be supported.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Children, Education and Families Policy Development and Scrutiny Committee

Report No. London Borough of Bromley FSD26041 PART 1 – PUBLIC

Title: CAPITAL PROGRAMME MONITORING - QUARTER 1 2026/27

Decision Maker: PORTFOLIO HOLDER FOR CHILDREN, EDUCATION, AND FAMILIES

Date: 8 September 2026

For Pre-Decision Scrutiny by the Children, Education and Families Policy Development and Scrutiny Committee Decision Type: Non-Urgent Executive Non-Key

Contact Officer: Abdul Munim, Head of Capital, Treasury and Banking Tel: 0208 313 4334 E-mail: [email protected]

Chief Officer: Peter Turner, Director of Finance

Ward(s): All Wards

1. REASON FOR REPORT

1.1On 16 September 2026, the Executive will receive a report summarising the current position on capital expenditure and receipts following the first quarter of 2026/27 and be asked to agree a revised capital programme for the period 2026/27 to 2030/31. This report highlights changes to be considered by the Executive in respect of the capital programme for the Children, Education and Families portfolio. The revised programme for this portfolio is set out in Appendix A and detailed comments on individual schemes are shown in Appendix B; while Appendix C details the variance between the 2025/26 budget and the outturn position at year end.

________________________________________________________________________________

2. RECOMMENDATION(S)

2.1The Portfolio Holder is asked to note and acknowledge the current position in respect of capital schemes, to be considered by the Executive on 16 September 2026.

1 3. KEY SUMMARIES ________________________________________________________________________________ Financial 1. Cost of proposal: Not Applicable 2. Ongoing costs: Not Applicable 3. Budget head/performance centre: Capital Programme 4. Total current budget for this head: £61.7m 5. Source of funding: Capital grants, capital receipts, external borrowing and earmarked revenue reserves. ________________________________________________________________________________ Legal 1. Legal Requirement: Non-Statutory - Government Guidance 2. Call-in: Applicable ________________________________________________________________________________

Background Capital Programme Monitoring Q1 25/26 (Executive 17/09/2025) Documents: Capital Programme Monitoring Q2 25/26 (Executive 26/11/2025) (Access via Contact Capital Programme Monitoring Q3 25/26 (Executive 11/02/2026) Officer) Capital Programme Outturn 25/26 (Executive 24/06/2026)

2 4. COMMENTARY

Capital monitoring – variations to be considered by the Executive on 16 September 2026

4.1A revised capital programme will be considered by the Executive on 16 September 2026, following a detailed monitoring exercise carried out after the first quarter of 2026/27. The base position is the programme approved by the Executive on 11 February 2026, as amended by variations approved at subsequent Executive meetings. All changes to schemes in the Children, Education and Families portfolio programme are itemised in the table below and further details are included in paragraphs 4.2 and 4.5. The revised programme for the Children, Education and Families Portfolio is attached as Appendix A, whilst Appendix B shows actual spend against budget up to the end of the first quarter of 2026/27, together with detailed comments on individual scheme progress.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitoring: Quarter 1 2026/27Report 209 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 18 attended
MB
Councillor Mark BrockChairman, present
HG
Councillor Hannah GrayVice-Chairman, present
DB
Councillor Daniel BurdenCommittee Member, apologies, sent representative
GC
Councillor Graeme CaseyCommittee Member, present
JC
Councillor Jenny ColemanCommittee Member, present
GC
Councillor Giles CordwellCommittee Member, present
MD
Councillor Michael DobleCommittee Member, present as substitute
SG
Councillor Serena GuptaCommittee Member, present as substitute
PP
Councillor Panos PapayannakosCommittee Member, present
AP
Councillor Alwin PuthenpurakalCommittee Member, apologies, sent representative
WR
Councillor Will RawlesCommittee Member, present
RT
Councillor Ryan ThomsonCommittee Member, present

All 18 on the meeting page

On this subject at Bromley

Search all
  1. CAPITAL PROGRAMME MONITORING - QUARTER 1 2026/27This decision
  2. Capital programme monitoring - quarter 1 2026/27Noted
  3. Capital programme monitoring - quarter 1 2026/27Decided
  4. 2026/27 q1 capital programme monitoringNoted
  5. Capital programme monitoring - quarter 1 2026/27Decided
  6. Capital programme monitoring - quarter 3 2025/26Noted

More from Bromley Children, Education and Families Policy Development and Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Appointment of coopted memberThat the following Co-opted Membership appointment be made to the Children, Education and Families PDS Committee for ... Decided Open
8 Sep 2026 Minutes of the children, education and families pds committee meeting held on 10 june 2026That the minutes of the meeting held on 10 June 2026 be agreed and signed as a correct record. Agreed Open
8 Sep 2026 Matters outstanding and forward work programmeThat progress on matters arising from previous meetings and the forward work programme be noted. Noted Open
8 Sep 2026 Portfolio holder updateThat the update be noted. Noted Open
8 Sep 2026 Children, education and families portfolio plan - 2026/27 q1 updateThat progress on actions associated with the Children, Education and Families Portfolio Plan be noted. Noted Open