GATEWAY 1 - PROCEEDING TO PROCUREMENT FOR ADVISORY PARTNER TO THE BETTER LIVES PROGRAMME
AgreedExecutive1 paper
AI summaryBromley Executive agrees to procure an advisory partner for the Better Lives Programme, a transformation of Working Age Adults social care, with an estimated £500K Phase 1 cost funded from reserves.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedProceed to open tender for advisory partner
Money£500K Phase 1, £4.5m-£5.5m Phase 2Funded from council reserves initially
What happens nextTender issued on Find a Tender Service. Phase 1 decision on Phase 2 follows
Who it affectsWorking age adults receiving social careEspecially adults with learning disabilities
What was decided
The Executive agreed to proceed to procurement for an advisory partner to support the transformation of services to Working Age Adults under the Better Lives Programme, using an open tender procedure. Report 13.1
Council reserves will be drawn upon to fund the procurement and associated work, treated as an invest to save proposal. Report 10.2
The contract will operate in two parts: a 12-week Phase 1 review at an estimated £500K, and a Phase 2 implementation support estimated at £4.5m to £5.5m, with the Phase 2 decision reserved to the Executive. Report 13.1
Why
The Council wants to transform services to working age adults, with a stated focus on improving outcomes for adults and children with a disability. Report 11.2
The programme will contribute to mitigating financial risks on the Council's Adult Social Care Risk Register and support the Making Bromley Even Better priorities. Report 16.1, 17.1
Currently too many residents with a learning disability are supported in residential care outside the borough, and the Council spends around £54m per annum on adults with a learning disability. Report 20.1, 20.2
What happens next
A Tender Notice will be published on the Find a Tender Service and the procurement will be run via the Council's e-procurement system in line with the Procurement Act 2023. Report 13.4
Legal Services will review and settle procurement documentation and contractual arrangements before publication. Report 11.5
Phase 1 outcomes will be reported back to the Executive, who will then decide whether to proceed to Phase 2, with or without the advisory partner.
The money
£500k Estimated cost of Phase 1, to be borne from reserves as invest to save Report 10.2, P8
£4.5m to £5.5m Estimated cost of Phase 2 advisory partner implementation Report 13.1
£6.5m Total estimated partner cost across all years Report P8
£0.35m Additional staffing cost per annum for first two years of Phase 2 Report P10, 10.3
£7.2m Subtotal of all costs across the programme Report P11
£4.3m Interest and repayment of principal on precipitated borrowing Report P13
£(7.0m) Total cumulative cashable savings Report P15
£(2.4m) Total cumulative cost avoidance Report P19
c.£54m Annual Council spend on adults with a learning disability Report 20.1
Options considered
Chosen: Two-part contract: Phase 1 review then Phase 2 implementation. Allows the Executive to decide on Phase 2 after seeing Phase 1 outcomes; no further contractual obligation if Phase 2 not pursued Report P21
Chosen: Fund from reserves as invest to save. Costs to be recovered from savings generated by the project; reserves carry interest rate and balanced budget risks Report 10.2, P22, P23
Implications
Legal: The contract is an above-threshold public services contract under the Procurement Act 2023 and must comply with its transparency, notice and competitive tendering requirements; the Council relies on the general power of competence under section 1 of the Localism Act 2011. Report 11.2, 11.3
Staffing: Provision of £350K per annum covers project management support and resources for additional assessments, care plan reviews and co-production with residents, to be determined at implementation. Report 12.1
Risk: Interest rate and balanced budget risks arise from the use of reserves and precipitated borrowing, while the programme is expected to mitigate financial risks on the Adult Social Care Risk Register. Report P22, 16.1
Other: Property implications are likely to emerge from the final delivery plan and will be raised with PDS Committees and the Executive during implementation. Report 14.1
Equalities: The programme has the specific intention of improving outcomes for adults and children with a disability and their health and wellbeing.
Who and where
Working age adults receiving adult social care from Bromley Council Report 11.1
Adults and children with a disability and their carers Report 22.1, 22.2
Local voluntary, community and not for profit organisations that hold care and support contracts with the Council Report 20.1
All wards in the London Borough of Bromley Report 23.1
Timeline
2026-27: Phase 1 partner cost of £0.5m to be spent from reserves Report P8
2027-28: Phase 2 partner cost of £5.0m plus £0.35m staffing and cumulative cashable savings of £(0.6m) and cost avoidance of £(0.2m) Report P8, P10, P15, P19
2028-29: Phase 2 partner cost of £1.0m plus £0.35m staffing and cumulative cashable savings of £(4.0m) and cost avoidance of £(1.5m) Report P8, P10, P15, P19
2029-30: Cumulative cashable savings of £(6.0m) and cost avoidance of £(2.1m) Report P15, P19
2030-31: Cumulative cashable savings of £(6.7m) and cost avoidance of £(2.4m) Report P15, P19
2031-32: Cumulative cashable savings of £(7.0m) and cost avoidance of £(2.4m) Report P15, P19
Plain English for the jargon
Better Lives Programme: Bromley's transformation programme for Adult Social Care services to working age adults
Gateway 1: Approval stage requiring Executive authorisation before procurement can proceed under the Council's Contract Procedure Rules
Invest to save: Spending funded from reserves that is expected to be recovered from future savings generated by the project
Precipitated borrowing: Borrowing that the Council must undertake when reserves are used to fund capital expenditure, creating interest and Minimum Revenue Provision costs
Minimum Revenue Provision: The repayment of principal on borrowing that councils must make from revenue each year
Open Procedure: A procurement route under the Procurement Act 2023 open to all interested bidders
PA23 Regulations: The Procurement Act 2023 regulations governing above-threshold public procurements
General power of competence: Power under section 1 of the Localism Act 2011 allowing councils to do anything an individual can do, subject to limits
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item34
Resolved
That 1. T he proceed to procurement for an advisory partner to support the transformation of services to Working Age Adults, the Better Lives Programme be agreed. 2. It be agree that Council reserves are drawn upon to fund this procurement and associated work as described in the report. 3. It be agreed that the contract will operate in two parts. Phase 1 will involve a 12-week detailed review of current provision and costs to size the opportunities and develop a plan for change at an estimated cost of £500K. Subject to further agreement, a Phase 2 will involve the advisory partner supporting the Council in the implementation of the plan at an estimated £4.5m to £5.5m. The decision to proceed to Phase 2, with or without the support of the advisory partner, will be made by the Executive following a report on the outcome of the Phase 1 work.
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
Report No. London Borough of Bromley ACH26-042 PART 1 – PUBLIC
Title: GATEWAY 1 - PROCEEDING TO PROCUREMENT FOR ADVISORY PARTNER TO THE BETTER LIVES PROGRAMME
Decision Maker: EXECUTIVE
Date: 16 September 2026 For pre-decision scrutiny by the Executive, Resources and Contracts PDS Committee on 14 September 2026 Decision Type: Urgent Non-Urgent Executive Non-Executive Key Non-Key
Contact Officer: Sean Rafferty, Assistant Director of Integrated Commissioning Tel: 0208 8313 4103 E-mail: [email protected]
Chief Officer: Donna Glover, Director of Adult Social Services
Ward(s): ALL
1. REASON FOR REPORT
1.1This report seeks Executive approval to procure a contract for the appointment of an advisory partner to support the Council’s Working Age Adults Transformation Programme – The Better Lives Programme.
1.2This programme of work is to be delivered in support of the Bromley Learning Disabilities Strategy 2025-2030 to achieve better outcomes for local residents and develop a more financially sustainable model of support in the Borough.
1.3The report recommends an open tender process to appoint a suitably experienced advisory partner to assist the Council to undertake a review of current provision and costs to size the opportunities and develop a plan for change with a further option to then support the Council in the implementation of the plan.
2.2Agree the proceed to procurement for an advisory partner to support the transformation of services to Working Age Adults, the Better Lives Programme.
2.3Agree that Council reserves are drawn upon to fund this procurement and associated work as described in the report.
1 2.4 The contract will operate in two parts. Phase 1 will involve a 12-week detailed review of current provision and costs to size the opportunities and develop a plan for change at an estimated cost of £500K. Subject to further agreement, a Phase 2 will involve the advisory partner supporting the Council in the implementation of the plan at an estimated £4.5m to £5.5m. The decision to proceed to Phase 2, with or without the support of the advisory partner, will be made by the Executive following a report on the outcome of the Phase 1 work.
3. KEY SUMMARIES ________________________________________________________________________________ Financial 1. Cost of proposal: £7.2m 2. Ongoing costs: £8.96m in total 3. Budget head/performance centre: Adult Social Care 4. Total current budget for this head: £Not Applicable as to be funded from reserves 5. Source of funding: Reserves ________________________________________________________________________________ Legal 1. Legal Requirement: None: Further Details 2. Call-in: Applicable ________________________________________________________________________________
Background Documents: Bromley Learning Disabilities Strategy 2025 to 2030 (Access via Contact Officer)
2 4. BACKGROUND
The Bromley Learning Disabilities Strategy
4.1The Council’s focus for transforming Adult Social Care outcomes and costs over the last 10 years has been, in the main, directed at the Borough’s growing older people population and a series of initiatives have been delivered, and or are in train , to improve outcomes and deliver services in a cost effective way to these residents. The next transformation priorities for Adult Services need to be concerned with prevention activities and services to Working Age Adults (WAA), i.e. adults with learning disabilities and or complex physical disabilities, with a view to managing demand, improving residents’ lives and reducing costs.
4.2In 2025 the Council, with the South East London Integrated Care Board (SELICB), agreed a Learning Disabilities Strategy that was co-produced with residents with a learning disability and their carers. The themes for developing local support to adults with a learning disability were agreed as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.