Resolved
RESOLVED that the application be deferred. Councillor R I Jackson experienced a technical difficulty and was not able to vote thereon. He re-joined the meeting for the next item.
Planning Committee deferred this item on Wednesday 30 September 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the application be deferred. Councillor R I Jackson experienced a technical difficulty and was not able to vote thereon. He re-joined the meeting for the next item.
1.1This is a major hybrid planning application comprising two elements. Detailed (full) planning permission is sought for 132 dwellings, associated infrastructure, flood attenuation works, play area and open space. Outline planning permission, with all matters reserved except for access, is sought for up to 200 dwellings, a local centre (comprising a use(s) falling within an ‘A’ Use Class), associated infrastructure, flood attenuation works and open space.
1.2Outline permission was granted in 2014 for up to 450 dwellings (11/00758/OUT) and phase 1 (118 dwellings) has reserved matters approval (15/00841/REM) and is being constructed. The outline permission has now expired so this application has been made for the remaining part of the site. The detailed application will comprise phase 2 (132 dwellings) of the development of the wider site. A mix of dwelling sizes is proposed, with the design relating to three main character areas based on the principles established with the phase 1 development. Access will be taken from Ilkeston Road and this forms the southern boundary of the site with Boundary Brook forming the northern boundary. A drainage pond and play area are proposed towards the west of the site beside a right of way, with the phase 1 site beyond. The outline site (200 dwellings) is to the north east of the phase 2 site and extends to the railway line, with a TPO woodland retained which extends from Mayfield Drive to the east towards the brook. The total number of dwellings across the wider site will remain as approved at outline stage – up to 450 dwellings.
1.3The main issues relate to the design of the development, the impact of the development on flooding and ecology and whether the principle of the inclusion of a local centre is acceptable. Planning Committee 30 September 2020
1.4The design of the dwellings comprising the full application is based on the design approved by an Inspector in relation to Phase 1 so is considered to be acceptable. A drainage strategy has been agreed by the LLFA and extensive flood mitigation works were undertaken as part of the phase 1 development so the development is considered to be acceptable in flood risk terms. Ecological surveys submitted have been accepted by NWT and the TPO woodland is to be largely retained as part of the outline site. The ecological impacts of the development are considered to be acceptable. Given the size of the proposed local centre (500 square metres), it is considered to have no detrimental impact on the vitality or viability of Stapleford town centre and will meet the local need generated by the occupants of the development.
1.5The Committee is asked to resolve that the hybrid application be approved subject to the comments of Highways England being addressed, the s106 Agreement being completed and the conditions outlined in the appendix. Planning Committee 30 September 2020
Appendix 1
1 Details of the Application
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
20/00116/FULReport | 3.2 MB | DownloadRead as text |
Follow Planning Committee at Broxtowe and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Oct 2026 | 26/00581/fulRESOLVED that the Planning permission be refused due to the proposed two-storey rear extension, by reason of its scal... | Refused | Open |
| 28 Oct 2026 | 26/00554/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant advertisement conse... | Approved | Open |
| 28 Oct 2026 | 26/00495/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... | Approved | Open |
| 28 Oct 2026 | 26/00335/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... | Agreed | Open |
| 28 Oct 2026 | 26/00516/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.