RESOLVED that: 1. A delegation be made to the Deputy Chief Executive, following consultation with the Beeston Town Centre Project Board and the group leaders and their depoties, authority to award a building contract for the Beeston Town Centre Phase 2 based on qualitative and quantitative analysis of tenders. 2. That the other capital budget variations for 2019/20 be approved.
Word for word from the decision Broxtowe published for this meeting.Source: democracy.broxtowe.gov.uk
To seek approval for a number of capital budget variations in respect of the 2019/20 financial year.
Background
Examination of the approved capital programme for 2019/20 has resulted in a number of proposed amendments to the 2019/20 capital programme. Further details are set out in appendix 1 with a financial summary shown in appendix 2.
Included in appendix 1 is an in-depth analysis of the anticipated expenditure and accompanying financing of the Beeston Town Centre Phase 2 Development. This provides details of expenditure incurred in 2018/19 and current projections for the scheme over the following years.
Tender invitations were sent out to a shortlist of 5 contractors on 7 June 2019. The Project Board is due to review responses on 12 August 2019 with a view to selecting a construction partner. Bids will be evaluated on a combination of quality and cost. The Council’s Financial Regulations (section 9.3) requires the evaluation of tenders in excess of £25,000 that include a qualitative evaluation to be presented to the appropriate Committee with a recommendation as to the tender that should be accepted and the basis for such a recommendation. The Committee cycle will not allow for this without significant delay (and potential cost) to the project. Accordingly, the Committee is requested to waive this requirement, particularly in view of the Project Board’s cross-party representation and delegate authority to the Deputy Chief Executive to award the building contract following the consideration of the tenders by the Project Board.
Recommendations
The Committee is asked to:
1. RECOMMEND to Council on 17 July 2019 that the budget in the 2019/20 capital programme for the Beeston Town Centre Phase 2 Development be increased by £1,000,000 to £3,553,850. 2. RESOLVE to delegate to the Deputy Chief Executive, following consultation with the Beeston Town Centre Project Board, authority to award a building contract for the Beeston Town Centre Phase 2 based on qualitative and quantitative analysis of tenders 3. RESOLVE that the other capital budget variations for 2019/20 as set out in appendices 1 and 2 be approved.
Background papers Nil Finance and Resources Committee 11 July 2019 APPENDIX 1
1. Beeston Town Centre Phase 2 Development
The Policy and Performance Committee on 21 November 2017 delegated to the Interim Deputy Chief Executive responsibility for the financing of the Beeston Town Centre Development scheme (sometimes referred to as Beeston Square Phase 2)..
The 2018/19 capital programme included £539,800 for the Beeston Town Centre Development scheme. Expenditure for the year totalled £421,865. This included £282,795 paid to Atkins Limited for site investigation, work on the planning application and elements of detailed design. A planning fee of £25,535 was paid to the Council. There were also payments totalling £16,638 to Cartwright Communications for public relations work, £9,500 to Jones Lang LaSalle for valuation work and £7,000 to Grant Thornton for undertaking a financial appraisal of a potential cinema operator. There was also expenditure of £50,675 on the services of the Interim Regeneration Manager.
The expenditure of £421,865 was financed using grant income of £320,000 and borrowing of £101,865. The grant income was comprised of £70,000 received from the Nottinghamshire Pre-Development Fund and £250,000 received from the D2N2 Local Enterprise Partnership (LEP) towards the regeneration of Beeston Town Centre. The LEP grant is to be supplemented with a further £500,000 to be received in 2019/20.
A further report on this agenda seeks approval to carry forward the unspent £117,350 budget in the 2018/19 capital programme into 2019/20.
The capital programme 2019/20 to 2021/22 presently includes a total of £10,436,500 for the scheme spread across each of the three years as follows:
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.