Cabinet, Wednesday 30 June 2021 at 6.00pm

Procurement of a Development Partner For Phase 2 of Chamberhall Business Park, Bury

Agreed Executive 2 papers

Cabinet agreed this item on Wednesday 30 June 2021. Below is the council's own wording, with the papers it was decided on.

ItemCA.92

Resolved

That a procurement exercise is now undertaken on Chamberhall phase 2 in order for a private sector developer partner to be appointed. 2. The disposal be in the form of a Council standard long lease and subject to a bespoke development agreement to ensure that Bury achieves maximum benefits from the project. 3. That the Director of Regeneration & Capital Growth be given delegated authority in consultation with the Monitoring Officer, Section 151 Officer and the Leader of the Council to consider all of the bids received and to approve the agreement of the terms of the most advantageous bid in accordance with the award criteria. 4. That details of the preferred developer and the wider updated development proposals be submitted to Cabinet not later than December 2021. Reasons for the decision: The procurement will ensure that a high-quality sustainable development is brought forward as well as ensuring best value is achieved for the site. Other options considered and rejected: Option 1 - Do Nothing In this scenario the site will be left vacant. This option has been dismissed as the Council is prioritising its redevelopment so as to bring forward new employment land to meet the needs of businesses. There is also an opportunity cost for not seeking new development in that the ability to secure a sustainable income flow through new business rates will be lost. Option 2 - Direct Development by the Council Under this option the Council would undertake the development directly. The Council would masterplan the site, undertake all further due diligence work and secure the relevant planning permissions. The Council would then tender the works contract and manage the construction of the new units. Once practically complete the Council would then take on full responsibility for the lettings. This option would mean that the Council would have to secure all of the funding for the scheme. This option has been dismissed as although a lot of this work could be done by external consultants it would still require significant internal resource from the Council. Furthermore, the Council would have to bear all the risk associated with funding a property development of this nature. Option 3 - Straight land sale through private treaty The Council could simply market the site and dispose at best value. Whilst there is likely to be strong interest in the site, this approach does not allow the Council to have controls over the subsequent development. The risk here being that a purchaser could ’land bank’ the site and / or undertake a sub optimal regeneration scheme. As such, this option has been discounted.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

PLAN REFERRED TO

27 31 32 22

22 18

Power Station

20 Recycling Business

11 15 17

FR EE S TO NE CLO SE

17 12

El Sub Sta

16 6 Water Monitoring Station Peel Industrial Estate

14 Tank

El 1 19

Sub Sta Weir 7

Posts CLOSE BRANCH 1

10 GO 6

RD 2

ON River Irwell

STRE ET

9 Bury Community

4 Fire Station

MA GD 38 ALEN E ROAD 39

1 3

CHA MB ERHALL STR EET

MS 84.1m 10 Drain

y East Lancashire Railwa Trav Crane

Works

ESS

El Sub Sta a 1

b St El Su

Trav Crane O AD OAD

TR DR

Post F RO RVAR

TLEC HA

C AS

Travelling Crane

DU NS TE R ROAD

Trav Crane

Police Headquarters

California Works

El Sub Sta

TANPIT S ROAD

SCHO OL

PEE L WA Y

Business Growth & Infrastructure PLAN Phase 2 Property Services & Asset Management Chamberhall 3 Knowsley Place SCALE 1:2500 Duke Street, DRAWN BY MB Bury, BL9 0EJ DATE Telephone 0161-253-5995 11/06/2021

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of a Development Partner For Phase 2 of Chamberhall Business Park, Bury: Appendix 1Decisions 246 KB DownloadRead as text
PDF
Procurement of a Development Partner For Phase 2 of Chamberhall Business Park, BuryDecisions 410 KB Download

At this meeting

Whole meeting

Who was there

8 of 18 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
AS
Councillor Andrea SimpsonCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
TR
Councillor Tahir RafiqCommittee Member, present
GL
Geoff LittleChief Executive, in attendance
LR
Lynne RidsdaleOfficer, in attendance
SE
Sam EvansOfficer, in attendance
PB
Philippa BraithwaiteOfficer, in attendance

All 18 on the meeting page

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies