AI summaryBury Cabinet approved heads of terms for a new 8 year Elms Bank College lease effective 1 September 2026, securing post 16 SEND provision without major capital expenditure. Minor variations and signing were delegated, avoiding a several million pounds modular accommodation bill.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCurrent heads of terms approved, with signing delegated.
Moneyseveral million poundsFor modular accommodation under the rejected option.
What happens nextFinalise and sign lease documentsMinor variations are delegated to the Assistant Director.
Who it affectsYoung people with SENDPost 16 education at Elms Bank College Hub.
What was decided
Cabinet approved the current heads of terms for the new lease and associated indemnity agreement.
Minor variations to the final heads of terms or indemnity agreement were delegated to the Assistant Director of Corporate Assets and Facilities Management.
Signing the lease, indemnity agreement and associated documents was delegated to the Council's Monitoring Officer.
Why
The new lease secures the operation of the Elms Bank College Hub without major capital expenditure in the medium term. Report P8
The lease gives the Council and OLP a 5 year period to plan for longer term post 16 SEN provision. Report P6
Securing the hub enables young people with SEND to continue their education in local provision. Report P20
What happens next
Legal Services must review the existing Deed of Indemnity. The review must define the extent and duration of the Council's liability and reflect the approved terms. Report P24
Minor variations may be agreed by the Assistant Director, provided they do not materially increase the Council's financial exposure. The Council's Monitoring Officer is authorised to sign the lease, indemnity agreement and associated documents. Report P25
Dialogue with StoC will continue to minimise the risk that the new lease is not approved. Report P24
Options considered
Chosen: Approve the new lease and associated indemnity agreement. It secures the Elms Bank College Hub without major capital expenditure in the medium term. Report P8
Rejected: Do not agree the new lease. OLP would have to vacate the existing buildings in August 2027, and the Council would need to secure a suitable site and spend several million pounds on modular accommodation. Without alternative provision, OLP would in effect need to close the provision. Report P9, P10, P11, P12
Implications
Financial: The Council will continue to underwrite costs for the building during the lease. A new indemnity agreement will be on similar terms to the current agreement. Report P16
Financial: The lease avoids major capital expenditure in the medium term. Without agreement, the Council would need to spend several million pounds on modular accommodation. Report P8, P10
Legal: The Council is not party to the proposed lease, so its financial commitment must be documented separately by a variation or replacement of the existing Deed of Indemnity with OLP. Legal Services must review the existing deed to define the extent and duration of the Council's liability and reflect the approved terms. Report P24
Legal: The heads of terms are subject to contract and do not create a binding lease. Delegated variations must not materially increase the Council's financial exposure. Report P25
Equalities: No equality impacts are expected because this extends current arrangements. Report P22
Climate: No environmental impacts are expected from this decision. Report P22
Risk: If StoC does not approve the new lease, ongoing dialogue is the stated mitigation. Report P24
Other: The new lease gives the Council and OLP a 5 year period to plan for longer term post 16 SEN provision. The SEND Sufficiency Strategy seeks to strengthen post 16 sufficiency and preparation for adulthood. Report P6, P17, P18
Who and where
Young people with SEND in post 16 education Report P17, P20
1 September 2026: The new 8 year lease takes effect. Report P5, P15
14 October 2026: Cabinet approves the heads of terms and delegates document signing. Report P2
5 year period: The Council and OLP have time to plan for longer term post 16 SEN provision. Report P6, P17
25 August 2027: The current 5 year lease expires. Report P3, P12
Plain English for the jargon
SEND: Special Educational Needs & Disabilities
SEN: Special educational needs
OLP: Oak Learning Partnership
StoC: Salford Romen Catholic Diocesan Trustees/St Teresa of Calcutta Trust
AP: Alternative provision
EOTAS: Education otherwise than at school
Heads of terms: Agreed terms for a proposed lease. They are subject to contract and do not create a binding lease.
Indemnity Agreement or Deed of Indemnity: Agreement under which the Council takes responsibility for OLP costs, including rents, for the college.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.81
Resolved
Decision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity agreement b. Delegated any minor variations to the final heads of terms or Indemnity Agreement to the Assistant Director of Corporate Assets and Facilities Management. c. Delegated the signing of the lease, Indemnity Agreement and any associated documents to Councils Monitoring Officer. Reasons for decision(s) · The grant of the new lease secures the operation of the Elms Bank College Hub without major capital expenditure for in the medium term. Alternative options considered and rejected · Not to agree to the agreement to the new lease o In this scenario the OLP would have to vacate the existing buildings in August 2027. o The Council would need to secure a suitable site and spend several million pounds on modular accommodation to ensure provision could continue past August 2027. o Without alternative provision OLP would in effect need to close the provision. o As such, this option has been discounted.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
Report to: Cabinet Date: 14 October 2026 Subject: Grant of new Lease for Elms Bank College at St Monica’s Report of Cabinet Member for Children and Young People
Summary 1. Oak Learning Partnership (OLP) currently lease the former St Monica’s Sixth form buildings in Prestwich from Salford Romen Catholic Diocesan Trustees (StoC) for the provision of post 16 SEN teaching, known as Elms Bank College Hub. The lease is for period of 5 years expiring on 25 August 2027.
2. There is currently a separate Deed of Indemnity between the Council and OLP. Whereby the council underwrite all costs incurred by OLP, including rents, for the running of the Elms Bank College.
3. Following discussions with StoC, terms have been agreed for a new 8 year lease of the college buildings with effect from 1 September 2026
4. The grant of the new lease will allow the Council and OLP a 5 year period to plan for the longer-term provision of the post 16 SEN provision.
Recommendation(s) 5. That Cabinet: a. Approve the current heads of terms for the grant of the new lease and associated indemnity agreement b. Delegate any minor variations to the final heads of terms or Indemnity Agreement to the Assistant Director of Corporate Assets and Facilities Management. c. Delegate the signing of the lease, Indemnity Agreement and any associated documents to Councils Monitoring Officer.
Reasons for recommendation(s) 6. The grant of the new lease secures the operation of the Elms Bank College Hub without major capital expenditure for in the medium term.
Alternative options considered and rejected 7. Not to agree to the agreement to the new lease • In this scenario the OLP would have to vacate the existing buildings in August 2027.
• The Council would need to secure a suitable site and spend several million pounds on modular accommodation to ensure provision could continue past August 2027.
• Without alternative provision OLP would in effect need to close the provision.
• As such, this option has been discounted. _________________________________________________________ Report Author and Contact Details: Name: Roger Frith Position: Assistant Director of Corporate Assets and Facilities Management Department: Place E-mail: [email protected] ________________________________________________________________ Background 8. Oak Learning Partnership (OLP) currently lease the former St Monica’s Sixth form buildings in Prestwich from Salford Romen Catholic Diocesan Trustees/St Teresa of Calcutta Trust (StoC) for the provision of post 16 SEND teaching, known as Elms Bank College Hub. The lease is for period of 5 years expiring on 25 August 2027.
9. There is currently a separate Deed of Indemnity between the Council and OLP. Whereby the council underwrite all costs incurred by OLP, including rents, for the running of the Elms Bank College.
Current Position
10. Following extensive discussions with StoC, terms have been agreed for a new 8 year lease of the college buildings with effect from 1 September 2026. A copy of the agreed heads of terms is in Part B of this report.
11. The Council will continue to underwrite costs for the building during this period and a new Indemnity Agreement on similar terms to the current agreement between the Council and OLP will also be required.
12. The grant of the new lease will allow the Council and OLP a 5 year period to plan for the longer-term provision of the post 16 SEN provision in dialogue with StoC and in accordance with the SEND Sufficiency Strategy. 13. The Bury SEND Sufficiency Strategy 2026–2030 sets out how the Council will meet its statutory duty to secure sufficient, appropriate educational provision for children and young people with special educational needs and disabilities (SEND), including those requiring alternative provision (AP) and education otherwise than at school (EOTAS).
14. The Strategy seeks to strengthen post-16 sufficiency and preparation for adulthood.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.