CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bury Metropolitan Borough Council
Cabinet, Wednesday 13 October 2021 at 6.00pm

Request from Telecoms Operators to site Telecommunications on Council owned land (Public Open Space) at Peel Brow, Ramsbottom

Approved Executive 3 papers

Cabinet approved this item on Wednesday 13 October 2021. Below is the council's own wording, with the papers it was decided on.

ItemCA.151

Resolved

Cabinet approved the grant of a lease to the telecoms operators. Reasons for the decision: · The lease of the site will maintain the provision of existing mobile telecommunications for the area and provide a site that will enable the rollout of technologies such as 5G to improve digital connectivity for the area. · It should be noted that the agreement with EE Ltd and Hutchison 3G UK Ltd would be subject to the Electronic Communications Code. The Code was created by Schedule 2 of the Telecommunications Act 1984. Electronic communication services are now classed as essential services – this includes landlines, mobile phones and internet services. To allow these services to be provided where they are needed, the Electronic Communications Code provides a statutory basis whereby communications providers can place their apparatus on land or buildings owned by another person or organisation, which includes land owned by Councils. Other options considered and rejected: · Refuse the request from the telecoms operators for a lease of the land - refusing the request could threaten the provision of the mobile telecommunications service to the area if an alternative location cannot be found. Refusal could also result in the operators exercising powers enjoyed under the Electronic Communications Code which include the ability to apply to the Upper Tribunal (Land Chamber) seeking the imposition of the agreement. · Ask the telecoms operators to look for an alternative area of land on which to locate the telecommunications equipment - this was discussed with WHP however we are informed that the Council’s land at Peel Brow is the preferred location for the siting of the equipment.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

1. In March 2020 the Council agreed to the temporary location of telecommunications equipment operated by EE Ltd and Hutchison 3G UK Ltd on an area of open space on Peel Brow, Ramsbottom. The telecommunications equipment was installed to replace existing equipment located on a chimney of industrial premises located on Kenyon Street that was scheduled for demolition.

2. At the time, WHP Telecom Ltd (WHP) acting for the operators were negotiating with Ramsbottom Cricket Club to locate a permanent telecoms installation near their ground. The Council were subsequently informed by WHP that negotiations between them and the Club had broken down and as a consequence, WHP made a request to the Council that an area of land next to the temporary mast be considered as a permanent location for the telecommunications equipment.

3. WHP have asked that the Council grant their clients a lease of the land for a term of ten years. It should be noted that the telecoms operators will have rights to renew the lease.

4. In October 2020 WHP submitted an application for Prior Approval to the Planning department for the proposed permanent installation of the mast on the land at Peel Brow and this was granted in December 2020.

5. As the proposed location of the equipment is on land that is public open space, the Council advertised its possible disposal in the Bury Times on 4 and 11 March.

6. Four objections were received to the proposed disposal and so Cabinet is now asked to consider those objections and decide whether to agree to the disposal of the land via the grant of a lease to the telecoms operators.

Recommendation(s)

That Cabinet approve the grant of a lease to the telecoms operators.

Reasons for recommendation(s) 7. The lease of the site will maintain the provision of existing mobile telecommunications for the area and provide a site that will enable the rollout of technologies such as 5G to improve digital connectivity for the area.

8. It should be noted that the agreement with EE Ltd and Hutchison 3G UK Ltd would be subject to the Electronic Communications Code. The Code was created by Schedule 2 of the Telecommunications Act 1984. Electronic communication services are now classed as essential services – this includes landlines, mobile phones and internet services. To allow these services to be provided where they are needed, the Electronic Communications Code provides a statutory basis whereby communications providers can place their apparatus on land or buildings owned by another person or organisation, which includes land owned by Councils.

Alternative options considered and rejected

9. Refuse the request from the telecoms operators for a lease of the land.

Refusing the request could threaten the provision of the mobile telecommunications service to the area if an alternative location cannot be found.

Refusal could also result in the operators exercising powers enjoyed under the Electronic Communications Code which include the ability to apply to the Upper Tribunal (Land Chamber) seeking the imposition of the agreement. Further information on the Electronic Communications Code is provided in section 5, ‘Background’.

10. Ask the telecoms operators to look for an alternative area of land on which to locate the telecommunications equipment.

This was discussed with WHP however we are informed that the Council’s land at Peel Brow is the preferred location for the siting of the equipment.

_________________________________________________________ Report Author and Contact Details: Name: Paul Aungier Position: Principal Surveyor Department: Business Growth and Infrastructure E-mail: [email protected]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Peel Brow site planAppendix 1 4.7 MB Download
PDF
ObjectionsAppendix 2 459 KB Withheld: personal details
PDF
Request from Telecoms Operators to site Telecommunications on Council owned land (Public Open Space) at Peel Brow, RamsbottomDecisions 321 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 19 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, present
RG
Councillor Richard GoldCommittee Member, apologies
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
AS
Councillor Andrea SimpsonCommittee Member, apologies
TT
Councillor Tamoor TariqCommittee Member, present
TR
Councillor Tahir RafiqCommittee Member, present
GL
Geoff LittleChief Executive, in attendance
SE
Sam EvansOfficer, in attendance
JD
Jacqui DennisOfficer, in attendance
PB
Philippa BraithwaiteOfficer, in attendance

All 19 on the meeting page

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies