Resolved
RESOLVED that the capital budget variation set out in appendix 3 be approved.
Finance and Resources Committee approved this item on Thursday 9 December 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the capital budget variation set out in appendix 3 be approved.
To report upon capital expenditure incurred in 2021/22 up to 30 September 2021 along with the planned financing of the 2021/22 capital programme and to seek approval for a capital budget variation in the current financial year.
Appendix 1 sets out the 2021/22 capital programme on a scheme by scheme basis and shows expenditure incurred on all capital schemes up to 30 September 2021. The 2021/22 capital programme includes schemes totalling £8,542,650 that were carried forward from 2020/21. It also includes all subsequent adjustments to the budgets that were approved by this Committee up to and including 7 October 2021.
Capital expenditure totalling £6,778,712 (31% of the planned capital programme) had been incurred by 30 September 2021.
Also included in the capital programme are schemes totalling £1,103,000 that are on a ‘reserve list’ and will be brought forward for formal approval to proceed once a source of funding is identified.
Appendix 2 sets out how it is anticipated that the 2021/22 capital programme is to be financed along with details of the capital receipts that are likely to be available for capital financing.
Finally, there is an additional budget allocation required in respect of property asset management. Further details are set out in appendix 3 which sets out the amendment identified in the Capital Programme together with likely financing that will be confirmed at the end of the current financial year.
The Committee is asked to:
1. NOTE the expenditure on the 2021/22 capital programme to 30 September 2021 in appendix 1 and the planned financing of the capital programme in appendix 2; and
2. RESOLVE that the capital budget variation set out in appendix 3 be approved.
Background papers – Nil Finance and Resources Committee 9 December 2021
APPENDIX CAPITAL PROGRAMME 2021/22 UPDATE
The following table summarises the Capital Programme 2021/22 expenditure by service area to 30 September 2021.
Service Area Approved Spend Spend Budget to Date to Date £ £ % Housing 15,035,230 4,631,959 31 Jobs and Economy 488,700 100,370 21 Leisure and Health 93,600 28,107 34 Environment and Climate Change 1,638,400 451,391 28 Community Safety 25,000 0 0 Finance and Resources 5,172,245 1,566,885 31
GRAND TOTAL 22,453,175 6,778,712 30
The capital budget updates approved by this Committee on 7 October 2021 are included in the tables for completeness. For comparative purposes the capital expenditure in the previous year up to 30 September 2020 was £5.896m of a £28.467m budget (21%).
There are a further 20 schemes with an estimated cost of £1,103,000 that are on a ‘reserve list’ which may come forward for approval to proceed once a funding source has been identified.
The following tables provide a summary expenditure by individual schemes as at 30 September 2021.
Budget Spend to HOUSING 2021/22 30/09/21 % £ £ Disabled Facilities Grant 1,351,380 356,008 26 Warm Homes on Prescription 50,000 - - Central Heating Replacement 2,406,850 590,911 25 Modernisation Programme 2,215,300 1,112,680 50 Major Relets 150,000 143,795 96 Disabled Adaptations 593,450 80,306 14 Window & Door Replacement 688,150 83,106 12 External Decoration & Pre Paint Repairs 928,850 371,738 40 Electrical Periodic Improvements 484,950 111,635 23 External Works – Paths/Paving 222,600 112,904 51 Fire Safety Assessment & Remedial Work 371,000 326,485 88 Finance and Resources Committee 9 December 2021
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL PROGRAMME 2021/22 UPDATEReport | 387 KB | DownloadRead as text |
Follow Finance and Resources Committee at Broxtowe and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Feb 2022 | Business plans and financial estimates 2022/23 - 2024/25RESOLVED that the Business Plans relating to the support service areas be approved. 2. RECOMMENDED to Council that th... | Approved | Open |
| 10 Feb 2022 | Budget proposals and associated strategiesRESOLVED to approve: 1. The business plans for the Council’s corporate priorities and support functions, subject to a... | Approved | Open |
| 10 Feb 2022 | Capital programme amendments 2021/22RESOLVED that the capital budget variations for 2021/22 as set out in the appendix be approved. | Approved | Open |
| 10 Feb 2022 | Grants to voluntary and community organisations, charitable bodies and individuals involved in sports, the arts and disability matters 2021/22RESOLVED that the Grant applications be dealt with as follows: New Stapleford Community Association £4,000 Stapleford... | Decided | Open |
| 10 Feb 2022 | Civic event-freeman/alderman of the boroughRESOLVED that the finances be provisionally approved subject to Council’s approval of the establishment of a special ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.