24/00044/VOC

Approved Planning 2 papers

Planning Committee approved this item on Wednesday 24 July 2024. Below is the council's own wording, with the papers it was decided on.

Item11.6

Resolved

RESOLVED that planning permission be granted subject to the following conditions. 1. The development hereby approved shall be carried out in accordance with drawing numbers ADC1044/005 revision D and drawing ADC1044/007 revision A received by the Local Planning Authority on 7 October and 29 January 2020 respectively. No more than 20 occupations of the proposed development shall take place until site access arrangements shown on drawing ADC1044/005 revision D have been provided. Reason: For the avoidance of doubt and in the interest of highway safety. 2. Following the written approval of the Local Planning Authority dated 31 May 2023 of the Site Investigation findings, the remedial works identified, shall be implemented for each dwelling in full accordance with the approved details prior to the occupation of each dwelling. Reason: The undertaking of intrusive site investigations, prior to the commencement of development, is considered to be necessary to ensure that adequate information pertaining to ground conditions and coal mining legacy is available to enable appropriate remedial and mitigation measures to be identified and carried out before building works commence on site. This is in order to ensure the safety and stability of the development and in accordance with the aims of Policy 19 of the Broxtowe Part 2 Local Plan (2019). 3. The hereby approved development shall be carried out in accordance with the approved Construction Method Statement (February 2023 REV B) unless otherwise agreed in writing by the Local Planning Authority. Reason: In the interest of highway safety. 4. The hereby approved detailed Surface Water Drainage Scheme shall be carried out in accordance with the following approved details dated 01 August 2023 unless otherwise agreed in writing by the Local Planning Authority. Reason: A detailed surface water management plan is required to ensure that the development prevents an increase in flood risk, improves and protects water quality and sufficient surface water management in accordance with the aims of the NPPF and Policy 1 of the Broxtowe Part 2 Local Plan 2019. 5. The hereby approved development shall be carried out in accordance with the approved details of appropriate gas prevention measures. No building to be erected pursuant to this permission shall be occupied or brought into use until: ( i ) all necessary remedial measures have been completed in accordance ... view the full minutes text for item 11.6
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Planning Committee

Purpose of report

The application is brought to the Committee at the request of Councillor D D Pringle. The application was originally brought to 5 June 2024 Committee, but was deferred.

Recommendation

The Committee is asked to resolve that planning permission be granted subject to conditions outlined in the appendix.

3. Detail

This application was first brought before Planning Committee on the 5 June 2024 with a recommendation to grant planning permissions. Members deferred decision on the application to seek clarification with the road junction on Shilo Way in respect of the occupation of the first 20 houses. Further information has now been submitted which is set out below and in the appendix. The application seeks to vary condition 3 of application Reference Number: 20/00056/OUT to allow the occupation of up to 20 dwellings prior to the Shilo Way site access arrangements being made available.

The original description of this planning application was to allow for the occupation of up to 50 dwellings, which was considered excessive hence the change of description to allow the occupation of up to 20 dwellings.

This application seeks planning permission for the variation of condition 3 of outline planning permission reference number 20/00056/OUT. This condition restricts the occupation of any of the dwellings prior to the provision of the access roads located off Shilo Way and Newtons Lane being made available for use.

The development hereby approved shall be carried out in accordance with drawing numbers ADC1044/005 revision D and drawing ADC1044/007 revision A received by the Local Planning Authority on 7 October and 29 January 2020 respectively. Occupation of the proposed development shall not take place until the site access arrangements as shown on both of these plans have been provided. Planning Committee 24 July 2024

Access into the site has now been built out from Newton Lane and construction works are well underway on the site. Technical approval for the Shilo Way access and a legal agreement following technical approval which is required from Nottinghamshire County Council Highways had previously been delayed and it is was likely that works would have begun on the access road in September this year and finish December this year/early January 2025. Due to construction works ongoing on site under reserved matters application reference 22/00346/REM, with the first occupation expected to be September this year, this application seeks to vary condition 3 to allow the occupation of up to 20 dwellings prior to the access arrangements off Shilo Way being provided.

In terms of additional information, Avant Homes have now received Technical Approval for the S.278 works at Shilo Way which was confirmed by Nottinghamshire County Council (NCC) on 9th May 2024. As the S278 works are classed as Major Works, Avant Homes have already issued a three month notice to NCC to access the public highway to undertake the works, provisionally starting on 12 August 2024 and completing on 27 January 2025. Avant Homes are actively progressing the s278 legal agreement with solicitors, and this will need to be completed by the end of July 2024.

Based on Avant Homes current forecast, 20 occupations will be reached by the middle of January 2025.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24/00044/VOCReport 310 KB DownloadRead as text
PDF
Shilo Way photos and plansPlan 2.6 MB Download

At this meeting

Whole meeting

Who was there

14 of 16 attended
DB
Councillor David BagshawChair, present
SP
Councillor Stephen P JeremiahVice-Chair, present
PJ
Councillor Peter J BalesCommittee Member, present
LA
Councillor Lydia A Ball BEMCommittee Member, present
RE
Councillor Ross E BofingerCommittee Member, present
GB
Councillor Gabrielle BunnCommittee Member, present
SJ
Councillor Stephen J CarrCommittee Member, apologies, sent representative
GS
Councillor Graham S HillsCommittee Member, present
GM
Councillor Greg MarshallCommittee Member, present
DP
Councillor Don PringleCommittee Member, present
HE
Councillor Helen E SkinnerCommittee Member, present
PA
Councillor Pauline A SmithCommittee Member, present

All 16 on the meeting page

On this subject at Broxtowe

Search all
  1. 24/00044/VOCThis decision
  2. 25/00553/vocApproved
  3. 24/00304/vocAgreed
  4. 25/00223/vocAgreed
  5. Application Number 24/00863/VOCApproved
  6. Application Number 24/00864/VOCApproved

More from Broxtowe Planning Committee

All decisions
MeetingDecisionOutcome
28 Oct 2026 26/00581/fulRESOLVED that the Planning permission be refused due to the proposed two-storey rear extension, by reason of its scal... Refused Open
28 Oct 2026 26/00554/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant advertisement conse... Approved Open
28 Oct 2026 26/00495/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Approved Open
28 Oct 2026 26/00335/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open
28 Oct 2026 26/00516/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open