CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bury Metropolitan Borough Council
Cabinet, Wednesday 1 September 2021 at 6.00pm

Estates Transformation: Bury Hub Proposals - Phase 1 Humphrey House - Part A

Approved Executive 1 paper

Cabinet approved this item on Wednesday 1 September 2021. Below is the council's own wording, with the papers it was decided on.

ItemCA.132

Resolved

Cabinet: 1. Approved the disposal of Humphrey House and offer an alternative leasing option to the existing tenants as set out in this report. 2. Approved an increase to the capital programme of up to £500k to fund the works required to facilitate shared occupation of 3 Knowsley Place and a modern, flexible working environment. 3. Delegated the finalised terms of any revised leasing arrangements and commercial negotiations to the Director of Regeneration and the Section 151 Officer and Monitoring Officer. Reasons for the decision: · The Council has challenging savings targets to meet through the ‘Let’s Do It’ transformation programme, ‘Let’s Do It Flexibly’ · There is an immediate opportunity to realise a significant saving by seeking to share the space we let. 3 Knowsley Place and 6 Knowsley Place have the potential to be shared with other public sector partners. This opportunity is time-bound because if Humphrey House is to be retained a major refurbishment programme would have to be funded in the very short-term to bring the building up to a modern standard. · The implementation of agile working means that we do not expect staff to return to the office en-mass (subject to the evaluation of the model which will take place in December). However, we do expect teams and people to meet up regularly and to have spaces and areas that promote collaborative working. · 3 Knowsley Place was fitted out 10 years ago as a standalone office building for Council workers – replacing a similar building Craig House on Bank Street in Bury. The current ground floor layout does not allow for multiple tenancy or provide spaces and areas that enable agile working, collaboration and teamwork. · By moving into modern, efficient buildings, the NHS tenants will save on energy bills likely to be in the region of £24k per annum. Other options considered and rejected: · Advise the NHS Trusts that we are selling Humphrey House and ask if they would like to buy it. However, one Trust has already been advised of our existing use asset valuation and have not responded with an offer. The other two trusts have indicated they are content with the leasing option and are not seeking to acquire a property. · Retain Humphrey House and offer the tenants new 5-year leases. This would require an immediate capital outlay of circa £900K to undertake urgent works (of which there is no budget currently), plus an estimated £200K p/a to maintain the building over the five-year period. The costs of undertaking ... view the full minutes text for item CA.132
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Classification: Decision Type: Open Non-Key

Report to: CABINET Date: 01 September 2021

ESTATES TRANSFORMATION: BURY HUB PROPOSALS - Phase 1 Subject: Humphrey House – PART A

Report of Leader and Cabinet Member for Finance and Growth

1.0Summary 1.1 This paper is a the first in a series of requested cabinet approvals that seek to deliver interventions that unlock economic growth, integrate public services, realise commercial efficiencies and capital receipts along with implementing the Councils aspirations for creating an agile working environment. 1.2 The outputs of this programme are driven by the key deliverables set out within the One Public Estate (OPE) property programme and the Councils Let’s Do It Strategy 2020.

1.3Humphrey House is surplus to requirements, requires considerable capital investment to bring up to occupational standards and has a significant capital receipt once disposed of for redevelopment. The site has the potential to deliver new homes on brownfield land as part of the town centre regeneration programme.

1.4Knowsley Place is an underperforming element of the corporate estate. The fit out of the buildings were completed over 10 years ago and does not allow for either flexible working – a collection of informal collaborative spaces or the delivery of integrated public services sharing the same building.

1.5This Estates Transformation work is underway with the objective of reducing the operating costs and improving standards of the Council Estate, and is in- line with the Transformation Strategy agreed in July and in support of the Year 1 savings detailed in this report. It also represents an implementation of our ‘One Public Estate’ Strategy, which seeks to promote the shared use of public buildings to reduce the overall property cost burden on the taxpayer. 1.6 The proposal is to formally close and sell Humphrey House, a council-owned 1970’s office block fronting Angouleme Way. It is proposed the current tenants in Humphrey House are offered space within the 3KP office block, which the Council is not currently fully utilising. 1.7 The project also seeks to implement flexi-working by providing high-quality co-working/social space on the ground floor and reception area of 3KP. This will bring together the staff of the Council, stakeholders, members and partners into a space where there will be a focus on informal meetings, using technology to link teams and create acoustically sound meeting spaces. This will be an important enabler of the Council’s Agile Working model. 1.8 The overall project will create an annual saving to the Council as we will be able to share the lease-costs we currently incur at 3KP with other public bodies. Further adaption works to enable true flexible working can be funded via the projected capital receipt from the sale of Humphrey House.

2.0Recommendation(s) 2.1 Approve the disposal of Humphrey House and offer an alternative leasing option to the existing tenants as set out in this report. 2.2 Approve an increase to the capital programme of up to £500k to fund the works required to facilitate shared occupation of 3 Knowsley Place and a modern, flexible working environment. 2.3 Delegate the finalised terms of any revised leasing arrangements and commercial negotiations to the Director of Regeneration and the Section 151 Officer and Monitoring Officer.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Estates Transformation: Bury Hub Proposals: Phase 1 Humphrey House: Part ADecisions 468 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 18 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
AS
Councillor Andrea SimpsonCommittee Member, apologies
TT
Councillor Tamoor TariqCommittee Member, present
TR
Councillor Tahir RafiqCommittee Member, present
GL
Geoff LittleChief Executive, in attendance
JD
Jacqui DennisOfficer, in attendance
PB
Philippa BraithwaiteOfficer, in attendance
NJ
Councillor Nicholas JonesCommittee Member, in attendance

All 18 on the meeting page

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies