AI summaryBromley Executive approved £16.2m of increases to existing capital schemes and £389k for two new projects, noted £37.1m rephased from 2026/27 to later years, and added £250k for Ethelbert Close care leavers accommodation.
Written from the decision and the officer reportPDF Pro
OutcomeNotedIncreases, reductions, rephasing and new schemes approved
MoneyNot stated
What happens nextQuarterly DfT incentive funding submissionsWaldo Road completion forecast July 2027
Who it affectsWaste, housing, highways and children servicesCouncil assets, residents and capital receipts
What was decided
The Executive noted £37.1m rephased from 2026/27 into future years and approved £16,205k of increases to existing schemes, a net £11,286k of monitoring reductions, £389k for two new schemes, and £250k for the Ethelbert Close Care Leavers repairs scheme. Report P20, P21, P22
An additional £4.944m was approved for the Waldo Road Depot Improvement Scheme, taking the revised forecast to £15.763m against an original £11.0m budget. Report P41, P46
Officers set out a projected capital financing shortfall from 2028/29 onwards, with further borrowing likely unless the council's financial position improves. Report 5.4, P30, P32
Why
Q1 monitoring set out rephasing, cost variations and new bids; chief officers are required to ensure capital bids provide value for money and match council priorities. Report 7.1, P14, P17, P20
The Waldo Road increase was driven by unforeseen site conditions including asbestos, underground oil tanks, contaminated soils, an unknown well, structural issues, approval delays and ongoing operational mitigation costs. Report P42, P50, P51, P52, P53, P54, P55
The Bromley North unit was preferred for the Our House project because it is council owned, new build with lower running costs, and avoids uncontrolled future rent and service charge rises. Report P77, P83, P84
What happens next
Officers will continue active project governance on Waldo Road, with a post completion report covering additional costs, liquidated damages and lessons learned. Report P44, P56, P63, P70, P75
A separate report will be taken to the relevant portfolio holder to seek authority to tender for the design and build contract for Our House at Bromley North, funded by external borrowing. Report P85
The council will continue submitting required information to the DfT each quarter to secure the highways maintenance incentive fund and monitor the impact of further potential schemes on the capital programme. Report P6, 6.2, 6.3, 6.4, P94, P96
The money
£37.1m Total rephasing from 2026/27 into future years Report P20, P27
£16,205k Total increase to various existing schemes Report P17, P18
£11,286k Net reduction from monitoring adjustments Report P21
£389k Addition of two new schemes (Our House Bromley North £300k and Gul-E EV footway channels £89k) Report P17, P85, P88
£250k Supported Accommodation Care Leavers Ethelbert Close Repairs Scheme budget allocation
£4.944 million Further forecast allocation for the Waldo Road Depot Improvement Scheme Report P17, P41, P46, P48
£15.763 million Revised total forecast cost for the Waldo Road Depot Improvement Scheme Report P41, P46, P48
£11.0 million Original capital budget for the Waldo Road Depot Improvement Scheme Report P41
£300,000 Estimated total capital cost to LBB of locating Our House at Bromley North Report P82, P85
£16.237m plus £372k Highways maintenance grant allocation received by the council Report P94
£7.3 billion National highways maintenance funding announced by government for the next four years Report P94
£89,000 Council share of DfT/OZEV grant for pavement EV charging channels Report P17, P88
Options considered
Chosen: Locate Our House in a ground floor unit at the new Bromley North housing scheme at £300,000 capital cost and £25,000 foregone rent per year. Council owned, brand new building with lower running costs, no lift, design influence during build, removes uncontrolled future rent and service charge risk Report P77, P81, P82, P83, P84, P85
Rejected: Locate Our House in space within the Churchill Theatre and Central Library building at £20,000 capital cost but £60,000 per year in rent, service charge and fit out. Higher revenue cost, temporary nature of site, and risk of costs rising outside the council's control Report P81, P82, P83
Chosen: Approve additional £4.944m funding for the Waldo Road Depot Improvement Scheme to enable completion. Failure to approve would risk scheme completion, prolong operational disruption and increase delay related costs; revised forecast cost is £15.763m Report P41, P44, P46
Implications
Financial: A capital financing shortfall is projected from 2028/29 onwards caused by increased capital expenditure and use of usable capital receipts, with further borrowing likely unless the financial position improves. Report 5.4, P30, P32
Risk: Several potential future schemes are excluded from this programme including park building works, further depot works, replacement of key IT systems, respite facilities, property compliance works, new invest to save schemes and outcomes of the estate review; they may add significant cost later. Report 6.1, P6, 6.2, 6.3, 6.4
Risk: Waldo Road project risks include further unforeseen ground conditions, ongoing contractor delay and loss and expense claims, inflationary pressures, additional operational mitigation costs if reopening is delayed, and remaining construction programme risks. Report P44, P63, P64, P65, P66, P67, P68
Equalities: The Our House relocation supports the council's duties as Corporate Parents and strategic priority of helping care leavers thrive, reducing future risk of entry to adult social care. Report P78, P79
Climate: The completed Waldo Road scheme is expected to support the council's environmental and sustainability objectives, including its ambition to remain London's leading borough for recycling performance; the Gul-E EV footway channels scheme subsidises pavement EV charging for residents. Report P40, P61, P87, P88, P89, P92
Other: Officers will run a Post Completion Report at the end of the Waldo Road project covering additional costs, liquidated damages and lessons learned. Report P56
Who and where
Council tenants and residents using the Reuse and Recycling Centre at Waldo Road, with the centre forecast to reopen November 2026 and transfer station overall completion July 2027 Report P41, P43, P48, P59
Children in care aged 11 to 18 and care leavers aged 18 to 25 who will use the new Our House facility at Bromley North Report P78, P79
Around 280 to 300 households expected to benefit from subsidised Gul-E pavement EV charging installations Report P91, P92, P93
Future capital programme users and council taxpayers, who will bear further borrowing costs and the projected financing shortfall from 2028/29 onwards Report 5.4, P30, P32, P34
Timeline
February 2025: Waldo Road Depot Improvement Scheme commenced on site Report P43, P47
December 2025: Government announced £7.3 billion highways maintenance funding for the next four years; Bromley's share £16.237m plus £372k Report P94
February 2026: Council successful in DfT/OZEV application for £89,000 share of pavement EV charging fund Report P88
11/02/2026: Current approved capital programme approved by the Executive Report P14
16/09/2026: Q1 2026/27 capital programme monitoring reported to the Executive Report P12
November 2026: Reuse and Recycling Centre at Waldo Road forecast to reopen Report P43
April 2027 (estimate): Bromley North unit for Our House forecast to be ready for occupation Report P81
July 2027: Waldo Road transfer station overall completion forecast Report P43
2028/29 onwards: Capital financing shortfall projected to begin Report P30, P32
Plain English for the jargon
Capital programme: The council's multi-year plan for spending on assets such as buildings, infrastructure and major equipment
Rephasing: Moving the planned timing of capital spending between financial years
Usable capital receipts: Proceeds from selling council assets that can be used to fund new capital expenditure
Internal borrowing: Temporary use of the council's own cash balances to fund capital spending, to be refinanced by external borrowing later
Our House: Council facility for children in care aged 11 to 18 and care leavers aged 18 to 25, providing a supported social space and self-care skills
DfT: Department for Transport
OZEV: Office for Zero Emission Vehicles
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item32
Resolved
That 1. The contents of the report, including a total rephasing of £37.1m from 2026/27 into future years as detailed in section 4.8 be noted; 2. The following amendments to the Capital Programme be approved: (a) A total increase of £16,205k to various existing schemes as detailed in paragraph 4.5.1 to 4.5.7; (b) Adjustments identified as part of the capital monitoring process totalling a net reduction of £11,286k as detailed in section 4.7; and (c) The addition of £389k for two new schemes as detailed in paragraphs 4.9.2 and 4.9.3. (d) The inclusion of the Supported Accommodation Care Leavers – Ethelbert Close Repairs Scheme to the Capital Programme, with a budget allocation of £250k be approved.
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
Report No. London Borough of Bromley FSD26037 PART 1 – PUBLIC
Title: CAPITAL PROGRAMME MONITORING – QUARTER 1 2026/27
Decision Maker: EXECUTIVE
Date: 16 September 2026
Decision Type: Non-Urgent Executive Key
Contact Officer: Abdul Munim, Head of Capital, Treasury and Banking Tel: 0208 313 4334 E-mail: [email protected]
Chief Officer: Peter Turner, Director of Finance
Ward(s): All
1. REASON FOR REPORT
1.1This report summarises the current position on capital expenditure and receipts following the conclusion of the first quarter of 2026/27 monitoring exercise.
1.2The report also includes details of proposed new schemes and additions to existing schemes, as well as reduction in budgets and the removal of various schemes that are now either complete or no longer being progressed.
1.3Also included are details of the related Capital Financing implications and the projected shortfall in capital resources and details of how these proposals will impact the Council’s revenue budget. ________________________________________________________________________________
2. RECOMMENDATION(S)
2.1The Executive is requested to:
(a) Note the contents of the report, including a total rephasing of £37.1m from 2026/27 into future years as detailed in section 4.8;
(b) Approve the following amendments to the Capital Programme: i. A total increase of £16,205k to various existing schemes as detailed in paragraph 4.5.1 to 4.5.7;
ii. Adjustments identified as part of the capital monitoring process totalling a net reduction of £11,286k as detailed in section 4.7; and
iii. The addition of £389k for two new schemes as detailed in paragraphs 4.9.2 and 4.9.3. 1 3. KEY SUMMARIES ________________________________________________________________________________ Financial 1. Cost of proposal: Total net increase of £21.8m over the five years 2026/27 to 2030/31 2. Ongoing costs: As detailed above 3. Budget head/performance centre: Capital programme 4. Total current budget for this head: Total £394.6m over the period 2026/27 to 2030/31 5. Source of funding: Capital grants, capital receipts, external borrowing and earmarked revenue reserves. ________________________________________________________________________________ Legal 1. Legal Requirement: Statutory Requirement 2. Call-in: Applicable ________________________________________________________________________________
Background Capital programme monitoring Q1 25/26 (Executive 17/09/2025) Documents: Capital programme monitoring Q2 25/26 (Executive 26/11/2025) (Access via Contact Capital programme monitoring Q3 25/26 (Executive 11/02/2025) Officer) Capital programme Outturn 25/26 (Executive 24/06/2026)
2 4. COMMENTARY
Updated Capital Position
4.1This report sets out proposed changes to the Capital Programme following a detailed monitoring exercise carried out after the first quarter of 2026/27.
4.2Appendix A summarises the proposed changes to the Capital Programme. The base position is the revised programme approved by the Executive on 11th February 2026, as amended by variations approved at subsequent meetings.
4.3If all the changes proposed in this report are approved, the total Capital Programme 2026/27 to 2030/31 would increase by £21.8m, mainly due to the inclusion of new capital bids, partly offset by reductions to existing schemes and removal of completed schemes. Planned capital expenditure of £37.1m will be re-phased from 2026/27 into future years.
4.4Details of the monitoring variations are included in Appendices A and B, and the proposed revised programme, including the additional funding provided, is summarised in the table below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.