CAPITAL PROJECT STAGE II APPROVAL, DERBY HIGH SCHOOL, PHILIPS HIGH SCHOOL - PART A

Noted Executive 1 paper

Cabinet noted this item on Wednesday 21 July 2021. Below is the council's own wording, with the papers it was decided on.

ItemCA.113

Resolved

That Cabinet note the programmes of investment. Reasons for the decision: The project costs are within the identified capital programme budget. Other options considered and rejected: N/A
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Executive summary

The report sets out of a number of capital projects at The Derby High & Philips High schools, for which financial provision is made through the 2021/22 and 2022/23 Children’s Services Capital Programme.

Recommendation(s)

That Cabinet: Note the programmes of investment.

Reasons for the decision

The project costs are within the identified capital programme budget.

Background

1.1The Council receives annual capital grant from the Department for Education to fund condition related works in local authority maintained schools. These allocations are calculated based on the number of schools, rather than the condition of school buildings, and therefore, available funding falls short of the investment needs across all schools. Academies are subject to separate funding arrangements and must apply directly to their Academy Trust or Department for Education for funding.

1.2For a number of years, the available funding has been used to target essential condition related work across a number of schools. This approach, whilst ensuring that immediate building works are addressed, has not allowed more strategic investment in the improvement of facilities in schools.

1.3This lack of investment in improving the suitability of accommodation and facilities is not sustainable and will impact over time on the ability of schools to deliver a broad and balanced curriculum, and maintain educational standards.

1.4In order to address this, an element of the available funding is to be targeted at investment in a small number of schools, to enable facilities to be upgraded.

1.5Funding will continue to be available to address condition related works in other schools, albeit at a reduced level.

1.6The schools initially identified for this targeted investment are The Derby High School and Philips High School.

1.7Both schools have produced development plans to outline how investment could be prioritised to improve the school and impact positively on educational outcomes.

1.8From within the Children’s Services agreed capital programme, an allocation has been made to each school to support the delivery of those development plans. Each school has also committed to the use of revenue balances on the school’s budget to contribute to these projects.

1.9Because of the scale of the projects, they need to be funded and delivered across several years. This requires provisional commitments to be made against futures years’ capital allocations. The phasing of works will align to the confirmed resources for each financial year.

2.0REVENUE CONSEQUENCES

There will be no direct revenue implications arising from the projects. Savings from improved energy efficiency and reduction in ongoing maintenance cost will accrue to the schools’ budgets.

2.1Timescales

The project plan will be developed by each school, with the works being commissioned by the school and delivered in accordance with each school’s own priorities. This being conditional upon the projects being delivered in accordance with the cash flow based on the multi-year allocation of resources. 2.2 Risk Management

The Project Initiation Document considers the risks with regards to the financial constraints and the deliverability of the project and identifies appropriate mitigating measures. Each school will be required to have a project plan in place, to include appropriate risk management arrangements.

2.3Health and Safety

There are risks associated with undertaking a building project on a school site whilst the school is in session, however this would be covered by the contractor’s health and safety plan and considered through the project phasing

2.4CONCLUSION

To enable the projects to progress, Cabinet is requested to note the arrangements set out in this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAPITAL PROJECT STAGE II APPROVAL, DERBY HIGH SCHOOL, PHILIPS HIGH SCHOOL: PART ADecisions 568 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 21 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, apologies
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
TR
Councillor Tahir RafiqCommittee Member, apologies
AS
Councillor Andrea SimpsonCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, apologies
LR
Lynne RidsdaleOfficer, expected
SE
Sam EvansOfficer, expected
JD
Jacqui DennisOfficer, expected
DB
Donna BallOfficer, expected

All 21 on the meeting page

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies