Resolved
RESOLVED that the capital budget variations for 2021/22 as set out in the appendix be approved.
Finance and Resources Committee approved this item on Thursday 7 October 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the capital budget variations for 2021/22 as set out in the appendix be approved.
To seek approval to revise the Capital Programme for 2021/22.
2. Detail
The previous year’s Capital Programme was delayed in several areas due primarily to the effects of the pandemic and national restrictions on activity. Accordingly, the outturn report for 2020/21 identified carry forward budgets of £8,495,900 into 2021/22. All projects are being reviewed to ensure revised timescales are identified, phasing of expenditure matches to activity and that all targets can be met. A summary expenditure analysis of progress with all capital schemes will be brought to the next meeting of this Committee in December.
In the meantime, there are a number of new projects that are required in respect of property asset development, transport and ICT technical infrastructure. The table in the appendix sets out amendments identified in the Capital Programme together with likely financing that will be confirmed at the end of the current financial year.
Any further changes to the Capital Programme will be reported to Committee as necessary.
The Committee is asked to RESOLVE that the capital budget variations for 2021/22 as set out in the appendix be approved.
Background papers Nil Finance and Resources Committee 7 October 2021
APPENDIX Capital Budget Amendments and Capital Financial
Activity Spend Commentary Financing £ Purchase of two new 44,000 The Council is currently renting two vehicles for Funded by Housing Revenue Account (HRA) electric vehicles for mobile use by mobile cleaning staff at a cost of £5,500 borrowing. While the HRA will pick up the cleaning staff per unit per annum. The anticipated cost of borrowing costs over the anticipated asset life, purchasing two new electric vehicles is £44,000 this should be comfortably offset by the rental with an expected life of 15 years. This represents savings. These costs/savings will be reflected in a short payback period for the purchases when the HRA budgets for subsequent years. compared to current rental arrangements. Further Beeston Square 500,000 Redevelopment of the ‘Argos block’ in Beeston The redevelopment may be met from General Redevelopment Square as agreed by the Beeston Town Centres Fund (GF) capital receipts, if available. Otherwise Board in September 2021. the scheme will be funded by borrowing. Technical Infrastructure (100,000) Additional cost of changes to the Microsoft EA as Reduction in the capital budget will reduce the Architecture – Microsoft part of the upgrade of the telephony solution. impact on GF capital receipts and additional Enterprise Agreement Microsoft has finalised the Government pricing borrowing. (EA) Renewal strategy (DTA21) used to determine prices for the next three years. The resulting revenue cost increase will be funded by a further £100k being removed from the ICT Technical Infrastructure Architecture capital budget. Leisure Facilities Strategy 11,000 Following the report to Policy and Performance Additional borrowing. – Feasibility Study for Committee on 1 July 2021, further development Bramcote Leisure Centre on Leisure Facilities Strategy with consultancy on a feasibility/option appraisal of the Bramcote site. Total 455,000
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL PROGRAMME 2021/22 UPDATEReport | 114 KB | DownloadRead as text |
Follow Finance and Resources Committee at Broxtowe and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Feb 2022 | Business plans and financial estimates 2022/23 - 2024/25RESOLVED that the Business Plans relating to the support service areas be approved. 2. RECOMMENDED to Council that th... | Approved | Open |
| 10 Feb 2022 | Budget proposals and associated strategiesRESOLVED to approve: 1. The business plans for the Council’s corporate priorities and support functions, subject to a... | Approved | Open |
| 10 Feb 2022 | Capital programme amendments 2021/22RESOLVED that the capital budget variations for 2021/22 as set out in the appendix be approved. | Approved | Open |
| 10 Feb 2022 | Grants to voluntary and community organisations, charitable bodies and individuals involved in sports, the arts and disability matters 2021/22RESOLVED that the Grant applications be dealt with as follows: New Stapleford Community Association £4,000 Stapleford... | Decided | Open |
| 10 Feb 2022 | Civic event-freeman/alderman of the boroughRESOLVED that the finances be provisionally approved subject to Council’s approval of the establishment of a special ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.