Resolved

RESOLVED that planning permission be granted subject to the following conditions, with the above amendment: 1. The development hereby approved shall be begun before the expiration of 3 years from the date of this permission. 2. This permission shall be read in accordance with the following plans: · AUG-TOTON-GRID-104-S Site Access Sheet 1 & 2 · AUG-TOTON-GRID-104-S 100MW 2H Site + 30MW 2H Site Layout Sheet 1 & 2 · AUG-TOTON-GRID-106-B Land Regs Borders · AUG-TOTON-GRID-107-D Tree Survey · AUG-TOTON-GRID-108-E Proposed Footpaths and Bridal Ways Sheet 1 & 2 · AUG-TOTON-GRID-109-E Topo Sheet 1 · AUG-TOTON-GRID-109-E Topo Sheet 2 · AUG-TOTON-GRID-109-E Topo Sheet 3 · AUG-TOTON-GRID-111-D Existing Site Plan · AUG-TOTON-GRID-113-C Site Cross Sections · AUG-TOTON-GRID-114-B Indicative Cable Route · AUG-TOTON-GRID-115-B Prominent Area of Special Protection Overlay · AUG-TOTON-GRID-301-B Std Battery Container · AUG-TOTON-GRID-302-B Invertor · AUG-TOTON-GRID-302-B TX · AUG-TOTON-GRID-303-A Switchgear container · AUG-TOTON-GRID-304-A Aux. Transformer · AUG-TOTON-GRID-305-A Fence Panel & Gate Sheet 1 & 2 · AUG-TOTON-GRID-306-A Substation elevation · AUG-TOTON-GRID-307-D DNO control room Sheet 1 · AUG-TOTON-GRID-308-A 33kV S/S · AUG-TOTON-GRID-309-A 20 FT Container – Storage pump · AUG-TOTON-GRID-401-A Boundary Comparison · AUG-TOTON-GRID-402-C ... view the full minutes text for item 11.1
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Planning Committee

Purpose of report

The application seeks full planning permission for the construction and operation of two adjacent Battery Energy Storage Systems (BESS) facilities operating at different voltages (132kV and 33kV) in order to fully support the local electricity network. Both facilities are adjacent to each other within a single new overall site compound comprising: the erection of battery containers, switchgear containers, inverters, control building, and new substations; installation of new underground cable circuits to connect the new BESS substations; improvements to access from Common Lane; establishing new internal access roads, resurfaced compound, and turning area; installation of perimeter fencing and access gate; associated ground works; and landscaping.

This application is an amended re-submission of previous application 22/00799/FUL which was refused 13 June 2023.

Recommendation

The Committee is asked to RESOLVE that planning permission be granted subject to conditions outlined in the Appendix. Planning Committee 24 July 2024

3. Detail

The application seeks full planning permission for the development as outlined in paragraph 1 above.

The application site approximately 4.38 hectares (ha), with approximately 1.9 (ha) of this being dedicated to the BESS facility, 1.93 (ha) for landscaping and tree planting, and the remainder for the subterranean cable routing. The site currently forms agricultural land within the Green Belt.

The main issues relate to whether the principle of the development in the Green Belt is acceptable; the impact on the openness of the Green Belt; the impact on the visual amenity and Prominent Area of Special Protection; the impact on heritage assets and archaeology; the impact on the living conditions of neighbouring properties; the impact on highway safety; the impact on ecology; and the impact on drainage.

What is proposed is considered to be inappropriate development in the Green Belt. The main issue to assess is whether any of the matters within the report contained within the Appendix taken individually or collectively, amount to the Very Special Circumstances (VSC) necessary to outweigh the harm to the Green Belt through inappropriateness. What constitutes VSC will depend on the weight of each of the factors put forward and the degree of weight to be accorded to each is a matter for the decision taker. Firstly, it is to determine whether any individual factor taken by itself outweighs the harm. Secondly, to consider whether a number of factors combine to create VSC.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24/00066/FULReport 16 KB DownloadRead as text
PDF
/00066/FULAppendix 24 436 KB Download
PDF
BESS Photos and PlansPlan 3.7 MB Download

At this meeting

Whole meeting

Who was there

14 of 16 attended
DB
Councillor David BagshawChair, present
SP
Councillor Stephen P JeremiahVice-Chair, present
PJ
Councillor Peter J BalesCommittee Member, present
LA
Councillor Lydia A Ball BEMCommittee Member, present
RE
Councillor Ross E BofingerCommittee Member, present
GB
Councillor Gabrielle BunnCommittee Member, present
SJ
Councillor Stephen J CarrCommittee Member, apologies, sent representative
GS
Councillor Graham S HillsCommittee Member, present
GM
Councillor Greg MarshallCommittee Member, present
DP
Councillor Don PringleCommittee Member, present
HE
Councillor Helen E SkinnerCommittee Member, present
PA
Councillor Pauline A SmithCommittee Member, present

All 16 on the meeting page

On this subject at Broxtowe

Search all
  1. 24/00066/FULThis decision
  2. 26/00581/fulRefused
  3. 26/00495/fulApproved
  4. 26/00516/fulAgreed
  5. 26/00564/fulAgreed
  6. 26/00404/fulAgreed

More from Broxtowe Planning Committee

All decisions
MeetingDecisionOutcome
28 Oct 2026 26/00581/fulRESOLVED that the Planning permission be refused due to the proposed two-storey rear extension, by reason of its scal... Refused Open
28 Oct 2026 26/00554/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant advertisement conse... Approved Open
28 Oct 2026 26/00495/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Approved Open
28 Oct 2026 26/00335/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open
28 Oct 2026 26/00516/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies