Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.

Approved Executive 1 paper

AI summaryBury Metropolitan Borough Council Cabinet delegated final acceptance of Balfour Beatty's Stage 3 contract sum, up to a provisional maximum of £3,129,915, approved Bentley Project Management's £423,000 contract sum and accepted £8.5 million of Investment Zone capital grant for Western Access pre construction work [D].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedBalfour Beatty final acceptance is delegated [D][P12]
Money£8.5 million grant accepted [D][P13]The remaining £8,500,000 grant funds the £3,552,915 approval [P54]
What happens nextStage 2b, then Stage 3 [P4][P29]Preliminary designs due by early 2027 [P4][P25]
Who it affectsNorthern Gateway early development [P14]Potential capacity for up to 600,000 sqm employment uses [P14]

What was decided

Final acceptance of Balfour Beatty Civil Engineering Ltd's Stage 3 contract sum, up to a provisional maximum of £3,129,915, is delegated to the Director of Law and Democratic Services, in consultation with the Executive Director of Place, Director of Finance and Leader. The work covers the Full Business Case and detailed design [D][P12]. Report P12

Cabinet approved Bentley Project Management (UK) Limited's £423,000 contract sum for the remaining Stage 2b and Stage 3 pre construction services. This includes finishing the Outline Business Case and preliminary designs, then the Full Business Case and detailed design [D][P12]. Report P12

Cabinet accepted the remaining £8.5 million of Investment Zone capital grant for the Western Access scheme. It will be included in the Council's Capital Programme [D][P13]. Report P13

Why

The Western Access scheme, also called Pilsworth Road Corridor Improvements, is a cross boundary scheme with Rochdale Council. It will provide the off site highway and transport infrastructure needed to access the early Northern Gateway Investment Zone site [P14]. Report P14

The scheme could unlock capacity for up to 600,000 sqm of employment uses, including advanced manufacturing and foundational sectors [P14]. Report P14

Finishing the Outline Business Case will identify a preferred option, preliminary designs and an updated budget estimate, and provide the basis for the Full Business Case. Grant milestones require preliminary designs by early 2027 and detailed designs and costings during 2028, so delay would put the grant funding at risk [P15][P16][P18]. Report P15, P16, P18

What happens next

Balfour Beatty and Sweco UK Limited are due to complete Stage 2b work, including the Outline Business Case, preliminary designs and public consultations. This work is forecast to finish by early 2027 [P4][P24][P25]. Report P4, P24, P25

Stage 3 is expected to start in the first half of 2027 to finalise the Full Business Case and detailed design. The forecast end of Stage 3 is August 2028 [P29][P56]. Report P29, P56

The £52,100,000 Good Growth Funding allocation is for construction, but it remains subject to the Full Business Case and other grant conditions. Funding must be secured before the notice to proceed is signed, and a further Cabinet report will set out construction costs and funding sources [P57]. Report P57

The money

  • £3,552,915 Total expenditure covered by this approval [P54] Report P54
  • £8.5 million Remaining Investment Zone capital grant for the Capital Programme [D][P13] Report P13
  • £3,129,915 Provisional maximum Balfour Beatty Stage 3 contract sum [P12][P54] Report P12, P54
  • £423,000 Bentley Project Management contract sum for remaining Stage 2b and Stage 3 [P12][P54] Report P12, P54
  • £1,891,037 Forecast remaining Balfour Beatty Stage 2b costs, plus legal and internal project management costs [P55] Report P55
  • £7,165,272 Forecast Stage 2b and Stage 3 expenditure to August 2028, excluding land assembly [P56] Report P56
  • £52,100,000 Good Growth Funding allocation for construction, subject to conditions [P57] Report P57
  • £10m Northern Gateway allocation for Western Access over 5 years from 2024/25 [P41] Report P41

Options considered

  • Chosen: Continue the existing Balfour Beatty and Bentley contracts through the remaining pre construction stages. This provides best value and programme certainty, and avoids delay, extra mobilisation costs, duplicated work and loss of scheme knowledge [P19][P38]. Report P19, P38
  • Rejected: Delay approval of the Balfour Beatty Stage 3 provisional maximum. This would delay the Full Business Case, detailed designs and costings, then Stage 4 construction. It would also risk failing grant requirements and losing Investment Zone funding [P18]. Report P18
  • Rejected: Do not approve the Bentley Project Management contract sum. Without approval, the Outline Business Case, preliminary designs, Full Business Case and detailed designs would be at risk, as would early Northern Gateway site delivery [P19]. Report P19
  • Rejected: Procure the services again rather than continue the existing contracts. This would cause delay, higher mobilisation costs, duplicated design and business case work, loss of scheme knowledge and grant milestone risk [P19]. Report P19
  • Rejected: Do not accept the remaining £8.5 million and allow it to be reallocated elsewhere in Greater Manchester. This would present a high risk to delivery of the Places for Everyone plan, the Western Access scheme and the Northern Gateway Investment Zone [P20]. Report P20

Implications

  • Financial: The £3,552,915 approval is funded from the remaining £8,500,000 Investment Zone grant [P54]. Report P54
  • Legal: Approval of the Stage 3 sum does not commit the Council to construction. Any construction phase remains subject to separate approvals and funding arrangements [P52]. Report P52
  • Legal: Contract changes must follow the existing contracts, the Council's Constitution and Contract Procedure Rules. The Bentley variation can be lawfully implemented if it stays within the original procurement and contractual scope [P51][P53]. Report P51, P53
  • Risk: Both contracts include break clauses and monthly monitoring. Under Option C, savings and cost overruns are shared on terms that favour the Council [P27][P28][P36]. Report P27, P28, P36
  • Risk: Delaying approval would breach grant milestones and risk the receipt of Investment Zone funding. Procuring the services again would add delay, cost, duplicated design work and loss of scheme knowledge [P18][P19]. Report P18, P19
  • Equalities: The Equality Impact Assessment concludes that scheme impacts are positive. It will be reassessed as the project progresses [P46]. Report P46
  • Climate: Environmental impacts will be monitored through surveys and investigations. Current work includes biodiversity net gain requirements and carbon assessments to inform the Outline Business Case [P47]. Report P47
  • Staffing: The Council does not have the internal resources and technical skills needed for the remaining time critical pre construction stages. The external professional team and main contractor will provide those resources [P16]. Report P16

Who and where

  • Developers and future occupiers of Northern Gateway employment space Report P14, P45
  • Residents and businesses in Bury and Rochdale Report P43, P45
  • Bury Council and Rochdale Borough Council delivery teams Report P21, P25
  • Balfour Beatty Civil Engineering Ltd and Sweco UK Limited Report P4, P12
  • Bentley Project Management (UK) Limited Report P12
  • Greater Manchester Combined Authority Report P10, P42
  • National Highways Report P21, P41
  • Transport for Greater Manchester Report P21

Timeline

  • 14 October 2026: Cabinet delegated the Balfour Beatty Stage 3 sum, approved the Bentley sum and accepted the capital grant [D][P2] Report P2
  • November 2026: Planned in person and online consultation on draft preliminary designs [P24] Report P24
  • early 2027: Stage 2b Outline Business Case and preliminary designs forecast for completion [P4][P25] Report P4, P25
  • first half of 2027: Stage 3 expected to start for the Full Business Case and detailed design [P29] Report P29
  • during 2028: Production of detailed and technical designs and costings [P16] Report P16
  • August 2028: Estimated end of the Stage 3 process [P56] Report P56
  • autumn 2028: Required start of Stage 4 construction delivery [P18] Report P18
  • summer 2030: Construction completion and revised spend output milestone [P17][P18] Report P17, P18

Plain English for the jargon

  • RIBA: Royal Institute of British Architects, stages of development [P60]
  • OBC: Outline Business Case [P60]
  • FBC: Full Business Case [P60]
  • NEC 4, PSC and ECC: New Engineering Contract series 4; Professional Service Contract; Engineering and Construction Contract (NEC4) [P60]
  • IZ: Investment Zone [P60]
  • PfE: Places for Everyone Plan [P60]
  • MDC: Mayoral Development Corporation, Atom Valley and Northern Gateway [P60]
  • GFA: Grant Funding Agreement [P16]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.79

Resolved

Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up to a provisional maximum of £3,129,915, covering the finalisation of the Detailed Design/ Full Business Case stage work packages (Stage 3), to the Director of Law and Democratic Services in consultation with the Executive Director of Place and Director of Finance and the Leader. b. Approved the Bentley Project Management (UK) Limited contract sum of £423,000 covering the remaining Pre-Construction Stages of the scheme (finalisation of Stage 2b Outline Business Case/ Preliminary Design stage, and Stage 3 Full Business Case/ Detailed Design stage). c. Accepted the remaining £8.5 million of Investment Zone capital grant funding allocated to the Western Access scheme, for inclusion in the Council’s Capital Programme. Reasons for decision(s) · The Western Access scheme (Pilsworth Road Corridor Improvements) is a cross-boundary scheme with Rochdale Council, and will provide the necessary off-site, highway and transportation infrastructure required to access the early development phases of the Northern Gateway Investment Zone (IZ) site (JPA 1.1 allocation). The construction of the Western Access scheme will create the potential capacity to unlock up to 600,000 sqm of employment generating uses and support the creation of high quality, employment floor space, including space within the advanced manufacturing and foundational sectors. · The completion of on-going Stage 2b activities to finalise the Outline Business Case (OBC) for the Western Access scheme will result in a preferred option for the scheme being identified and associated Preliminary Designs and an updated scheme budget estimate being prepared. Importantly, the OBC will also provide the robust strategic, economic, commercial and financial cases for the scheme. This in turn will provide the firm foundation for the development of the subsequent Stage 3 Full Business Case (FBC), which will confirm detailed designs and costings. · Investment Zone (IZ) year one revenue grant funding was allocated ... view the full minutes text for item CA.79
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Classification: Decision Type: Open Key

Report to: Cabinet Date: 14 October 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, Subject: External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding. Report of Leader

Summary 1. Stage 3 Contract Sum: In December 2025 Cabinet approved the delegation of a final contract sum of £2,830,403 covering the finalisation of the Western Access scheme’s Stage 2b pre-construction works, and the finalisation of the Main Pre-Construction and Construction Contract (NEC4 ECC Option C X22 contract) to the Director of Law and Democratic Services in consultation with the Executive Director of Place and Director of Finance and the Council Leader and Cabinet Member for Strategic Growth.

2. Balfour Beatty Civil Engineering Ltd (Western Access scheme main construction contractor) is now nearing completion of the Stage 2b initial pre- construction activities. These include finalising the scheme Outline Business Case (OBC), preparing preliminary designs and facilitating associated public consultations which are currently being planned to take place during November, preparing Pre-application Planning Application, and planning a comprehensive programme of on / off site surveys. These Stage 2b activities are due to be completed in early 2027 following which the remaining Pre- Construction work packages will then be undertaken by Balfour Beatty (and its Design Partner Sweco UK Limited) during Stage 3 (ie. Full Business Case, Detailed Designs/ technical designs).

3. In advance of the above, to maintain project continuity and avoid any programme delays, in line with the approval and contractual process previously undertaken at Stage 2b above, Balfour Beatty has now prepared its Stage 3 (Full Business Case/ Detailed Design) provisional maximum, contract sum, which Cabinet’s delegated approval is now being sought.

4. External Professional Team Contract Extension: On 12th February 2025, Cabinet was notified of the procurement and appointment of a multi- disciplinary external project management team, Bentley Project Management (UK) Limited (Company number 08482170), to support the Council’s delivery of the Northern Gateway Western Access scheme. This procurement and appointment encompass the full pre-construction stage project life cycle (ie. Stage 2/ Outline Business Case and Stage 3/ Full Business Case), covering the core services being provided by Bentley Project Management (UK) Limited, including external project and contract management, and cost consultancy advice and support. This pre-construction appointment was formalised utilising an NEC 4 Professional Servies Contract (PSC) which was finalised and signed on 7th March 2025 with Bentley Project Management.

5. In January 2026, due to scheme prolongation at Stage 2b, approval was received via an Officer Delegation Scheme to amend the existing PSC with Bentley Project Management (UK) Limited. This amendment reflected the extended Stage 2b/ OBC programme duration to the end October 2026; ensuring the PSC continues to remain fully aligned with the overall scheme pre-construction programme.

6. Cabinet approval is now being sought for the approval of the Bentley Project Management (UK) Limited contract sum covering the continuation of their pre- construction, professional services during the remaining Stage 2b period as activities are finalised and also during Stage 3 of the pre-construction period (ie. Full Business Case/ Detailed Design). This is because the cumulative value of the PSC contract sum now requires a Key Decision.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decisions 306 KB DownloadRead as text

At this meeting

Whole meeting
CA.74Public Question TimeOn the agenda CA.76MinutesOn the agenda CA.78Review and amendments to Bury Council's Housing Allocations PolicyApproved
CA.79Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.This decision
CA.80New Persona Shareholder Agreement - PART AApproved CA.81Extension of Lease for St Monica's - Part AApproved CA.82Objections to the proposed disposal of Public Open Space - Land on the North Side of Milton Road, Radcliffe, BuryOn the agenda CA.83New Ash Grove Additional Provision AcademyOn the agenda CA.84Proposed creation of an End-to-End Greater Manchester Fostering HubNoted CA.85Families First Partnership Programme - Part AApproved CA.8610-year occupational Lease - 6b & 6c Bridge Trading EstateApproved CA.87Highways Capital Programme - Highway Maintenance Funding 2026/27Approved CA.88Live Well Implementation in the BoroughNoted CA.89Draft 2027/28 BudgetOn the agenda CA.90Prestwich Village Regeneration Project: Phase 1A (Travel Hub) - Operations StrategyApproved CA.91Parking and Bus Lane Enforcement ServicesNoted CA.92Minutes Of Association Of Greater Manchester Authorities / Greater Manchester Combined AuthorityOn the agenda CA.94Exclusion of Press and PublicDecided CA.95New Shareholder Agreement with Persona PART B - October Cabinet 2026Approved CA.96Extension of lease for St Monica's - Part BApproved CA.97Families First Partnership Programme - Part BApproved

Who was there

0 of 17 attended
EO
Councillor Eamonn O'BrienChair, expected
AA
Councillor Ayesha ArifCommittee Member, expected
RG
Councillor Richard GoldCommittee Member, expected
GM
Councillor Gavin McGillCommittee Member, expected
CM
Councillor Charlotte MorrisCommittee Member, expected
LS
Councillor Lucy SmithCommittee Member, expected
TT
Councillor Tamoor TariqCommittee Member, expected
ST
Councillor Sean ThorpeCommittee Member, expected
SW
Councillor Sandra WalmsleyCommittee Member, expected
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
NK
Neil KissockOfficer, expected

All 17 on the meeting page

On this subject at Bury

Search all
  1. Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.This decision
  2. Northern Gateway Mayoral Development Corporation UpdateNoted
  3. Northern Gateway, Western Access scheme: Approval of Main Construction Contract to undertake Pre-construction and Construction Stage activitiesDecided
  4. Northern Gateway (Transport Framework Document; Social Value Strategy; MDC Business Plan and annual Delivery Plan) - PART ANoted
  5. Northern Gateway MDCNoted
  6. Northern Gateway Development Framework Supplementary Planning DocumentNoted

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open